Possession date of Gandhi Amaris Suites (MahaRERA PR1170002502166): 31 July 2029. It has 18 homes (1 BHK, 2 BHK and 3 BHK, 421–2217 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1170002502166, and currently active. Its completion date is now July 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1170002502166, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Gandhi Amaris Suites?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Gandhi Amaris Suites has moved

  1. 31 March 2029

    Completion date given when the project was registered

  2. 31 July 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Gandhi Amaris Suites’s extension records on MahaRERA (PR1170002502166), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gandhi Amaris Suites

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1170002502166
Status
Registered and active
Builder
C.M.GANDHI VENTURES
Location
Matunga, Mumbai · 400019
Project type
Residential / Group Housing
Registered on
23 Jan 2026
Completion date at registration
March 2029
Latest completion date
July 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
18
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Gandhi Amaris Suites, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMARIS SUITES0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • AMARIS SUITES: covers upto Plinth level

Latest CC order on MahaRERA: dated 30/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gandhi Amaris Suites every 1–2 months.

Gandhi Amaris Suites: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK594 – 7384
2 BHK908 – 1,0624
Multi Purpose Room421 – 4254
3 BHK1,227 – 1,6803
4 BHK2,2172
5 BHK2,0921

The builder’s record and reviews

CMG Enterprises (a group of 4 linked companies) has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.

Read Google reviews of Gandhi Amaris Suites →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gandhi Amaris Suites: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Gandhi Amaris Suites

What is the possession date of Gandhi Amaris Suites?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gandhi Amaris Suites in Matunga, Mumbai is 31 July 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Gandhi Amaris Suites?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gandhi Amaris Suites's builder has filed on MahaRERA, the official one, is 31 July 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Gandhi Amaris Suites?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gandhi Amaris Suites in Matunga, Mumbai is PR1170002502166.

Is Gandhi Amaris Suites registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites is registered as PR1170002502166 and its status is "Registered and active".

What is the current construction status of Gandhi Amaris Suites? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AMARIS SUITES is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Gandhi Amaris Suites have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Gandhi Amaris Suites safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites is registered on MahaRERA as PR1170002502166, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Gandhi Amaris Suites?

Gandhi Amaris Suites is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Gandhi Amaris Suites are 421 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Gandhi Amaris Suites?

For a flat in Gandhi Amaris Suites (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Gandhi Amaris Suites received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites is still under construction, with 31 July 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Gandhi Amaris Suites a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Gandhi Amaris Suites uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gandhi Amaris Suites was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Gandhi Amaris Suites's possession date changes?

The latest dates are on Gandhi Amaris Suites's MahaRERA page (PR1170002502166). GharKundli's Kundli Watch sends a free WhatsApp update on Gandhi Amaris Suites every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gandhi Amaris Suites have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites has one building filed: AMARIS SUITES with 16 floors and 18 units.

What are the flat sizes (carpet area) in Gandhi Amaris Suites?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Gandhi Amaris Suites: 1 BHK: 594 to 738 sq ft carpet (4 homes); 2 BHK: 908 to 1062 sq ft carpet (4 homes); Multi Purpose Room: 421 to 425 sq ft carpet (4 homes); 3 BHK: 1227 to 1680 sq ft carpet (3 homes); 4 BHK: 2217 sq ft carpet (2 homes); 5 BHK: 2092 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Gandhi Amaris Suites have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 39 covered car parking spaces for Gandhi Amaris Suites.

How big is the land of Gandhi Amaris Suites?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites stands on 618 sq m of land (about 0.2 acres), with 2,068 sq m of sanctioned built-up area.

What is the track record of Gandhi Amaris Suites's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), CMG Enterprises (a group of 4 linked companies) has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Gandhi Amaris Suites?

Google Maps has reviews of Gandhi Amaris Suites written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Gandhi Amaris Suites?

Gandhi Amaris Suites by C.M.GANDHI VENTURES is in Matunga, Mumbai, pincode 400019 (near Wadala West, Dadar East, Ghatkopar East), Maharashtra, and is registered on MahaRERA as PR1170002502166, per GharKundli's check of MahaRERA records. GharKundli lists all 104 MahaRERA projects in Matunga (400019).

How many flats are in Gandhi Amaris Suites, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites has 18 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Gandhi Amaris Suites registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi Amaris Suites was registered on MahaRERA on 23 January 2026. GharKundli did not find a title report on the land on file there.

Does Gandhi Amaris Suites have any legal issues or court cases?

No court cases are listed for Gandhi Amaris Suites on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Gandhi Amaris Suites?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is C.M.GANDHI VENTURES.

All projects with possession due in 2029 in Mumbai City →

Other projects in Matunga (400019)

All 104 projects in Matunga (400019) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.