Possession date of AL AMIR APARTMENT: 31 December 2028, moved from 31 July 2023 (65 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900007426, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AL AMIR APARTMENT?
How the possession date of AL AMIR APARTMENT has moved
31 July 2023
Completion date given when the project was registered
30 July 2024
Extended at the builder's request (MahaRERA application EXT51900017253)
Reason the builder gave MahaRERA: “Amalgamation of adjoining plot bearing C.S. No. 1808 of Mandvi division.”
31 December 2028
Extended at the builder's request (MahaRERA application EA19082622234)
Reason the builder gave MahaRERA:
“Extension is required on the grounds of additional incentive fsi available on the plot. Previously the structure of A wing was to be limited to 22 floors but now due to change in incentive this structure is to be reworked to 25 floors and b…” Read the full reason
“Extension is required on the grounds of additional incentive fsi available on the plot. Previously the structure of A wing was to be limited to 22 floors but now due to change in incentive this structure is to be reworked to 25 floors and balance excess fsi unutilised will be transferred to other scheme..”
Source: AL AMIR APARTMENT’s extension records on MahaRERA (P51900007426), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AL AMIR APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900007426
- Status
- Registered and active
- Builder
- JANZEB AMIRKAMAL KHAN
- Location
- Dongri, Mumbai · 400009
- Project type
- Mixed
- Registered on
- 17 Aug 2017
- Completion date at registration
- July 2023
- Latest completion date
- December 2028
- Delay so far
- 65 months
- Homes
- 231
- Sold or booked
- 90%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AL AMIR APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AL AMIR APARTMENT | 0% | 89% | 89% | 78% |
Commencement certificate (CC), as filed on MahaRERA
- AL AMIR APARTMENT: covers 26 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AL AMIR APARTMENT every month.
AL AMIR APARTMENT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 Room Kitchen | 225 – 360 | 157 |
| 1 BHK | 329 – 471 | 58 |
| Shops | 56 – 647 | 17 |
| 2 BHK | 465 – 529 | 15 |
| 3 BHK | 559 | 1 |
- Buildings: AL AMIR APARTMENT (27 floors, 248 units)
- Land: 868 sq m (about 0.2 acres) · sanctioned built-up 4,197 sq m
- Boundaries filed include: JAIL ROAD SOUTH, NISHANPADA ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AL AMIR APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AL AMIR APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AL AMIR APARTMENT
What is the possession date of AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AL AMIR APARTMENT in Dongri, Mumbai is 31 December 2028 — 65 months later than 31 July 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AL AMIR APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AL AMIR APARTMENT's builder has filed on MahaRERA, the official one, is 31 December 2028, already 65 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AL AMIR APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2024, giving the reason "Amalgamation of adjoining plot bearing C.S. No. 1808 of Mandvi division."; to 31 December 2028, giving the reason "Extension is required on the grounds of additional incentive fsi available on the plot. Previously the structure of A wing was to be limited to 22 floors but now due to change in incentive this structure is to be reworked to 25 floors and balance excess fsi unutilised will be transferred to other scheme..".
What is the RERA number of AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AL AMIR APARTMENT in Dongri, Mumbai is P51900007426.
Is AL AMIR APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT is registered as P51900007426 and its status is "Registered and active".
What is the construction status of AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AL AMIR APARTMENT is 89% done and internal work 89%. GharKundli's full report compares construction progress with the deadline.
Does AL AMIR APARTMENT have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AL AMIR APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT is registered on MahaRERA as P51900007426, its completion date has moved 65 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AL AMIR APARTMENT's possession date changes?
The latest dates are on AL AMIR APARTMENT's MahaRERA page (P51900007426). GharKundli's Kundli Watch sends a free WhatsApp update on AL AMIR APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AL AMIR APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT has one building filed: AL AMIR APARTMENT with 27 floors and 248 units.
What are the flat sizes (carpet area) in AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AL AMIR APARTMENT: 1 Room Kitchen: 225 to 360 sq ft carpet (157 homes); 1 BHK: 329 to 471 sq ft carpet (58 homes); 2 BHK: 465 to 529 sq ft carpet (15 homes); 3 BHK: 559 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT stands on 868 sq m of land (about 0.2 acres), with 4,197 sq m of sanctioned built-up area.
Where can I read reviews of AL AMIR APARTMENT?
Google Maps has reviews of AL AMIR APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AL AMIR APARTMENT?
AL AMIR APARTMENT by JANZEB AMIRKAMAL KHAN is in Dongri, Mumbai (pincode 400009), Maharashtra, and is registered on MahaRERA as P51900007426, per GharKundli's check of MahaRERA records. Its boundaries filed there include JAIL ROAD SOUTH, NISHANPADA ROAD.
How many homes are in AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT has 231 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.
When was AL AMIR APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL AMIR APARTMENT was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AL AMIR APARTMENT?
No court cases are listed for AL AMIR APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AL AMIR APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JANZEB AMIRKAMAL KHAN.
Check it yourself on MahaRERA
- How to check the possession date of AL AMIR APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in Mumbai City
- Simna Heights / Shantichndra Heights
- ZAHRA RESIDENCY
- GRANDEUR
- THE CANVAS RESIDENCES - CANVAS 1, CANVAS 2, CANVAS 3
- Privia Navkar
- Harsh Oasis
- Waterview
- Lodha Sewri Project
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.