by SUDAM ZIPA RASAL · Kohoj Khuntavali, ThaneAlso near Ambernath, Wimco Naka
Possession date of SUDAMA ELEVATE: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700047064, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SUDAMA ELEVATE?
How the possession date of SUDAMA ELEVATE has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA29122519105)
Reason the builder gave MahaRERA: “Unfavourable market situation and post Covid Effects.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SUDAMA ELEVATE’s extension records on MahaRERA (P51700047064), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUDAMA ELEVATE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700047064
- Status
- Registered and active
- Builder
- SUDAM ZIPA RASAL
- Location
- Kohoj Khuntavali, Thane · 421502
- Project type
- Residential / Group Housing
- Registered on
- 29 Sep 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 194
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SUDAMA ELEVATE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TYPE-A | 100% | 100% | 60% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- TYPE-A: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUDAMA ELEVATE every month.
SUDAMA ELEVATE: buildings, flats and land, as filed on MahaRERA
- Buildings: TYPE-A (15 floors, 194 units)
- Car parking: 58 covered
- Land: 4,640 sq m (about 1.1 acres) · sanctioned built-up 10,129 sq m
- Boundaries filed include: GAONDEVI MANDIR, 6 MTS INTERNAL WIDE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SUDAMA ELEVATE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUDAMA ELEVATE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUDAMA ELEVATE
What is the possession date of SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUDAMA ELEVATE in Kohoj Khuntavali, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SUDAMA ELEVATE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUDAMA ELEVATE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SUDAMA ELEVATE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Unfavourable market situation and post Covid Effects.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUDAMA ELEVATE in Kohoj Khuntavali, Thane is P51700047064.
Is SUDAMA ELEVATE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE is registered as P51700047064 and its status is "Registered and active".
What is the construction status of SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TYPE-A is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does SUDAMA ELEVATE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SUDAMA ELEVATE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE is registered on MahaRERA as P51700047064, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SUDAMA ELEVATE's possession date changes?
The latest dates are on SUDAMA ELEVATE's MahaRERA page (P51700047064). GharKundli's Kundli Watch sends a free WhatsApp update on SUDAMA ELEVATE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUDAMA ELEVATE have?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE has one building filed: TYPE-A with 15 floors and 194 units.
How much parking does SUDAMA ELEVATE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 58 covered car parking spaces for SUDAMA ELEVATE.
How big is the land of SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE stands on 4,640 sq m of land (about 1.1 acres), with 10,129 sq m of sanctioned built-up area.
Where can I read reviews of SUDAMA ELEVATE?
Google Maps has reviews of SUDAMA ELEVATE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUDAMA ELEVATE?
SUDAMA ELEVATE by SUDAM ZIPA RASAL is in Kohoj Khuntavali, Thane (pincode 421502), near Ambernath, Wimco Naka, Maharashtra, and is registered on MahaRERA as P51700047064, per GharKundli's check of MahaRERA records. Its boundaries filed there include GAONDEVI MANDIR, 6 MTS INTERNAL WIDE ROAD.
How many homes are in SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE has 194 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was SUDAMA ELEVATE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDAMA ELEVATE was registered on MahaRERA on 29 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SUDAMA ELEVATE?
No court cases are listed for SUDAMA ELEVATE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SUDAMA ELEVATE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUDAM ZIPA RASAL.
Check it yourself on MahaRERA
- How to check the possession date of SUDAMA ELEVATE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambarnath
- DAVE TOWERS
- Neelkrishna amalgamated project of Neelam CHS Ltd and Krishna Milan CHS Ltd
- NAKODA COOPERATIVE HOUSING SOCIETY LTD
- Nature Vista Building - 1
- MIDTOWN B AND C WING
- MERY VILLA CHSL
- SAI UNIVERSE
- MAHADEV HEIGHTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.