Possession date of SOFRANCE WING A: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800007146, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SOFRANCE WING A?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SOFRANCE WING A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800007146
Status
Registered and active
Builder
DAGA DEVELOPERS PRIVATE LIMITED
Location
Kurla, Mumbai · 400075
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
76
Sold or booked
48%
Towers
1
Complaints on MahaRERA
1
Court cases listed
2
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SOFRANCE WING A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SOFRANCE WING A100%12%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SOFRANCE WING A: covers Gr+16 Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SOFRANCE WING A every month.

SOFRANCE WING A: buildings, flats and land, as filed on MahaRERA

  • Buildings: SOFRANCE WING A (17 floors, 80 units)
  • Land: 4,976 sq m (about 1.2 acres) · sanctioned built-up 4,939 sq m · recreational space 142 sq m
  • Boundaries filed include: ANDHERI GHATKOPAR LINK ROAD, SAVITRIBAI PHULE NAGAR, SWAMI SAMARTH ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Daga Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 18 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of SOFRANCE WING A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SOFRANCE WING A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SOFRANCE WING A

What is the possession date of SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SOFRANCE WING A in Kurla, Mumbai is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SOFRANCE WING A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SOFRANCE WING A's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SOFRANCE WING A in Kurla, Mumbai is P51800007146.

Is SOFRANCE WING A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A is registered as P51800007146 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: quarterly reports not filed. MahaRERA has put this project in abeyance for not filing its quarterly progress reports (August 2017). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SOFRANCE WING A is 12% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SOFRANCE WING A have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SOFRANCE WING A safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A is registered on MahaRERA as P51800007146, its completion date has moved 48 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: quarterly reports not filed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SOFRANCE WING A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SOFRANCE WING B (P51800006959, possession 30 Dec 2022). Check that your agreement names the registration of your own wing.

How can I get updates if SOFRANCE WING A's possession date changes?

The latest dates are on SOFRANCE WING A's MahaRERA page (P51800007146). GharKundli's Kundli Watch sends a free WhatsApp update on SOFRANCE WING A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SOFRANCE WING A have?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A has one building filed: SOFRANCE WING A with 17 floors and 80 units.

How big is the land of SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A stands on 4,976 sq m of land (about 1.2 acres), with 4,939 sq m of sanctioned built-up area and 142 sq m of recreational open space.

What is the track record of SOFRANCE WING A's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Daga Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 18 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SOFRANCE WING A?

Google Maps has reviews of SOFRANCE WING A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SOFRANCE WING A?

SOFRANCE WING A by DAGA DEVELOPERS PRIVATE LIMITED is in Kurla, Mumbai (pincode 400075), near Ghatkopar East, Pant Nagar, Ghatkopar Kirol, Maharashtra, and is registered on MahaRERA as P51800007146, per GharKundli's check of MahaRERA records. Its boundaries filed there include ANDHERI GHATKOPAR LINK ROAD, SAVITRIBAI PHULE NAGAR, SWAMI SAMARTH ROAD.

How many homes are in SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A has 76 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.

When was SOFRANCE WING A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SOFRANCE WING A was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SOFRANCE WING A?

2 court cases are listed for SOFRANCE WING A on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SOFRANCE WING A?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DAGA DEVELOPERS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

All projects in Ghatkopar East (400075) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.