Possession date of Island Cove: 30 April 2029, moved from 31 August 2028 (4 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900046369, and currently active. Its completion date has moved from August 2028 to April 2029: 4 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Island Cove?
How the possession date of Island Cove has moved
31 August 2028
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT51900019398)
Reason the builder gave MahaRERA:
“Project taken over recently. Original application had only Tower 1 and all compliances for Tower 1 have been done till December, 2023. Tower 2 has been added on April 4, 2024 vide correction application approved on April 4, 2024, while the…” Read the full reason
“Project taken over recently. Original application had only Tower 1 and all compliances for Tower 1 have been done till December, 2023. Tower 2 has been added on April 4, 2024 vide correction application approved on April 4, 2024, while the extension application was pending at desk 2. Format B has already been uploaded in tab Resolution of the Association of Allottees Sr no 2 below.”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Island Cove’s extension records on MahaRERA (P51900046369), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Island Cove
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Island Cove Tower 3P51900080584 · possession 30 Apr 2030
- Island Cove Tower 4PR1170002500784 · possession 30 Apr 2031
- MahaRERA registration
- P51900046369
- Status
- Registered and active
- Builder
- LH Residential Housing Private Limited
- Location
- Mahim, Mumbai · 400016
- Project type
- Others
- Registered on
- 22 Jun 2022
- Completion date at registration
- August 2028
- Latest completion date
- April 2029
- Delay so far
- 4 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 498
- Sold or booked
- 91%
- Towers
- 2
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Island Cove, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sale Building Tower 1 | 100% | 42% | 0% | 0% |
| Sale Building Tower 2 | 100% | 48% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sale Building Tower 1: covers Upto top of 6th podium floor
- Sale Building Tower 2: covers Upto top of 6th podium floor
Latest CC order on MahaRERA: dated 12/02/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Island Cove every month.
Island Cove: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 695 – 1,045 | 256 |
| 3 BHK | 768 – 1,220 | 242 |
| Shops | 136 – 600 | 25 |
- Buildings: Sale Building Tower 1 (40 floors, 276 units) · Sale Building Tower 2 (40 floors, 247 units)
- Car parking: 771 covered
- Land: 6,368 sq m (about 1.6 acres) · sanctioned built-up 52,465 sq m · recreational space 52,465 sq m
- Boundaries filed include: Mahim Sion Link Road
The builder’s record and reviews
Larsen & Toubro Ltd Realty Division (a group of 3 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 5 months); 25 still being built, 5 past the promised date (typically 12 months late); 3 lapsed. 93 complaints on MahaRERA across 18 projects.
Read Google reviews of Island Cove →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Island Cove: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Island Cove
What is the possession date of Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Island Cove in Mahim, Mumbai is 30 April 2029 — 4 months later than 31 August 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Island Cove?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Island Cove's builder has filed on MahaRERA, the official one, is 30 April 2029, already 4 months later than the 31 August 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Island Cove extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "Project taken over recently. Original application had only Tower 1 and all compliances for Tower 1 have been done till December, 2023. Tower 2 has been added on April 4, 2024 vide correction application approved on April 4, 2024, while the extension application was pending at desk 2. Format B has already been uploaded in tab Resolution of the Association of Allottees Sr no 2 below.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Island Cove in Mahim, Mumbai is P51900046369.
Is Island Cove registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove is registered as P51900046369 and its status is "Registered and active".
What is the construction status of Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 42% to 48% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Island Cove have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Island Cove safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove is registered on MahaRERA as P51900046369, its completion date has moved 4 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Island Cove have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Island Cove Tower 3 (P51900080584, possession 30 Apr 2030); Island Cove Tower 4 (PR1170002500784, possession 30 Apr 2031). Check that your agreement names the registration of your own wing.
How can I get updates if Island Cove's possession date changes?
The latest dates are on Island Cove's MahaRERA page (P51900046369). GharKundli's Kundli Watch sends a free WhatsApp update on Island Cove every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Island Cove have?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove has 2 buildings filed: Sale Building Tower 1 with 40 floors and 276 units; Sale Building Tower 2 with 40 floors and 247 units.
What are the flat sizes (carpet area) in Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Island Cove: 2 BHK: 695 to 1045 sq ft carpet (256 homes); 3 BHK: 768 to 1220 sq ft carpet (242 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Island Cove have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 771 covered car parking spaces for Island Cove.
How big is the land of Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove stands on 6,368 sq m of land (about 1.6 acres), with 52,465 sq m of sanctioned built-up area and 52,465 sq m of recreational open space.
What is the track record of Island Cove's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Larsen & Toubro Ltd Realty Division (a group of 3 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 5 months); 25 still being built, 5 past the promised date (typically 12 months late); 3 lapsed. 93 complaints on MahaRERA across 18 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Island Cove?
Google Maps has reviews of Island Cove written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Island Cove?
Island Cove by LH Residential Housing Private Limited is in Mahim, Mumbai (pincode 400016), near Dharavi, Matunga, Bhawani Shankar, Maharashtra, and is registered on MahaRERA as P51900046369, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mahim Sion Link Road.
How many homes are in Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove has 498 homes in 2 towers registered on MahaRERA, and 91% of them are sold or booked.
When was Island Cove registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Island Cove was registered on MahaRERA on 22 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Island Cove?
No court cases are listed for Island Cove on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Island Cove?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LH Residential Housing Private Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Island Cove
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai City →
Other projects in pincode 400016
All 83 projects in Mahim (400016) →Other projects by LH Residential Housing Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.