Birla Niyaara Phase-1
by Aditya Birla Real Estate Limited · Lower Parel, MumbaiAlso near Worli, Prabhadevi, Kalanagar, Bandra East
Possession date of Birla Niyaara Phase-1: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900031916, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Birla Niyaara Phase-1?
How the possession date of Birla Niyaara Phase-1 has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Birla Niyaara Phase-1’s extension records on MahaRERA (P51900031916), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Birla Niyaara Phase-1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Birla Niyaara Phase-2P51900054455 · possession 31 Jul 2029
- MahaRERA registration
- P51900031916
- Status
- Registered and active
- Builder
- Aditya Birla Real Estate Limited
- Location
- Lower Parel, Mumbai · 400030
- Project type
- Residential / Group Housing
- Registered on
- 22 Nov 2021
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 414
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Birla Niyaara Phase-1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower A | 100% | 100% | 40% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Tower A: covers 81 floors
Latest CC order on MahaRERA: dated 18/02/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Birla Niyaara Phase-1 every month.
Birla Niyaara Phase-1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 117 – 1,841 | 172 |
| 2 BHK | 849 – 1,204 | 170 |
| 4 BHK | 1,864 – 2,167 | 33 |
| 5 BHK | 2,167 – 4,062 | 26 |
| Other | 4,149 – 11,914 | 7 |
| 6 BHK | 3,744 | 5 |
| 1 BHK | 819 | 1 |
- Buildings: Tower A (81 floors, 414 units)
- Car parking: 851 covered, 4 open
- Land: 1,373 sq m (about 0.3 acres) · sanctioned built-up 63,486 sq m
- Boundaries filed include: Pandurang Budhkar Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Century Textiles & Industries has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet. 9 complaints on MahaRERA across 3 projects.
Read Google reviews of Birla Niyaara Phase-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Birla Niyaara Phase-1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Birla Niyaara Phase-1
What is the possession date of Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Birla Niyaara Phase-1 in Lower Parel, Mumbai is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Birla Niyaara Phase-1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Birla Niyaara Phase-1's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Birla Niyaara Phase-1 in Lower Parel, Mumbai is P51900031916.
Is Birla Niyaara Phase-1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 is registered as P51900031916 and its status is "Registered and active".
What is the construction status of Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tower A is 100% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does Birla Niyaara Phase-1 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Birla Niyaara Phase-1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 is registered on MahaRERA as P51900031916, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Birla Niyaara Phase-1 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Birla Niyaara Phase-2 (P51900054455, possession 31 Jul 2029). Check that your agreement names the registration of your own wing.
How can I get updates if Birla Niyaara Phase-1's possession date changes?
The latest dates are on Birla Niyaara Phase-1's MahaRERA page (P51900031916). GharKundli's Kundli Watch sends a free WhatsApp update on Birla Niyaara Phase-1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Birla Niyaara Phase-1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 has one building filed: Tower A with 81 floors and 414 units.
What are the flat sizes (carpet area) in Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Birla Niyaara Phase-1: 3 BHK: 117 to 1841 sq ft carpet (172 homes); 2 BHK: 849 to 1204 sq ft carpet (170 homes); 4 BHK: 1864 to 2167 sq ft carpet (33 homes); 5 BHK: 2167 to 4062 sq ft carpet (26 homes); Other: 4149 to 11914 sq ft carpet (7 homes); 6 BHK: 3744 sq ft carpet (5 homes); 1 BHK: 819 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Birla Niyaara Phase-1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 851 covered and 4 open car parking spaces for Birla Niyaara Phase-1.
How big is the land of Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 stands on 1,373 sq m of land (about 0.3 acres), with 63,486 sq m of sanctioned built-up area.
What is the track record of Birla Niyaara Phase-1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Century Textiles & Industries has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet. 9 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Birla Niyaara Phase-1?
Google Maps has reviews of Birla Niyaara Phase-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Birla Niyaara Phase-1?
Birla Niyaara Phase-1 by Aditya Birla Real Estate Limited is in Lower Parel, Mumbai (pincode 400030), near Worli, Prabhadevi, Kalanagar, Bandra East, Maharashtra, and is registered on MahaRERA as P51900031916, per GharKundli's check of MahaRERA records. Its boundaries filed there include Pandurang Budhkar Marg.
How many homes are in Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 has 414 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was Birla Niyaara Phase-1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Niyaara Phase-1 was registered on MahaRERA on 22 November 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Birla Niyaara Phase-1?
No court cases are listed for Birla Niyaara Phase-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Birla Niyaara Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aditya Birla Real Estate Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Birla Niyaara Phase-1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in Lower Parel
- PLUS ART
- Siddharth Enclave
- Raheja Imperia II
- Sumer Samaq Prime
- 7 Mahalaxmi - Tower 3
- SILA TOWER
- Anant Serene Villas II
- RUNWAL RAAYA - TOWER 2
Other projects by Aditya Birla Real Estate Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.