KALYAN AASHIYANA
by AL BRUJ DEVELOPERS · Kongaon, ThaneAlso near Saravali
Possession date of KALYAN AASHIYANA: 31 December 2025, moved from 31 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700049257. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about KALYAN AASHIYANA?
How the possession date of KALYAN AASHIYANA has moved
31 December 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51700025116)
Reason the builder gave MahaRERA: “As you can check from records. Project is almost completed but Occupancy Certificate application is under process.”
31 December 2025
Extended at the builder's request (MahaRERA application EA18062501668)
Reason the builder gave MahaRERA:
“It may be noted that our project is completed and we have applied for Occupancy Certificate on 26.12.2024. But the approval is pending at MMRDA hence, we have requested for the extension. We are expecting the occupancy certificate by 31.12.…” Read the full reason
“It may be noted that our project is completed and we have applied for Occupancy Certificate on 26.12.2024. But the approval is pending at MMRDA hence, we have requested for the extension. We are expecting the occupancy certificate by 31.12.2024.”
Source: KALYAN AASHIYANA’s extension records on MahaRERA (P51700049257), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KALYAN AASHIYANA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700049257
- Status
- Lapsed (registration period ended)
- Builder
- AL BRUJ DEVELOPERS
- Location
- Kongaon, Thane · 421311
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2023
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 41
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KALYAN AASHIYANA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 100% |
| WING B | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 5 floors
- WING B: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KALYAN AASHIYANA every month.
KALYAN AASHIYANA: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (5 floors, 29 units) · WING B (5 floors, 12 units)
- Car parking: 10 covered
- Land: 825 sq m (about 0.2 acres) · sanctioned built-up 1,831 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KALYAN AASHIYANA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KALYAN AASHIYANA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KALYAN AASHIYANA
What is the possession date of KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KALYAN AASHIYANA in Kongaon, Thane is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for KALYAN AASHIYANA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KALYAN AASHIYANA's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KALYAN AASHIYANA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "As you can check from records. Project is almost completed but Occupancy Certificate application is under process."; to 31 December 2025, giving the reason "It may be noted that our project is completed and we have applied for Occupancy Certificate on 26.12.2024. But the approval is pending at MMRDA hence, we have requested for the extension. We are expecting the occupancy certificate by 31.12.2024.".
What is the RERA number of KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KALYAN AASHIYANA in Kongaon, Thane is P51700049257.
Is KALYAN AASHIYANA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA is registered as P51700049257 and its status is "Lapsed (registration period ended)".
What is the construction status of KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does KALYAN AASHIYANA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is KALYAN AASHIYANA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA is registered on MahaRERA as P51700049257, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KALYAN AASHIYANA's possession date changes?
The latest dates are on KALYAN AASHIYANA's MahaRERA page (P51700049257). GharKundli's Kundli Watch sends a free WhatsApp update on KALYAN AASHIYANA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KALYAN AASHIYANA have?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA has 2 buildings filed: WING A with 5 floors and 29 units; WING B with 5 floors and 12 units.
How much parking does KALYAN AASHIYANA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for KALYAN AASHIYANA.
How big is the land of KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA stands on 825 sq m of land (about 0.2 acres), with 1,831 sq m of sanctioned built-up area.
Where can I read reviews of KALYAN AASHIYANA?
Google Maps has reviews of KALYAN AASHIYANA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KALYAN AASHIYANA?
KALYAN AASHIYANA by AL BRUJ DEVELOPERS is in Kongaon, Thane (pincode 421311), near Saravali, Maharashtra, and is registered on MahaRERA as P51700049257, per GharKundli's check of MahaRERA records.
How many homes are in KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA has 41 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was KALYAN AASHIYANA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALYAN AASHIYANA was registered on MahaRERA on 3 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on KALYAN AASHIYANA?
No court cases are listed for KALYAN AASHIYANA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KALYAN AASHIYANA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AL BRUJ DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of KALYAN AASHIYANA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421311
- SAI DARSHAN
- Mahindra Happinest Kalyan-2 Project A
- SHREE SAI SABURI APARTMENT-BUILDING B
- RIDDHI SIDDHI PARK
- SHREE LAXMAN APARTMENT
- KALYAN SURABHI
- Hiranandani Woodspring Bldg A-Oakwood Bldg B-Bridgewood Bldg C-Greenwood
- KALYAN VATIKA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.