HARE KRISHNA JANVI HEIGHT
by HARE KRISHNA GROUP · Kansai, Thane
Possession date of HARE KRISHNA JANVI HEIGHT: 30 April 2028, moved from 31 March 2024 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048700, and currently active. Its completion date has moved from March 2024 to April 2028: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HARE KRISHNA JANVI HEIGHT?
How the possession date of HARE KRISHNA JANVI HEIGHT has moved
31 March 2024
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA20082622240)
Reason the builder gave MahaRERA: “DOE TO DELAY IN WORK AND SLOW SALES OUR PROJECT GOT DELAYED .BUT WE ARE APPLYING FOR EXTENSION AND VERY LITTLE WORK IS PENDING TO BE COMPLETED. THEREFORE GRANT EXTENSION”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HARE KRISHNA JANVI HEIGHT’s extension records on MahaRERA (P51700048700), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HARE KRISHNA JANVI HEIGHT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048700
- Status
- Registered and active
- Builder
- HARE KRISHNA GROUP
- Location
- Kansai, Thane · 421306
- Project type
- Residential / Group Housing
- Registered on
- 12 Jan 2023
- Completion date at registration
- March 2024
- Latest completion date
- April 2028
- Delay so far
- 45 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 10
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of HARE KRISHNA JANVI HEIGHT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HARE KRISHNA JANVI HEIGHT | 100% | 100% | 66% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- HARE KRISHNA JANVI HEIGHT: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARE KRISHNA JANVI HEIGHT every month.
HARE KRISHNA JANVI HEIGHT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 380 – 430 | 7 |
| Shops | 114 – 134 | 3 |
| 1 Room Kitchen | 221 | 3 |
- Buildings: HARE KRISHNA JANVI HEIGHT (4 floors, 13 units)
- Land: 277 sq m (about 0.1 acres) · sanctioned built-up 478 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HARE KRISHNA JANVI HEIGHT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HARE KRISHNA JANVI HEIGHT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HARE KRISHNA JANVI HEIGHT
What is the possession date of HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARE KRISHNA JANVI HEIGHT in Kansai, Thane is 30 April 2028 — 45 months later than 31 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HARE KRISHNA JANVI HEIGHT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HARE KRISHNA JANVI HEIGHT's builder has filed on MahaRERA, the official one, is 30 April 2028, already 45 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HARE KRISHNA JANVI HEIGHT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "DOE TO DELAY IN WORK AND SLOW SALES OUR PROJECT GOT DELAYED .BUT WE ARE APPLYING FOR EXTENSION AND VERY LITTLE WORK IS PENDING TO BE COMPLETED. THEREFORE GRANT EXTENSION". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARE KRISHNA JANVI HEIGHT in Kansai, Thane is P51700048700.
Is HARE KRISHNA JANVI HEIGHT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT is registered as P51700048700 and its status is "Registered and active".
What is the construction status of HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HARE KRISHNA JANVI HEIGHT is 100% done and internal work 66%. GharKundli's full report compares construction progress with the deadline.
Does HARE KRISHNA JANVI HEIGHT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is HARE KRISHNA JANVI HEIGHT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT is registered on MahaRERA as P51700048700, its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HARE KRISHNA JANVI HEIGHT's possession date changes?
The latest dates are on HARE KRISHNA JANVI HEIGHT's MahaRERA page (P51700048700). GharKundli's Kundli Watch sends a free WhatsApp update on HARE KRISHNA JANVI HEIGHT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HARE KRISHNA JANVI HEIGHT have?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT has one building filed: HARE KRISHNA JANVI HEIGHT with 4 floors and 13 units.
What are the flat sizes (carpet area) in HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for HARE KRISHNA JANVI HEIGHT: 1 BHK: 380 to 430 sq ft carpet (7 homes); 1 Room Kitchen: 221 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT stands on 277 sq m of land (about 0.1 acres), with 478 sq m of sanctioned built-up area.
Where can I read reviews of HARE KRISHNA JANVI HEIGHT?
Google Maps has reviews of HARE KRISHNA JANVI HEIGHT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HARE KRISHNA JANVI HEIGHT?
HARE KRISHNA JANVI HEIGHT by HARE KRISHNA GROUP is in Kansai, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700048700, per GharKundli's check of MahaRERA records.
How many homes are in HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT has 10 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was HARE KRISHNA JANVI HEIGHT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARE KRISHNA JANVI HEIGHT was registered on MahaRERA on 12 January 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on HARE KRISHNA JANVI HEIGHT?
No court cases are listed for HARE KRISHNA JANVI HEIGHT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of HARE KRISHNA JANVI HEIGHT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARE KRISHNA GROUP.
Check it yourself on MahaRERA
- How to check the possession date of HARE KRISHNA JANVI HEIGHT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kansai
- ISHWAR SARASWATI PALACE
- MAYURESH KRUPA CHS LTD
- OM SHIVANJALI CHS LTD
- INDIRA SADAN PHASE I
- ADWAIT GAURAV
- SPECTRUM
- AMRESHWAR CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE SAI ARNAV
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.