APNA GHAR PHASE III NX
by Seven Eleven Construction Pvt Ltd · Village Ghodbunder, ThaneAlso near Mira Road, Vinay Nagar, Vinaynagar
Possession date of APNA GHAR PHASE III NX: 31 July 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700045229, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about APNA GHAR PHASE III NX?
How the possession date of APNA GHAR PHASE III NX has moved
31 March 2027
Completion date given when the project was registered
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: APNA GHAR PHASE III NX’s extension records on MahaRERA (P51700045229), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on APNA GHAR PHASE III NX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- APNA GHAR PHASE II NXP51700045206 · possession 21 Aug 2027
- MahaRERA registration
- P51700045229
- Status
- Registered and active
- Builder
- Seven Eleven Construction Pvt Ltd
- Location
- Village Ghodbunder, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2022
- Completion date at registration
- March 2027
- Latest completion date
- July 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 299
- Towers
- 4
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of APNA GHAR PHASE III NX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A5 | 0% | 0% | 0% | 0% |
| A6 | 0% | 0% | 0% | 0% |
| A7 | 0% | 0% | 0% | 0% |
| C5 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on APNA GHAR PHASE III NX every month.
APNA GHAR PHASE III NX: buildings, flats and land, as filed on MahaRERA
- Buildings: A5 (23 floors) · A6 (23 floors) · A7 (8 floors) · C5 (8 floors)
- Land: 18,300 sq m (about 4.5 acres) · sanctioned built-up 12,826 sq m · recreational space 3,213 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Seven Eleven Construction has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 10 complaints on MahaRERA across 4 projects.
Read Google reviews of APNA GHAR PHASE III NX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
APNA GHAR PHASE III NX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about APNA GHAR PHASE III NX
What is the possession date of APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for APNA GHAR PHASE III NX in Village Ghodbunder, Thane is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for APNA GHAR PHASE III NX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date APNA GHAR PHASE III NX's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of APNA GHAR PHASE III NX in Village Ghodbunder, Thane is P51700045229.
Is APNA GHAR PHASE III NX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX is registered as P51700045229 and its status is "Registered and active".
What is the construction status of APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does APNA GHAR PHASE III NX have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is APNA GHAR PHASE III NX safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX is registered on MahaRERA as P51700045229, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does APNA GHAR PHASE III NX have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: APNA GHAR PHASE II NX (P51700045206, possession 21 Aug 2027). Check that your agreement names the registration of your own wing.
How can I get updates if APNA GHAR PHASE III NX's possession date changes?
The latest dates are on APNA GHAR PHASE III NX's MahaRERA page (P51700045229). GharKundli's Kundli Watch sends a free WhatsApp update on APNA GHAR PHASE III NX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does APNA GHAR PHASE III NX have?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX has 4 buildings filed: A5 with 23 floors; A6 with 23 floors; A7 with 8 floors; C5 with 8 floors.
How big is the land of APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX stands on 18,300 sq m of land (about 4.5 acres), with 12,826 sq m of sanctioned built-up area and 3,213 sq m of recreational open space.
What is the track record of APNA GHAR PHASE III NX's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Seven Eleven Construction has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 10 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of APNA GHAR PHASE III NX?
Google Maps has reviews of APNA GHAR PHASE III NX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is APNA GHAR PHASE III NX?
APNA GHAR PHASE III NX by Seven Eleven Construction Pvt Ltd is in Village Ghodbunder, Thane (pincode 401107), near Mira Road, Vinay Nagar, Vinaynagar, Maharashtra, and is registered on MahaRERA as P51700045229, per GharKundli's check of MahaRERA records.
How many homes are in APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX has 299 homes in 4 towers registered on MahaRERA.
When was APNA GHAR PHASE III NX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), APNA GHAR PHASE III NX was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on APNA GHAR PHASE III NX?
No court cases are listed for APNA GHAR PHASE III NX on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of APNA GHAR PHASE III NX?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Seven Eleven Construction Pvt Ltd, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of APNA GHAR PHASE III NX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 401107
- Umiya Oasis
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Other projects by Seven Eleven Construction Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.