Skip to content
GharKundli

1 OSR

by Shagun Builders · Dadar, MumbaiAlso near Mahim, Matunga West, Dharavi

Possession: 1 OSR is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900014754. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about 1 OSR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 1 OSR has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 29 March 2024

    Extended at the builder's request (MahaRERA application EXT51900013981)

    Reason the builder gave MahaRERA: “We have received approval on 21 st october 2022 and thefefore we need further extension”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900019410)

    Reason the builder gave MahaRERA: “Hello Sir/Madam, The project is almost completed, and we are expecting OC in next 2-3 months hence need extension.”
  4. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT51900024199)

    Reason the builder gave MahaRERA: “Dear Sir/Madam, OC applied, pending for MHADA NOC. Requesting you to kindly allow us extension of 3 months to complete the compliance with OC.”

Source: 1 OSR’s extension records on MahaRERA (P51900014754), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 1 OSR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the September 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900014754
Status
Completed
Builder
Shagun Builders
Location
Dadar, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
2 Jan 2018
Completion date at registration
March 2023
Latest completion date
September 2024
Delay so far
18 months
Homes
33
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of 1 OSR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
1 OSR100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 1 OSR every month.

1 OSR: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 1 OSR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

1 OSR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 1 OSR

What is the possession date of 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 1 OSR in Dadar, Mumbai is 30 September 2024 — 18 months later than 30 March 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 1 OSR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 1 OSR's builder has filed on MahaRERA, the official one, is 30 September 2024, already 18 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 1 OSR extended?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR's builder applied to MahaRERA to extend the completion date 3 times: to 29 March 2024, giving the reason "We have received approval on 21 st october 2022 and thefefore we need further extension"; to 30 June 2024, giving the reason "Hello Sir/Madam, The project is almost completed, and we are expecting OC in next 2-3 months hence need extension."; to 30 September 2024, giving the reason "Dear Sir/Madam, OC applied, pending for MHADA NOC. Requesting you to kindly allow us extension of 3 months to complete the compliance with OC.".

What is the RERA number of 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 1 OSR in Dadar, Mumbai is P51900014754.

Is 1 OSR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR is registered as P51900014754 and its status is "Completed".

What is the construction status of 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR's status on MahaRERA is "Completed". As filed by the builder, slab work on 1 OSR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does 1 OSR have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 1 OSR safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR is registered on MahaRERA as P51900014754, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 1 OSR's possession date changes?

The latest dates are on 1 OSR's MahaRERA page (P51900014754). GharKundli's Kundli Watch sends a free WhatsApp update on 1 OSR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 1 OSR have?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR has one building filed: 1 OSR with 23 floors.

How big is the land of 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR stands on 816 sq m of land (about 0.2 acres).

Where can I read reviews of 1 OSR?

Google Maps has reviews of 1 OSR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 1 OSR?

1 OSR by Shagun Builders is in Dadar, Mumbai (pincode 400016), near Mahim, Matunga West, Dharavi, Maharashtra, and is registered on MahaRERA as P51900014754, per GharKundli's check of MahaRERA records.

How many homes are in 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR has 33 homes in 1 tower registered on MahaRERA.

When was 1 OSR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 1 OSR was registered on MahaRERA on 2 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on 1 OSR?

No court cases are listed for 1 OSR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of 1 OSR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shagun Builders.

Other projects in Dadar

All 83 projects in Mahim (400016) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.