Skip to content
GharKundli

SHRI ADINATH HEIGHTS

by MANGAL ENTERPRISES · Charai, Thane

Possession date of SHRI ADINATH HEIGHTS: 30 April 2028, moved from 31 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700051915, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHRI ADINATH HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI ADINATH HEIGHTS has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA03062621215)

    Reason the builder gave MahaRERA:
    “he delay was primarily caused due to unforeseen circumstances beyond the control of the Promoter, including shortage of construction materials, fluctuations in material costs, shortage of skilled labour, and unforeseen technical/site-relate…” Read the full reason“he delay was primarily caused due to unforeseen circumstances beyond the control of the Promoter, including shortage of construction materials, fluctuations in material costs, shortage of skilled labour, and unforeseen technical/site-related challenges, which affected the overall pace of construction work. The Promoter has undertaken necessary corrective measures, including deployment of additional manpower and streamlining of procurement processes, to expedite the completion of the project. The Promoter remains fully committed to completing and delivering the project within the revised tim…”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHRI ADINATH HEIGHTS’s extension records on MahaRERA (P51700051915), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI ADINATH HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700051915
Status
Registered and active
Builder
MANGAL ENTERPRISES
Location
Charai, Thane · 400601
Project type
Residential / Group Housing
Registered on
13 Jul 2023
Completion date at registration
December 2024
Latest completion date
April 2028
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHRI ADINATH HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
1100%55%22%0%

Commencement certificate (CC), as filed on MahaRERA

  • 1: covers stilt plus 8 floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI ADINATH HEIGHTS every month.

SHRI ADINATH HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: 1 (9 floors, 29 units)
  • Land: 207 sq m (about 0.1 acres) · sanctioned built-up 897 sq m
  • Boundaries filed include: 9 MW PROP ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRI ADINATH HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI ADINATH HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI ADINATH HEIGHTS

What is the possession date of SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI ADINATH HEIGHTS in Charai, Thane is 30 April 2028 — 36 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHRI ADINATH HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI ADINATH HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2028, already 36 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI ADINATH HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "he delay was primarily caused due to unforeseen circumstances beyond the control of the Promoter, including shortage of construction materials, fluctuations in material costs, shortage of skilled labour, and unforeseen technical/site-related challenges, which affected the overall pace of construction work. The Promoter has undertaken necessary corrective measures, including deployment of additional manpower and streamlining of procurement processes, to expedite the completion of the project. The Promoter remains fully committed to completing and delivering the project within the revised tim…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRI ADINATH HEIGHTS in Charai, Thane is P51700051915.

Is SHRI ADINATH HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS is registered as P51700051915 and its status is "Registered and active".

What is the construction status of SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 1 is 55% done and internal work 22%. GharKundli's full report compares construction progress with the deadline.

Does SHRI ADINATH HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHRI ADINATH HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS is registered on MahaRERA as P51700051915, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI ADINATH HEIGHTS's possession date changes?

The latest dates are on SHRI ADINATH HEIGHTS's MahaRERA page (P51700051915). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI ADINATH HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI ADINATH HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS has one building filed: 1 with 9 floors and 29 units.

How big is the land of SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS stands on 207 sq m of land (about 0.1 acres), with 897 sq m of sanctioned built-up area.

Where can I read reviews of SHRI ADINATH HEIGHTS?

Google Maps has reviews of SHRI ADINATH HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI ADINATH HEIGHTS?

SHRI ADINATH HEIGHTS by MANGAL ENTERPRISES is in Charai, Thane (pincode 400601), Maharashtra, and is registered on MahaRERA as P51700051915, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MW PROP ROAD.

How many homes are in SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS has 29 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was SHRI ADINATH HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI ADINATH HEIGHTS was registered on MahaRERA on 13 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI ADINATH HEIGHTS?

No court cases are listed for SHRI ADINATH HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHRI ADINATH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGAL ENTERPRISES.

All projects with possession due in 2028 in Thane →

Other projects in Charai

All 178 projects in Thane (400601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.