DNS ANUUTHAM
by DNS CONSTRUCTIONS PRIVATE LIMITED · Sion West, MumbaiAlso near Kurla West, Parel, Byculla
Possession: DNS ANUUTHAM is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900047962. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DNS ANUUTHAM?
How the possession date of DNS ANUUTHAM has moved
31 December 2025
Completion date given when the project was registered
31 August 2026
Extended at the builder's request (MahaRERA application EA02062621199)
Reason the builder gave MahaRERA:
“The project is completed in all respects and application for obtaining Occupation Certificate for the project from Municipal Corporation of Greater Mumbai was submitted on 28-08-2025. The Form-1 for December quarter compliance shows that al…” Read the full reason
“The project is completed in all respects and application for obtaining Occupation Certificate for the project from Municipal Corporation of Greater Mumbai was submitted on 28-08-2025. The Form-1 for December quarter compliance shows that all activities related to construction has been completed. The said extension is necessitated only on the grounds that even though the project was completed well within timeline proposed for completion, the OC for the building was issued by MCGM only on 10/02/2026. Now that the OC has been issued, the Allottees have already been given/offered possession of…”
Source: DNS ANUUTHAM’s extension records on MahaRERA (P51900047962), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DNS ANUUTHAM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900047962
- Status
- Completed
- Builder
- DNS CONSTRUCTIONS PRIVATE LIMITED
- Location
- Sion West, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 2 Dec 2022
- Completion date at registration
- December 2025
- Latest completion date
- August 2026
- Delay so far
- 8 months
- Homes
- 28
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of DNS ANUUTHAM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DNS ANNUTHAM | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- DNS ANNUTHAM: covers 20 floors
Latest CC order on MahaRERA: dated 17/03/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DNS ANUUTHAM every month.
DNS ANUUTHAM: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 805 – 937 | 12 |
| 1 BHK | 419 – 635 | 9 |
| 3 BHK | 813 – 1,206 | 6 |
| Office Space | 544 – 1,001 | 2 |
| 4 BHK | 1,418 | 1 |
| Shops | 543 | 1 |
- Buildings: DNS ANNUTHAM (20 floors, 31 units)
- Car parking: 32 covered
- Land: 512 sq m (about 0.1 acres) · sanctioned built-up 2,594 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
DNS Constructions has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 7 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of DNS ANUUTHAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DNS ANUUTHAM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DNS ANUUTHAM
What is the possession date of DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DNS ANUUTHAM in Sion West, Mumbai is 31 August 2026 — 8 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DNS ANUUTHAM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DNS ANUUTHAM's builder has filed on MahaRERA, the official one, is 31 August 2026, already 8 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DNS ANUUTHAM extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM's builder applied to MahaRERA to extend the completion date once: to 31 August 2026, giving the reason "The project is completed in all respects and application for obtaining Occupation Certificate for the project from Municipal Corporation of Greater Mumbai was submitted on 28-08-2025. The Form-1 for December quarter compliance shows that all activities related to construction has been completed. The said extension is necessitated only on the grounds that even though the project was completed well within timeline proposed for completion, the OC for the building was issued by MCGM only on 10/02/2026. Now that the OC has been issued, the Allottees have already been given/offered possession of…".
What is the RERA number of DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DNS ANUUTHAM in Sion West, Mumbai is P51900047962.
Is DNS ANUUTHAM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM is registered as P51900047962 and its status is "Completed".
What is the construction status of DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM's status on MahaRERA is "Completed". As filed by the builder, slab work on DNS ANNUTHAM is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DNS ANUUTHAM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DNS ANUUTHAM safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM is registered on MahaRERA as P51900047962, its MahaRERA status is "Completed", its completion date has moved 8 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DNS ANUUTHAM's possession date changes?
The latest dates are on DNS ANUUTHAM's MahaRERA page (P51900047962). GharKundli's Kundli Watch sends a free WhatsApp update on DNS ANUUTHAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DNS ANUUTHAM have?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM has one building filed: DNS ANNUTHAM with 20 floors and 31 units.
What are the flat sizes (carpet area) in DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DNS ANUUTHAM: 2 BHK: 805 to 937 sq ft carpet (12 homes); 1 BHK: 419 to 635 sq ft carpet (9 homes); 3 BHK: 813 to 1206 sq ft carpet (6 homes); 4 BHK: 1418 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does DNS ANUUTHAM have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for DNS ANUUTHAM.
How big is the land of DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM stands on 512 sq m of land (about 0.1 acres), with 2,594 sq m of sanctioned built-up area.
What is the track record of DNS ANUUTHAM's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS Constructions has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 7 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DNS ANUUTHAM?
Google Maps has reviews of DNS ANUUTHAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DNS ANUUTHAM?
DNS ANUUTHAM by DNS CONSTRUCTIONS PRIVATE LIMITED is in Sion West, Mumbai (pincode 400022), near Kurla West, Parel, Byculla, Maharashtra, and is registered on MahaRERA as P51900047962, per GharKundli's check of MahaRERA records.
How many homes are in DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM has 28 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was DNS ANUUTHAM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DNS ANUUTHAM was registered on MahaRERA on 2 December 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on DNS ANUUTHAM?
No court cases are listed for DNS ANUUTHAM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DNS ANUUTHAM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DNS CONSTRUCTIONS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of DNS ANUUTHAM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400022
- Shankheshwar Heights
- DOSTI MEZZO 22
- SHANKESH CROWN
- ARIHANT NIWARA SKY
- SEAPLAZA
- DHANISHTHA
- KINGS HILL VIEW
- Privia Navkar
Other projects by DNS CONSTRUCTIONS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.