Sumer Samaq Prime
by Samaq Builders Private Limited · Lower Parel, MumbaiAlso near Kalanagar, Bandra East, Worli, Lalbaug
Possession date of Sumer Samaq Prime: 31 December 2027, moved from 31 January 2023 (59 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900022219, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sumer Samaq Prime?
How the possession date of Sumer Samaq Prime has moved
31 January 2023
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51900008911)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.”30 June 2026
Extended at the builder's request (MahaRERA application EXT51900024139)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 69.23% allottees for purpose of extension of RERA registration period of the said project.”31 December 2027
Extended at the builder's request (MahaRERA application EA04062621240)
Reason the builder gave MahaRERA:
“The delay in the completion of the project has primarily occurred due to a government-mandated design modification by the High-Rise Committee of the Brihanmumbai Municipal Corporation (BMC), which directed a complete structural overhaul of…” Read the full reason
“The delay in the completion of the project has primarily occurred due to a government-mandated design modification by the High-Rise Committee of the Brihanmumbai Municipal Corporation (BMC), which directed a complete structural overhaul of the Parking Tower from a Mild Steel (MS) structure to a Reinforced Cement Concrete (RCC) structure. This regulatory directive initiated an extensive engineering iteration and administrative approval process starting in January 2025, which consumed approximately 10 months in the statutory pipeline before the Further Commencement Certificate was ultimately…”
Source: Sumer Samaq Prime’s extension records on MahaRERA (P51900022219), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sumer Samaq Prime
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900022219
- Status
- Registered and active
- Builder
- Samaq Builders Private Limited
- Location
- Lower Parel, Mumbai · 400013
- Project type
- Residential / Group Housing
- Registered on
- 5 Sep 2019
- Completion date at registration
- January 2023
- Latest completion date
- December 2027
- Delay so far
- 59 months
- Homes
- 65
- Sold or booked
- 77%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sumer Samaq Prime, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sumer samaq Prime Sale Building | 100% | 85% | 90% | 50% |
| Rehab Building | 100% | 85% | 90% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Sumer samaq Prime Sale Building: covers 24 floors
Latest CC order on MahaRERA: dated 03/09/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sumer Samaq Prime every month.
Sumer Samaq Prime: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Unspecified | — | 198 |
| 2 BHK | 439 – 533 | 64 |
| 1 BHK | 332 | 1 |
- Buildings: Sumer samaq Prime Sale Building (24 floors, 65 units)
- Land: 1,008 sq m (about 0.2 acres) · sanctioned built-up 5,842 sq m
- Boundaries filed include: N M Joshi Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects.
Read Google reviews of Sumer Samaq Prime →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sumer Samaq Prime: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sumer Samaq Prime
What is the possession date of Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sumer Samaq Prime in Lower Parel, Mumbai is 31 December 2027 — 59 months later than 31 January 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sumer Samaq Prime?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sumer Samaq Prime's builder has filed on MahaRERA, the official one, is 31 December 2027, already 59 months later than the 31 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sumer Samaq Prime extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2023, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry."; to 30 June 2026, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 69.23% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2027, giving the reason "The delay in the completion of the project has primarily occurred due to a government-mandated design modification by the High-Rise Committee of the Brihanmumbai Municipal Corporation (BMC), which directed a complete structural overhaul of the Parking Tower from a Mild Steel (MS) structure to a Reinforced Cement Concrete (RCC) structure. This regulatory directive initiated an extensive engineering iteration and administrative approval process starting in January 2025, which consumed approximately 10 months in the statutory pipeline before the Further Commencement Certificate was ultimately…".
What is the RERA number of Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sumer Samaq Prime in Lower Parel, Mumbai is P51900022219.
Is Sumer Samaq Prime registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime is registered as P51900022219 and its status is "Registered and active".
What is the construction status of Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 85% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Sumer Samaq Prime have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sumer Samaq Prime safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime is registered on MahaRERA as P51900022219, its completion date has moved 59 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sumer Samaq Prime's possession date changes?
The latest dates are on Sumer Samaq Prime's MahaRERA page (P51900022219). GharKundli's Kundli Watch sends a free WhatsApp update on Sumer Samaq Prime every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sumer Samaq Prime have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime has one building filed: Sumer samaq Prime Sale Building with 24 floors and 65 units.
What are the flat sizes (carpet area) in Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sumer Samaq Prime: 2 BHK: 439 to 533 sq ft carpet (64 homes); 1 BHK: 332 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime stands on 1,008 sq m of land (about 0.2 acres), with 5,842 sq m of sanctioned built-up area.
What is the track record of Sumer Samaq Prime's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sumer Samaq Prime?
Google Maps has reviews of Sumer Samaq Prime written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sumer Samaq Prime?
Sumer Samaq Prime by Samaq Builders Private Limited is in Lower Parel, Mumbai (pincode 400013), near Kalanagar, Bandra East, Worli, Lalbaug, Maharashtra, and is registered on MahaRERA as P51900022219, per GharKundli's check of MahaRERA records. Its boundaries filed there include N M Joshi Marg.
How many homes are in Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime has 65 homes in 2 towers registered on MahaRERA, and 77% of them are sold or booked.
When was Sumer Samaq Prime registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Samaq Prime was registered on MahaRERA on 5 September 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Sumer Samaq Prime?
No court cases are listed for Sumer Samaq Prime on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sumer Samaq Prime?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Samaq Builders Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Sumer Samaq Prime
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Lower Parel
- PLUS ART
- Siddharth Enclave
- Raheja Imperia II
- 7 Mahalaxmi - Tower 3
- Birla Niyaara Phase-1
- SILA TOWER
- Anant Serene Villas II
- RUNWAL RAAYA - TOWER 2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.