EL MEJOR
by ARTH REALTECH SPACES PVT LTD · Dadar, MumbaiAlso near Matunga, Wadala west, Kalanagar, Bandra East
Possession date of EL MEJOR: 31 December 2026, moved from 30 March 2021 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900004688, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about EL MEJOR?
How the possession date of EL MEJOR has moved
30 March 2021
Completion date given when the project was registered
30 March 2022
Extended at the builder's request (MahaRERA application EXT51900009500)
Reason the builder gave MahaRERA: “Due to COVID, Construction was stopped.”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51900012241)
Reason the builder gave MahaRERA: “Project taken over by Arth Realtech Spaces Pvt Ltd from DVK Realestate Pvt Ltd as on 10th May 2022 hence require an extension for completion of the project”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900027334)
Reason the builder gave MahaRERA:
“a) As the entire country including Mumbai were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spr…” Read the full reason
“a) As the entire country including Mumbai were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still f…”31 December 2026
Extended at the builder's request (MahaRERA application EA27122519054)
Reason the builder gave MahaRERA:
“a) The construction of project is completed and only finishing work is in process. We have obtained part occupancy certificate for Ground Floor (NR) + 1st Floor (NR) + 2nd to 7th + 8th to 21st upper floors (pt.) including LMR / OHT for Reha…” Read the full reason
“a) The construction of project is completed and only finishing work is in process. We have obtained part occupancy certificate for Ground Floor (NR) + 1st Floor (NR) + 2nd to 7th + 8th to 21st upper floors (pt.) including LMR / OHT for Rehab component of PAP and corresponding sale thereon under Regn.33(12)(B) and for rehab component of existing cess tenants under Regn.33(7). b) The subject project is being developed under the provisions of Development Control and Promotion Regulations (DCPR) 2034, specifically Regulation 33(7) and Regulation 33(12)(B). While construction work pertaining to…”
Source: EL MEJOR’s extension records on MahaRERA (P51900004688), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EL MEJOR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004688
- Status
- Registered and active
- Builder
- ARTH REALTECH SPACES PVT LTD
- Location
- Dadar, Mumbai · 400014
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- March 2021
- Latest completion date
- December 2026
- Delay so far
- 69 months
- Homes
- 109
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of EL MEJOR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| EL MEJOR | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- EL MEJOR: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EL MEJOR every month.
EL MEJOR: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 424 – 1,378 | 82 |
| 3 BHK | 906 – 1,771 | 22 |
| Shops | 447 – 1,355 | 6 |
| 4 BHK | 381 – 1,541 | 4 |
| 1 BHK | 429 | 1 |
- Buildings: EL MEJOR (23 floors, 115 units)
- Car parking: 84 covered
- Land: 1,684 sq m (about 0.4 acres) · sanctioned built-up 5,854 sq m · recreational space 134 sq m
- Boundaries filed include: AMBEDKAR ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Arth Realtech Spaces has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 61 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of EL MEJOR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EL MEJOR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EL MEJOR
What is the possession date of EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EL MEJOR in Dadar, Mumbai is 31 December 2026 — 69 months later than 30 March 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EL MEJOR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EL MEJOR's builder has filed on MahaRERA, the official one, is 31 December 2026, already 69 months later than the 30 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EL MEJOR extended?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2022, giving the reason "Due to COVID, Construction was stopped."; to 31 December 2024, giving the reason "Project taken over by Arth Realtech Spaces Pvt Ltd from DVK Realestate Pvt Ltd as on 10th May 2022 hence require an extension for completion of the project"; to 31 December 2025, giving the reason "a) As the entire country including Mumbai were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still f…"; to 31 December 2026, giving the reason "a) The construction of project is completed and only finishing work is in process. We have obtained part occupancy certificate for Ground Floor (NR) + 1st Floor (NR) + 2nd to 7th + 8th to 21st upper floors (pt.) including LMR / OHT for Rehab component of PAP and corresponding sale thereon under Regn.33(12)(B) and for rehab component of existing cess tenants under Regn.33(7). b) The subject project is being developed under the provisions of Development Control and Promotion Regulations (DCPR) 2034, specifically Regulation 33(7) and Regulation 33(12)(B). While construction work pertaining to…".
What is the RERA number of EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EL MEJOR in Dadar, Mumbai is P51900004688.
Is EL MEJOR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR is registered as P51900004688 and its status is "Registered and active".
What is the construction status of EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR's status on MahaRERA is "Registered and active". As filed by the builder, slab work on EL MEJOR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does EL MEJOR have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is EL MEJOR safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR is registered on MahaRERA as P51900004688, its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EL MEJOR's possession date changes?
The latest dates are on EL MEJOR's MahaRERA page (P51900004688). GharKundli's Kundli Watch sends a free WhatsApp update on EL MEJOR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EL MEJOR have?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR has one building filed: EL MEJOR with 23 floors and 115 units.
What are the flat sizes (carpet area) in EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for EL MEJOR: 2 BHK: 424 to 1378 sq ft carpet (82 homes); 3 BHK: 906 to 1771 sq ft carpet (22 homes); 4 BHK: 381 to 1541 sq ft carpet (4 homes); 1 BHK: 429 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does EL MEJOR have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 84 covered car parking spaces for EL MEJOR.
How big is the land of EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR stands on 1,684 sq m of land (about 0.4 acres), with 5,854 sq m of sanctioned built-up area and 134 sq m of recreational open space.
What is the track record of EL MEJOR's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Arth Realtech Spaces has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 61 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EL MEJOR?
Google Maps has reviews of EL MEJOR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EL MEJOR?
EL MEJOR by ARTH REALTECH SPACES PVT LTD is in Dadar, Mumbai (pincode 400014), near Matunga, Wadala west, Kalanagar, Bandra East, Maharashtra, and is registered on MahaRERA as P51900004688, per GharKundli's check of MahaRERA records. Its boundaries filed there include AMBEDKAR ROAD.
How many homes are in EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR has 109 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was EL MEJOR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EL MEJOR was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EL MEJOR?
No court cases are listed for EL MEJOR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of EL MEJOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARTH REALTECH SPACES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of EL MEJOR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in pincode 400014
- PANCHRATNA-NX
- SOM NIWAS
- NINE REFLEX
- CHIRAG HEIGHTS
- Ratan Infinia
- SHREEJI SERENITY
- NAJAMAI MANSION
- 63 ELEGANCE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.