Skip to content
GharKundli

Sunstone Epitome

by SUNSTONE CONSTRUCTIONS · Sion, Mumbai 400022Also near Bandra East, Dharavi, Vidyanagari

What’s in the report? →

Possession date of Sunstone Epitome (MahaRERA P51900079349): 30 April 2029. It has 32 homes (1 BHK, 2 BHK and 3 BHK, 525–1486 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900079349, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51900079349, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sunstone Epitome?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sunstone Epitome has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sunstone Epitome’s extension records on MahaRERA (P51900079349), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sunstone Epitome

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900079349
Status
Registered and active
Builder
SUNSTONE CONSTRUCTIONS
Location
Sion, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
28 Feb 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sunstone Epitome, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SUNSTONE EPITOME100%17%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SUNSTONE EPITOME: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunstone Epitome every 1–2 months.

Sunstone Epitome: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK704 – 96223
3 BHK946 – 1,4868
1 BHK5251
  • Buildings: SUNSTONE EPITOME (22 floors, 32 units)
  • Car parking: 71 covered
  • Land: 801 sq m (about 0.2 acres) · sanctioned built-up 2,870 sq m
  • Land, as filed: 172A/6 & 173/6
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sunstone Epitome →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sunstone Epitome: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sunstone Epitome

What is the possession date of Sunstone Epitome?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunstone Epitome in Sion, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sunstone Epitome?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunstone Epitome's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sunstone Epitome?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunstone Epitome in Sion, Mumbai is P51900079349.

Is Sunstone Epitome registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome is registered as P51900079349 and its status is "Registered and active".

What is the current construction status of Sunstone Epitome? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SUNSTONE EPITOME is 17% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sunstone Epitome have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sunstone Epitome safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome is registered on MahaRERA as P51900079349, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sunstone Epitome?

Sunstone Epitome is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sunstone Epitome are 525 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sunstone Epitome?

For a flat in Sunstone Epitome (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sunstone Epitome received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Sunstone Epitome a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Sunstone Epitome uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sunstone Epitome was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sunstone Epitome's possession date changes?

The latest dates are on Sunstone Epitome's MahaRERA page (P51900079349). GharKundli's Kundli Watch sends a free WhatsApp update on Sunstone Epitome every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sunstone Epitome have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome has one building filed: SUNSTONE EPITOME with 22 floors and 32 units.

What are the flat sizes (carpet area) in Sunstone Epitome?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sunstone Epitome: 2 BHK: 704 to 962 sq ft carpet (23 homes); 3 BHK: 946 to 1486 sq ft carpet (8 homes); 1 BHK: 525 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Sunstone Epitome have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 71 covered car parking spaces for Sunstone Epitome.

How big is the land of Sunstone Epitome?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome stands on 801 sq m of land (about 0.2 acres), with 2,870 sq m of sanctioned built-up area.

What are the reviews of Sunstone Epitome?

Google Maps has reviews of Sunstone Epitome written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sunstone Epitome?

Sunstone Epitome by SUNSTONE CONSTRUCTIONS is in Sion, Mumbai, pincode 400022 (near Bandra East, Dharavi, Vidyanagari), Maharashtra, and is registered on MahaRERA as P51900079349, per GharKundli's check of MahaRERA records. Its land is filed as 172A/6 & 173/6. GharKundli lists all 98 MahaRERA projects in Sion (400022).

How many flats are in Sunstone Epitome, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome has 32 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Sunstone Epitome registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunstone Epitome was registered on MahaRERA on 28 February 2025. GharKundli did not find a title report on the land on file there.

Does Sunstone Epitome have any legal issues or court cases?

No court cases are listed for Sunstone Epitome on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sunstone Epitome?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNSTONE CONSTRUCTIONS.

All projects with possession due in 2029 in Mumbai City →

Other projects in Sion (400022)

All 98 projects in Sion (400022) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.