63 ELEGANCE

by SIDDHARTH DEVELOPERS · Dadar, MumbaiAlso near Matunga, Shivaji Park, Kalanagar, Bandra East

Possession date of 63 ELEGANCE: 30 June 2026, moved from 30 December 2022 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009011. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about 63 ELEGANCE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 63 ELEGANCE has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800010616)

    Reason the builder gave MahaRERA: “We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P51800009011. Form-5 for F.Y 2021-22 is uploaded in others as Specific tab is not available and similar for Form 2A for FY 2021-22”
  3. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800024394)

    Reason the builder gave MahaRERA: “ABC”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA11102518091)

    Reason the builder gave MahaRERA:
    “There are still substantial construction and finishing activities pending. Delays have occurred due to:Post-COVID market slowdown, Misinterpretation in financial planning, Dependency on multiple departments for approvals as the project fall…” Read the full reason“There are still substantial construction and finishing activities pending. Delays have occurred due to:Post-COVID market slowdown, Misinterpretation in financial planning, Dependency on multiple departments for approvals as the project falls under Dadar area, specifically: BMC Estate, MHADA, Building Proposal Department The major delay was caused due to prolonged approval timelines from BMC Estate, which had a cascading effect on overall compliance and progress. We are optimistic that, once the extension is granted, We will be able to generate new sales, Recover dues from existing allottees…”

Source: 63 ELEGANCE’s extension records on MahaRERA (P51800009011), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 63 ELEGANCE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009011
Status
Lapsed (registration period ended)
Builder
SIDDHARTH DEVELOPERS
Location
Dadar, Mumbai · 400014
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2022
Latest completion date
June 2026
Delay so far
42 months
Homes
18
Sold or booked
33%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of 63 ELEGANCE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
63 ELEGANCE100%100%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • 63 ELEGANCE: covers Stilt + 19

Latest CC order on MahaRERA: dated 30/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 63 ELEGANCE every month.

63 ELEGANCE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK8309
2 BHK630 – 6598
1 BHK4441

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 63 ELEGANCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

63 ELEGANCE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 63 ELEGANCE

What is the possession date of 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 63 ELEGANCE in Dadar, Mumbai is 30 June 2026 — 42 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for 63 ELEGANCE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 63 ELEGANCE's builder has filed on MahaRERA, the official one, is 30 June 2026, already 42 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 63 ELEGANCE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2023, giving the reason "We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P51800009011. Form-5 for F.Y 2021-22 is uploaded in others as Specific tab is not available and similar for Form 2A for FY 2021-22"; to 31 March 2025, giving the reason "ABC"; to 30 June 2026, giving the reason "There are still substantial construction and finishing activities pending. Delays have occurred due to:Post-COVID market slowdown, Misinterpretation in financial planning, Dependency on multiple departments for approvals as the project falls under Dadar area, specifically: BMC Estate, MHADA, Building Proposal Department The major delay was caused due to prolonged approval timelines from BMC Estate, which had a cascading effect on overall compliance and progress. We are optimistic that, once the extension is granted, We will be able to generate new sales, Recover dues from existing allottees…".

What is the RERA number of 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 63 ELEGANCE in Dadar, Mumbai is P51800009011.

Is 63 ELEGANCE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE is registered as P51800009011 and its status is "Lapsed (registration period ended)".

What is the construction status of 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on 63 ELEGANCE is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does 63 ELEGANCE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is 63 ELEGANCE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE is registered on MahaRERA as P51800009011, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 63 ELEGANCE's possession date changes?

The latest dates are on 63 ELEGANCE's MahaRERA page (P51800009011). GharKundli's Kundli Watch sends a free WhatsApp update on 63 ELEGANCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 63 ELEGANCE have?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE has one building filed: 63 ELEGANCE with 20 floors and 18 units.

What are the flat sizes (carpet area) in 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 63 ELEGANCE: 3 BHK: 830 sq ft carpet (9 homes); 2 BHK: 630 to 659 sq ft carpet (8 homes); 1 BHK: 444 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does 63 ELEGANCE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for 63 ELEGANCE.

How big is the land of 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE stands on 345 sq m of land (about 0.1 acres), with 1,378 sq m of sanctioned built-up area.

Where can I read reviews of 63 ELEGANCE?

Google Maps has reviews of 63 ELEGANCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 63 ELEGANCE?

63 ELEGANCE by SIDDHARTH DEVELOPERS is in Dadar, Mumbai (pincode 400014), near Matunga, Shivaji Park, Kalanagar, Bandra East, Maharashtra, and is registered on MahaRERA as P51800009011, per GharKundli's check of MahaRERA records.

How many homes are in 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE has 18 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was 63 ELEGANCE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 63 ELEGANCE was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 63 ELEGANCE?

No court cases are listed for 63 ELEGANCE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of 63 ELEGANCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHARTH DEVELOPERS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai City →

Other projects in pincode 400014

All 61 projects in Dadar (400014) →

Other projects by SIDDHARTH DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.