Skip to content
GharKundli

MORAJ OPULENCE

by MORAJ AHN DEVELOPERS LLP · Mahim, MumbaiAlso near Dharavi, Matunga, Bhawani Shankar

Possession date of MORAJ OPULENCE: 31 December 2029, moved from 28 December 2026 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900032370, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MORAJ OPULENCE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MORAJ OPULENCE has moved

  1. 28 December 2026

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EXT51900019361)

    Reason the builder gave MahaRERA: “1. Application filed u/s 7(3) 2. Consent of 75% of allottees uploaded in format 3. Seeking extension due to lack of demand in the area 4. Variation in Material prices and labour wages 5. Labour shortage”

Source: MORAJ OPULENCE’s extension records on MahaRERA (P51900032370), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MORAJ OPULENCE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900032370
Status
Registered and active
Builder
MORAJ AHN DEVELOPERS LLP
Location
Mahim, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
29 Dec 2021
Completion date at registration
December 2026
Latest completion date
December 2029
Delay so far
36 months
Homes
44
Sold or booked
48%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of MORAJ OPULENCE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MORAJ OPULENCE100%67%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • MORAJ OPULENCE: covers 28 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MORAJ OPULENCE every month.

MORAJ OPULENCE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,077 – 1,58044
Shops413 – 4652
  • Buildings: MORAJ OPULENCE (28 floors, 46 units)
  • Land: 2,328 sq m (about 0.6 acres) · sanctioned built-up 5,905 sq m · recreational space 196 sq m
  • Boundaries filed include: MUNISUVRAT SWAMI JAIN MANDIR, GOPI TANK ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MORAJ OPULENCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MORAJ OPULENCE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MORAJ OPULENCE

What is the possession date of MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MORAJ OPULENCE in Mahim, Mumbai is 31 December 2029 — 36 months later than 28 December 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MORAJ OPULENCE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MORAJ OPULENCE's builder has filed on MahaRERA, the official one, is 31 December 2029, already 36 months later than the 28 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MORAJ OPULENCE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "1. Application filed u/s 7(3) 2. Consent of 75% of allottees uploaded in format 3. Seeking extension due to lack of demand in the area 4. Variation in Material prices and labour wages 5. Labour shortage".

What is the RERA number of MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MORAJ OPULENCE in Mahim, Mumbai is P51900032370.

Is MORAJ OPULENCE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE is registered as P51900032370 and its status is "Registered and active".

What is the construction status of MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MORAJ OPULENCE is 67% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does MORAJ OPULENCE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MORAJ OPULENCE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE is registered on MahaRERA as P51900032370, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MORAJ OPULENCE's possession date changes?

The latest dates are on MORAJ OPULENCE's MahaRERA page (P51900032370). GharKundli's Kundli Watch sends a free WhatsApp update on MORAJ OPULENCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MORAJ OPULENCE have?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE has one building filed: MORAJ OPULENCE with 28 floors and 46 units.

What are the flat sizes (carpet area) in MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MORAJ OPULENCE: 3 BHK: 1077 to 1580 sq ft carpet (44 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE stands on 2,328 sq m of land (about 0.6 acres), with 5,905 sq m of sanctioned built-up area and 196 sq m of recreational open space.

Where can I read reviews of MORAJ OPULENCE?

Google Maps has reviews of MORAJ OPULENCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MORAJ OPULENCE?

MORAJ OPULENCE by MORAJ AHN DEVELOPERS LLP is in Mahim, Mumbai (pincode 400016), near Dharavi, Matunga, Bhawani Shankar, Maharashtra, and is registered on MahaRERA as P51900032370, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNISUVRAT SWAMI JAIN MANDIR, GOPI TANK ROAD.

How many homes are in MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE has 44 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.

When was MORAJ OPULENCE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MORAJ OPULENCE was registered on MahaRERA on 29 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on MORAJ OPULENCE?

No court cases are listed for MORAJ OPULENCE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MORAJ OPULENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MORAJ AHN DEVELOPERS LLP.

All projects with possession due in 2029 in Mumbai City →

Other projects in pincode 400016

All 83 projects in Mahim (400016) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.