Possession date of ATLANTA CROWN: 30 August 2027, moved from 30 April 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051441, and currently active. Its completion date has moved from April 2026 to August 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ATLANTA CROWN?
How the possession date of ATLANTA CROWN has moved
30 April 2026
Completion date given when the project was registered
30 April 2027
Extended at the builder's request (MahaRERA application EA20032620308)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, We, M/s Atlanta Construction, ("Atlanta"), and we are writing you with regards to our application for extension of time till 30th April, 2027; 1) As you are aware that the company is engaged in the constructing a real estate…” Read the full reason
“Dear Sir/Madam, We, M/s Atlanta Construction, ("Atlanta"), and we are writing you with regards to our application for extension of time till 30th April, 2027; 1) As you are aware that the company is engaged in the constructing a real estate project at Ulhasnagar, Maharashtra on its plot of land comprising of 1 Building. The registered as “Atlanta Crown”. [hereinafter collectively referred to as "the Project"). 2) We say that we obtained the Rera registration number for Project Atlanta Crown 2 at Ulhasnagar, Thane bearing number P51700051441. 3. We say that our project 90% completed in Decem…”30 August 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ATLANTA CROWN’s extension records on MahaRERA (P51700051441), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ATLANTA CROWN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051441
- Status
- Registered and active
- Builder
- ATLANTA CONSTRUCTION
- Location
- Ulhasnagar, Thane · 421003
- Project type
- Others
- Registered on
- 14 Jun 2023
- Completion date at registration
- April 2026
- Latest completion date
- August 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 42
- Sold or booked
- 26%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ATLANTA CROWN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ATLANTA CROWN | 100% | 100% | 100% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- ATLANTA CROWN: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ATLANTA CROWN every month.
ATLANTA CROWN: buildings, flats and land, as filed on MahaRERA
- Buildings: ATLANTA CROWN (8 floors, 63 units)
- Car parking: 10 covered
- Land: 899 sq m (about 0.2 acres) · sanctioned built-up 3,374 sq m
- Boundaries filed include: POWER HOUSE ROAD
The builder’s record and reviews
Atlanta Landmark (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 2 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of ATLANTA CROWN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ATLANTA CROWN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ATLANTA CROWN
What is the possession date of ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ATLANTA CROWN in Ulhasnagar, Thane is 30 August 2027 — 12 months later than 30 April 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ATLANTA CROWN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ATLANTA CROWN's builder has filed on MahaRERA, the official one, is 30 August 2027, already 12 months later than the 30 April 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ATLANTA CROWN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN's builder applied to MahaRERA to extend the completion date once: to 30 April 2027, giving the reason "Dear Sir/Madam, We, M/s Atlanta Construction, ("Atlanta"), and we are writing you with regards to our application for extension of time till 30th April, 2027; 1) As you are aware that the company is engaged in the constructing a real estate project at Ulhasnagar, Maharashtra on its plot of land comprising of 1 Building. The registered as “Atlanta Crown”. [hereinafter collectively referred to as "the Project"). 2) We say that we obtained the Rera registration number for Project Atlanta Crown 2 at Ulhasnagar, Thane bearing number P51700051441. 3. We say that our project 90% completed in Decem…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ATLANTA CROWN in Ulhasnagar, Thane is P51700051441.
Is ATLANTA CROWN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN is registered as P51700051441 and its status is "Registered and active".
What is the construction status of ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ATLANTA CROWN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ATLANTA CROWN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ATLANTA CROWN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN is registered on MahaRERA as P51700051441, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ATLANTA CROWN's possession date changes?
The latest dates are on ATLANTA CROWN's MahaRERA page (P51700051441). GharKundli's Kundli Watch sends a free WhatsApp update on ATLANTA CROWN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ATLANTA CROWN have?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN has one building filed: ATLANTA CROWN with 8 floors and 63 units.
How much parking does ATLANTA CROWN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for ATLANTA CROWN.
How big is the land of ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN stands on 899 sq m of land (about 0.2 acres), with 3,374 sq m of sanctioned built-up area.
What is the track record of ATLANTA CROWN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Atlanta Landmark (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 2 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ATLANTA CROWN?
Google Maps has reviews of ATLANTA CROWN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ATLANTA CROWN?
ATLANTA CROWN by ATLANTA CONSTRUCTION is in Ulhasnagar, Thane (pincode 421003), Maharashtra, and is registered on MahaRERA as P51700051441, per GharKundli's check of MahaRERA records. Its boundaries filed there include POWER HOUSE ROAD.
How many homes are in ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN has 42 homes in 1 tower registered on MahaRERA, and 26% of them are sold or booked.
When was ATLANTA CROWN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA CROWN was registered on MahaRERA on 14 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on ATLANTA CROWN?
No court cases are listed for ATLANTA CROWN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ATLANTA CROWN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATLANTA CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of ATLANTA CROWN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ulhasnagar
All Thane projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.