Darshan Aura
by DARSHAN SKY HIGH CONSTRUCTIONS LLP · Ghodapdeo, Mumbai 400033Also near Tank Road, Sewri, Mazgaon
What’s in the report? →Possession date of Darshan Aura (MahaRERA P51900056427): 30 April 2029. It has 178 homes (1 BHK, 1 Room Kitchen and 2 BHK, 252–608 sq ft carpet), 55% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900056427, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51900056427, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Darshan Aura?
11 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Darshan Aura has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Darshan Aura’s extension records on MahaRERA (P51900056427), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Darshan Aura
Ready · November 2026 · 85 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each of the 11 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900056427
- Status
- Registered and active
- Builder
- DARSHAN SKY HIGH CONSTRUCTIONS LLP
- Location
- Ghodapdeo, Mumbai · 400033
- Project type
- Others
- Registered on
- 31 May 2024
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 178
- Sold or booked
- 55%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 11
- Title report on file
- Yes
- Latest construction certificate
- 30 Jun 2026
Construction progress of Darshan Aura, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DARSHAN AURA WING A | 100% | 0% | 0% | 0% |
| DARSHAN AURA WING B | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Darshan Aura every 1–2 months.
Darshan Aura: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 252 – 521 | 134 |
| 2 BHK | 580 – 608 | 41 |
| Other | 96 – 1,137 | 10 |
| Multi Purpose Room | 212 – 422 | 5 |
| 1 Room Kitchen | 317 – 321 | 2 |
| Shops | 954 | 1 |
| Showroom | 821 | 1 |
- Buildings: DARSHAN AURA WING A (22 floors) · DARSHAN AURA WING B (23 floors)
- Car parking: 59 covered
- Land: 2,644 sq m (about 0.7 acres) · sanctioned built-up 10,161 sq m · recreational space 165 sq m
- Land, as filed: 718
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Darshan Aura →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Darshan Aura: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Darshan Aura
What is the possession date of Darshan Aura?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Darshan Aura in Ghodapdeo, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Darshan Aura?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Darshan Aura's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Darshan Aura?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Darshan Aura in Ghodapdeo, Mumbai is P51900056427.
Is Darshan Aura registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura is registered as P51900056427 and its status is "Registered and active".
What is the current construction status of Darshan Aura? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. The latest construction certificate the builder filed there is dated 30 June 2026. GharKundli's full report compares construction progress with the deadline.
Does Darshan Aura have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Darshan Aura safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura is registered on MahaRERA as P51900056427, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Darshan Aura?
Darshan Aura is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Darshan Aura are 252 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Darshan Aura?
For a flat in Darshan Aura (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Darshan Aura received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Darshan Aura a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura is a redevelopment: 102 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Darshan Aura uploaded its title report on MahaRERA?
Yes. According to GharKundli's check of MahaRERA records (updated November 2026), an advocate's title report for Darshan Aura is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.
A loan or claim on the land can hold up your flat or your home loan. See what the title report says →
How can I get updates if Darshan Aura's possession date changes?
The latest dates are on Darshan Aura's MahaRERA page (P51900056427). GharKundli's Kundli Watch sends a free WhatsApp update on Darshan Aura every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Darshan Aura have?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura has 2 buildings filed: DARSHAN AURA WING A with 22 floors; DARSHAN AURA WING B with 23 floors.
What are the flat sizes (carpet area) in Darshan Aura?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed these homes for Darshan Aura: 1 BHK: 252 to 521 sq ft carpet (134 homes); 2 BHK: 580 to 608 sq ft carpet (41 homes); 1 Room Kitchen: 317 to 321 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Darshan Aura have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 59 covered car parking spaces for Darshan Aura.
How big is the land of Darshan Aura?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura stands on 2,644 sq m of land (about 0.7 acres), with 10,161 sq m of sanctioned built-up area and 165 sq m of recreational open space.
What are the reviews of Darshan Aura?
Google Maps has reviews of Darshan Aura written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Darshan Aura?
Darshan Aura by DARSHAN SKY HIGH CONSTRUCTIONS LLP is in Ghodapdeo, Mumbai, pincode 400033 (near Tank Road, Sewri, Mazgaon), Maharashtra, and is registered on MahaRERA as P51900056427, per GharKundli's check of MahaRERA records. Its land is filed as 718. GharKundli lists all 17 MahaRERA projects in Mazgaon (400033).
How many flats are in Darshan Aura, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura has 178 homes in 2 towers registered on MahaRERA, and 55% of them are sold or booked.
When was Darshan Aura registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Darshan Aura was registered on MahaRERA on 31 May 2024. A title report on the land is on file there.
Does Darshan Aura have any legal issues or court cases?
11 court cases are listed for Darshan Aura on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Darshan Aura?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DARSHAN SKY HIGH CONSTRUCTIONS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Darshan Aura
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai City →
Other projects in Ward E
- Vardhman Flora Phase -II - Vardhman Habitat
- Ibrahim Residency
- Bismillah Arcade 2
- Presidence Eternia
- Raheja Modern Vivarea North Tower
- Chaitya 777
- Parshwa Lotus & Rangari Heights
- 52 Avenue
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.