ARIHANT NIWARA SKY
by DREAM ARIHANT INFRASTRUCTURE COMPANY · Chunabhatti MHADA Layout, MumbaiAlso near Sion Chunabhatti, Nehru Nagar
Possession date of ARIHANT NIWARA SKY: 30 May 2027, moved from 30 May 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800025450, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ARIHANT NIWARA SKY?
How the possession date of ARIHANT NIWARA SKY has moved
30 May 2025
Completion date given when the project was registered
30 May 2026
Extended at the builder's request (MahaRERA application EXT51800028281)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-05-2026. to complete the project and fulfil all regulatory requirements.”30 May 2027
Extended at the builder's request (MahaRERA application EA14052620954)
Reason the builder gave MahaRERA:
“Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions an…” Read the full reason
“Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions and workforce constraints, which consequently impacted the finishing stages of the project. Further, the process of obtaining the Occupancy Certificate (OC) has been prolonged due to pending inspections and approvals from the concerned authorities. In view of the above, we kindly request an extension for project completion until 30-05-2027.”
Source: ARIHANT NIWARA SKY’s extension records on MahaRERA (P51800025450), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARIHANT NIWARA SKY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800025450
- Status
- Registered and active
- Builder
- DREAM ARIHANT INFRASTRUCTURE COMPANY
- Location
- Chunabhatti MHADA Layout, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 30 May 2020
- Completion date at registration
- May 2025
- Latest completion date
- May 2027
- Delay so far
- 24 months
- Homes
- 159
- Sold or booked
- 88%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of ARIHANT NIWARA SKY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ARIHANT NIWARA SKY | 100% | 100% | 80% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- ARIHANT NIWARA SKY: covers 24 (G + 23)
Latest CC order on MahaRERA: dated 15/09/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT NIWARA SKY every month.
ARIHANT NIWARA SKY: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 650 – 725 | 67 |
| 3 BHK | 1,000 – 1,155 | 46 |
| 1 BHK | 440 – 485 | 46 |
- Buildings: ARIHANT NIWARA SKY (24 floors, 159 units)
- Land: 1,908 sq m (about 0.5 acres) · recreational space 742 sq m
- Boundaries filed include: BHAKTIDHAM MANDIR MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects.
Read Google reviews of ARIHANT NIWARA SKY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARIHANT NIWARA SKY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARIHANT NIWARA SKY
What is the possession date of ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT NIWARA SKY in Chunabhatti MHADA Layout, Mumbai is 30 May 2027 — 24 months later than 30 May 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARIHANT NIWARA SKY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT NIWARA SKY's builder has filed on MahaRERA, the official one, is 30 May 2027, already 24 months later than the 30 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARIHANT NIWARA SKY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY's builder applied to MahaRERA to extend the completion date 2 times: to 30 May 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-05-2026. to complete the project and fulfil all regulatory requirements."; to 30 May 2027, giving the reason "Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions and workforce constraints, which consequently impacted the finishing stages of the project. Further, the process of obtaining the Occupancy Certificate (OC) has been prolonged due to pending inspections and approvals from the concerned authorities. In view of the above, we kindly request an extension for project completion until 30-05-2027.".
What is the RERA number of ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT NIWARA SKY in Chunabhatti MHADA Layout, Mumbai is P51800025450.
Is ARIHANT NIWARA SKY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY is registered as P51800025450 and its status is "Registered and active".
What is the construction status of ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ARIHANT NIWARA SKY is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does ARIHANT NIWARA SKY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ARIHANT NIWARA SKY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY is registered on MahaRERA as P51800025450, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARIHANT NIWARA SKY's possession date changes?
The latest dates are on ARIHANT NIWARA SKY's MahaRERA page (P51800025450). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT NIWARA SKY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARIHANT NIWARA SKY have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY has one building filed: ARIHANT NIWARA SKY with 24 floors and 159 units.
What are the flat sizes (carpet area) in ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ARIHANT NIWARA SKY: 2 BHK: 650 to 725 sq ft carpet (67 homes); 3 BHK: 1000 to 1155 sq ft carpet (46 homes); 1 BHK: 440 to 485 sq ft carpet (46 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY stands on 1,908 sq m of land (about 0.5 acres) and 742 sq m of recreational open space.
What is the track record of ARIHANT NIWARA SKY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARIHANT NIWARA SKY?
Google Maps has reviews of ARIHANT NIWARA SKY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARIHANT NIWARA SKY?
ARIHANT NIWARA SKY by DREAM ARIHANT INFRASTRUCTURE COMPANY is in Chunabhatti MHADA Layout, Mumbai (pincode 400022), near Sion Chunabhatti, Nehru Nagar, Maharashtra, and is registered on MahaRERA as P51800025450, per GharKundli's check of MahaRERA records. Its boundaries filed there include BHAKTIDHAM MANDIR MARG.
How many homes are in ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY has 159 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.
When was ARIHANT NIWARA SKY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT NIWARA SKY was registered on MahaRERA on 30 May 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on ARIHANT NIWARA SKY?
No court cases are listed for ARIHANT NIWARA SKY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ARIHANT NIWARA SKY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DREAM ARIHANT INFRASTRUCTURE COMPANY, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARIHANT NIWARA SKY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in pincode 400022
- Shankheshwar Heights
- DOSTI MEZZO 22
- DNS ANUUTHAM
- SHANKESH CROWN
- SEAPLAZA
- DHANISHTHA
- KINGS HILL VIEW
- Privia Navkar
Other projects by DREAM ARIHANT INFRASTRUCTURE COMPANY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.