SAI DWARKA RESIDENCY
by HARI OM CONSTRUCTION · Gauripada, Thane
Possession date of SAI DWARKA RESIDENCY: 30 October 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053053, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI DWARKA RESIDENCY?
How the possession date of SAI DWARKA RESIDENCY has moved
30 June 2028
Completion date given when the project was registered
30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI DWARKA RESIDENCY’s extension records on MahaRERA (P51700053053), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI DWARKA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053053
- Status
- Registered and active
- Builder
- HARI OM CONSTRUCTION
- Location
- Gauripada, Thane · 421301
- Project type
- Others
- Registered on
- 12 Oct 2023
- Completion date at registration
- June 2028
- Latest completion date
- October 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 148
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of SAI DWARKA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI DWARKA RESIDENCY | 100% | 100% | 84% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAI DWARKA RESIDENCY: covers 24 floors
Latest CC order on MahaRERA: dated 27/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI DWARKA RESIDENCY every month.
SAI DWARKA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI DWARKA RESIDENCY (24 floors, 157 units)
- Car parking: 96 open
- Land: 3,230 sq m (about 0.8 acres) · sanctioned built-up 10,739 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI DWARKA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI DWARKA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI DWARKA RESIDENCY
What is the possession date of SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI DWARKA RESIDENCY in Gauripada, Thane is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI DWARKA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI DWARKA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI DWARKA RESIDENCY in Gauripada, Thane is P51700053053.
Is SAI DWARKA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY is registered as P51700053053 and its status is "Registered and active".
What is the construction status of SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DWARKA RESIDENCY is 100% done and internal work 84%. GharKundli's full report compares construction progress with the deadline.
Does SAI DWARKA RESIDENCY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI DWARKA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY is registered on MahaRERA as P51700053053, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI DWARKA RESIDENCY's possession date changes?
The latest dates are on SAI DWARKA RESIDENCY's MahaRERA page (P51700053053). GharKundli's Kundli Watch sends a free WhatsApp update on SAI DWARKA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI DWARKA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY has one building filed: SAI DWARKA RESIDENCY with 24 floors and 157 units.
How much parking does SAI DWARKA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 96 open car parking spaces for SAI DWARKA RESIDENCY.
How big is the land of SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY stands on 3,230 sq m of land (about 0.8 acres), with 10,739 sq m of sanctioned built-up area.
Where can I read reviews of SAI DWARKA RESIDENCY?
Google Maps has reviews of SAI DWARKA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI DWARKA RESIDENCY?
SAI DWARKA RESIDENCY by HARI OM CONSTRUCTION is in Gauripada, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700053053, per GharKundli's check of MahaRERA records.
How many homes are in SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY has 148 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was SAI DWARKA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI DWARKA RESIDENCY was registered on MahaRERA on 12 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI DWARKA RESIDENCY?
No court cases are listed for SAI DWARKA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI DWARKA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARI OM CONSTRUCTION, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI DWARKA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Gauripada
- Kailash Homes
- JAI GURUJI TOWER
- AMRUT PEARL BUILDING NO 1
- AMRUT PEARL BUILDING NO. 5 AND 6
- AMRUT PEARL BUILDING NO 2
Other projects by HARI OM CONSTRUCTION
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.