Skip to content
GharKundli

SEAPLAZA

by LDD CONSTRUCTIONS · Chunabhatti, MumbaiAlso near Sion, Nehru Nagar, Dharavi

Possession date of SEAPLAZA: 31 December 2032, moved from 30 April 2026 (80 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054646, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SEAPLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SEAPLAZA has moved

  1. 30 April 2026

    Completion date given when the project was registered

  2. 31 December 2032

    Extended at the builder's request (MahaRERA application EA20062621458)

    Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow . But now we have completed our 20% Projet”

Source: SEAPLAZA’s extension records on MahaRERA (P51800054646), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SEAPLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054646
Status
Registered and active
Builder
LDD CONSTRUCTIONS
Location
Chunabhatti, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
2 Feb 2024
Completion date at registration
April 2026
Latest completion date
December 2032
Delay so far
80 months
Homes
26
Sold or booked
4%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of SEAPLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SEAPLAZA100%100%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SEAPLAZA: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SEAPLAZA every month.

SEAPLAZA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK36225
2 BHK5071
  • Buildings: SEAPLAZA (15 floors, 26 units)
  • Car parking: 1 covered, 2 open
  • Land: 492 sq m (about 0.1 acres) · sanctioned built-up 985 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SEAPLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SEAPLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SEAPLAZA

What is the possession date of SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SEAPLAZA in Chunabhatti, Mumbai is 31 December 2032 — 80 months later than 30 April 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SEAPLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SEAPLAZA's builder has filed on MahaRERA, the official one, is 31 December 2032, already 80 months later than the 30 April 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SEAPLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA's builder applied to MahaRERA to extend the completion date once: to 31 December 2032, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow . But now we have completed our 20% Projet".

What is the RERA number of SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SEAPLAZA in Chunabhatti, Mumbai is P51800054646.

Is SEAPLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA is registered as P51800054646 and its status is "Registered and active".

What is the construction status of SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SEAPLAZA is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SEAPLAZA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SEAPLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA is registered on MahaRERA as P51800054646, its completion date has moved 80 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SEAPLAZA's possession date changes?

The latest dates are on SEAPLAZA's MahaRERA page (P51800054646). GharKundli's Kundli Watch sends a free WhatsApp update on SEAPLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SEAPLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA has one building filed: SEAPLAZA with 15 floors and 26 units.

What are the flat sizes (carpet area) in SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SEAPLAZA: 1 BHK: 362 sq ft carpet (25 homes); 2 BHK: 507 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does SEAPLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 2 open car parking spaces for SEAPLAZA.

How big is the land of SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA stands on 492 sq m of land (about 0.1 acres), with 985 sq m of sanctioned built-up area.

Where can I read reviews of SEAPLAZA?

Google Maps has reviews of SEAPLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SEAPLAZA?

SEAPLAZA by LDD CONSTRUCTIONS is in Chunabhatti, Mumbai (pincode 400022), near Sion, Nehru Nagar, Dharavi, Maharashtra, and is registered on MahaRERA as P51800054646, per GharKundli's check of MahaRERA records.

How many homes are in SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA has 26 homes in 1 tower registered on MahaRERA, and 4% of them are sold or booked.

When was SEAPLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SEAPLAZA was registered on MahaRERA on 2 February 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on SEAPLAZA?

No court cases are listed for SEAPLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SEAPLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LDD CONSTRUCTIONS.

Other projects in pincode 400022

All 98 projects in Sion (400022) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.