Shreeji One Divine
by DIVINE GANESHA ESTATE LLP · Mahim, Mumbai 400016Also near Matunga West, Dadar West, Dharavi
What’s in the report? →Possession date of Shreeji One Divine (MahaRERA PR1180002601193): 17 June 2029. It has 17 homes (1 BHK, 1 Room Kitchen and 2 BHK, 236–903 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002601193, and currently active. Its completion date is now June 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002601193, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shreeji One Divine?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shreeji One Divine has moved
17 February 2029
Completion date given when the project was registered
17 June 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shreeji One Divine’s extension records on MahaRERA (PR1180002601193), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreeji One Divine
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002601193
- Status
- Registered and active
- Builder
- DIVINE GANESHA ESTATE LLP
- Location
- Mahim, Mumbai · 400016
- Project type
- Residential / Group Housing
- Registered on
- 16 Jul 2026
- Completion date at registration
- February 2029
- Latest completion date
- June 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 17
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shreeji One Divine, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shreeji One Divine | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Shreeji One Divine: covers 14 floors
Latest CC order on MahaRERA: dated 29/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreeji One Divine every 1–2 months.
Shreeji One Divine: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 663 – 903 | 8 |
| 1 BHK | 426 – 482 | 7 |
| 1 Room Kitchen | 236 | 1 |
| 3 BHK | 844 | 1 |
- Buildings: Shreeji One Divine (14 floors, 17 units)
- Car parking: 54 covered
- Land: 453 sq m (about 0.1 acres) · sanctioned built-up 1,097 sq m
- Boundaries filed include: 12.58mtr Old Prabhadevi Road
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreeji One Divine →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreeji One Divine: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shreeji One Divine
What is the possession date of Shreeji One Divine?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreeji One Divine in Mahim, Mumbai is 17 June 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shreeji One Divine?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreeji One Divine's builder has filed on MahaRERA, the official one, is 17 June 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shreeji One Divine?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreeji One Divine in Mahim, Mumbai is PR1180002601193.
Is Shreeji One Divine registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine is registered as PR1180002601193 and its status is "Registered and active".
What is the current construction status of Shreeji One Divine? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shreeji One Divine is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Shreeji One Divine have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shreeji One Divine safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine is registered on MahaRERA as PR1180002601193, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shreeji One Divine?
Shreeji One Divine is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shreeji One Divine are 236 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shreeji One Divine?
For a flat in Shreeji One Divine (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shreeji One Divine received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine is still under construction, with 17 June 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Shreeji One Divine a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Shreeji One Divine uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreeji One Divine was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shreeji One Divine's possession date changes?
The latest dates are on Shreeji One Divine's MahaRERA page (PR1180002601193). GharKundli's Kundli Watch sends a free WhatsApp update on Shreeji One Divine every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreeji One Divine have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine has one building filed: Shreeji One Divine with 14 floors and 17 units.
What are the flat sizes (carpet area) in Shreeji One Divine?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shreeji One Divine: 2 BHK: 663 to 903 sq ft carpet (8 homes); 1 BHK: 426 to 482 sq ft carpet (7 homes); 1 Room Kitchen: 236 sq ft carpet (1 homes); 3 BHK: 844 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shreeji One Divine have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 54 covered car parking spaces for Shreeji One Divine.
How big is the land of Shreeji One Divine?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine stands on 453 sq m of land (about 0.1 acres), with 1,097 sq m of sanctioned built-up area.
What are the reviews of Shreeji One Divine?
Google Maps has reviews of Shreeji One Divine written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shreeji One Divine?
Shreeji One Divine by DIVINE GANESHA ESTATE LLP is in Mahim, Mumbai, pincode 400016 (near Matunga West, Dadar West, Dharavi), Maharashtra, and is registered on MahaRERA as PR1180002601193, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12.58mtr Old Prabhadevi Road. GharKundli lists all 84 MahaRERA projects in Mahim (400016).
How many flats are in Shreeji One Divine, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine has 17 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Shreeji One Divine registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji One Divine was registered on MahaRERA on 16 July 2026. GharKundli did not find a title report on the land on file there.
Does Shreeji One Divine have any legal issues or court cases?
No court cases are listed for Shreeji One Divine on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shreeji One Divine?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DIVINE GANESHA ESTATE LLP.
Check it yourself on MahaRERA
- How to check the possession date of Shreeji One Divine
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai City →
Other projects in Mahim (400016)
All 84 projects in Mahim (400016) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.