Siddharth Enclave
by Siddharth Developers · Lower Parel, MumbaiAlso near Worli, Kalanagar, Bandra East, Lalbaug
Possession date of Siddharth Enclave: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900001979, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Siddharth Enclave?
How the possession date of Siddharth Enclave has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51900003858)
Reason the builder gave MahaRERA:
“The promoter states that Phase I of the Building i.e. Siddharth Enclave is almost completed as per current approved plan. Phase II consist of additional 2 floors on sale building and the same will be sanctioned by the MCGM upon available of…” Read the full reason
“The promoter states that Phase I of the Building i.e. Siddharth Enclave is almost completed as per current approved plan. Phase II consist of additional 2 floors on sale building and the same will be sanctioned by the MCGM upon available of 9 mtrs. access road. The Promoter has already obtained requisite consent from the prospective purchasers. The Promoter further states that One of the I.O.D. condition is that 9.00 mtr. wide access road is required and the same is the condition for issuance of CFO NOC. Once the CFO NOC is issued then only we can apply for Occupation Certificate. In view t…”31 December 2022
Extended at the builder's request (MahaRERA application EXT51900010458)
Reason the builder gave MahaRERA:
“Due to failure of handing over the road set back area by adjoining property having C.S. No. 211 and 212, the C.F.O. NOC is not being issued in terms of compulsory 9 meter R.L. Road which is at present 6 meter. we have sold 57 flats out of 6…” Read the full reason
“Due to failure of handing over the road set back area by adjoining property having C.S. No. 211 and 212, the C.F.O. NOC is not being issued in terms of compulsory 9 meter R.L. Road which is at present 6 meter. we have sold 57 flats out of 68 flats and taken consent of 38 flats i.e. 67%. kindly issue the extension certificate.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51900016976)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 72.13% allottees for purpose of extension of RERA registration period of the said project”31 December 2026
Extended at the builder's request (MahaRERA application EA30082502478)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Siddharth Enclave’s extension records on MahaRERA (P51900001979), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Siddharth Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001979
- Status
- Registered and active
- Builder
- Siddharth Developers
- Location
- Lower Parel, Mumbai · 400013
- Project type
- Residential / Group Housing
- Registered on
- 31 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 94%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Siddharth Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B Wing | 100% | 100% | 95% | 90% |
| C Wing | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- B Wing: covers 12 floors
- C Wing: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siddharth Enclave every month.
Siddharth Enclave: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 337 – 366 | 62 |
| 2 BHK | 525 | 6 |
- Buildings: B Wing (16 floors, 58 units) · C Wing (10 floors, 10 units)
- Land: 2,322 sq m (about 0.6 acres) · sanctioned built-up 7,132 sq m · recreational space 192 sq m
- Boundaries filed include: western railway line
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shri Nakoda Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 52 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Siddharth Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Siddharth Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Siddharth Enclave
What is the possession date of Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siddharth Enclave in Lower Parel, Mumbai is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Siddharth Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Siddharth Enclave's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Siddharth Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2020, giving the reason "The promoter states that Phase I of the Building i.e. Siddharth Enclave is almost completed as per current approved plan. Phase II consist of additional 2 floors on sale building and the same will be sanctioned by the MCGM upon available of 9 mtrs. access road. The Promoter has already obtained requisite consent from the prospective purchasers. The Promoter further states that One of the I.O.D. condition is that 9.00 mtr. wide access road is required and the same is the condition for issuance of CFO NOC. Once the CFO NOC is issued then only we can apply for Occupation Certificate. In view t…"; to 31 December 2022, giving the reason "Due to failure of handing over the road set back area by adjoining property having C.S. No. 211 and 212, the C.F.O. NOC is not being issued in terms of compulsory 9 meter R.L. Road which is at present 6 meter. we have sold 57 flats out of 68 flats and taken consent of 38 flats i.e. 67%. kindly issue the extension certificate."; to 30 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 72.13% allottees for purpose of extension of RERA registration period of the said project"; to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Siddharth Enclave in Lower Parel, Mumbai is P51900001979.
Is Siddharth Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave is registered as P51900001979 and its status is "Registered and active".
What is the construction status of Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Siddharth Enclave have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Siddharth Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave is registered on MahaRERA as P51900001979, its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Siddharth Enclave's possession date changes?
The latest dates are on Siddharth Enclave's MahaRERA page (P51900001979). GharKundli's Kundli Watch sends a free WhatsApp update on Siddharth Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Siddharth Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave has 2 buildings filed: B Wing with 16 floors and 58 units; C Wing with 10 floors and 10 units.
What are the flat sizes (carpet area) in Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Siddharth Enclave: 1 BHK: 337 to 366 sq ft carpet (62 homes); 2 BHK: 525 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave stands on 2,322 sq m of land (about 0.6 acres), with 7,132 sq m of sanctioned built-up area and 192 sq m of recreational open space.
What is the track record of Siddharth Enclave's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shri Nakoda Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 52 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Siddharth Enclave?
Google Maps has reviews of Siddharth Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Siddharth Enclave?
Siddharth Enclave by Siddharth Developers is in Lower Parel, Mumbai (pincode 400013), near Worli, Kalanagar, Bandra East, Lalbaug, Maharashtra, and is registered on MahaRERA as P51900001979, per GharKundli's check of MahaRERA records. Its boundaries filed there include western railway line.
How many homes are in Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave has 68 homes in 2 towers registered on MahaRERA, and 94% of them are sold or booked.
When was Siddharth Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siddharth Enclave was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Siddharth Enclave?
No court cases are listed for Siddharth Enclave on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Siddharth Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Siddharth Developers, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Siddharth Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Lower Parel
- PLUS ART
- Raheja Imperia II
- Sumer Samaq Prime
- 7 Mahalaxmi - Tower 3
- Birla Niyaara Phase-1
- SILA TOWER
- Anant Serene Villas II
- RUNWAL RAAYA - TOWER 2
Other projects by Siddharth Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.