GharKundli

Parvati Niwas

by AADARSH DEVELOPERS · Naupada, Thane

Possession date of Parvati Niwas: 30 April 2028, moved from 31 December 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700052981, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Parvati Niwas?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Parvati Niwas has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA25122518998)

    Reason the builder gave MahaRERA:
    “The current facts of the case are being explained hereunder. The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected t…” Read the full reason“The current facts of the case are being explained hereunder. The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/12/2025. Though almost all units available for sale are sold, pace of sale is very slow due to many reasons. In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contributed the delay.…”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Parvati Niwas’s extension records on MahaRERA (P51700052981), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Parvati Niwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700052981
Status
Registered and active
Builder
AADARSH DEVELOPERS
Location
Naupada, Thane · 400602
Project type
Residential / Group Housing
Registered on
10 Oct 2023
Completion date at registration
December 2025
Latest completion date
April 2028
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
54
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Parvati Niwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Parvati Niwas100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • Parvati Niwas: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Parvati Niwas every month.

Parvati Niwas: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK315 – 37727
2 BHK526 – 54414
Shops66 – 23112
1 Room Kitchen2181
  • Buildings: Parvati Niwas (8 floors, 54 units)
  • Land: 811 sq m (about 0.2 acres) · sanctioned built-up 2,730 sq m
  • Boundaries filed include: Veer Bajiprabhu Deshpande Marg

The builder’s record and reviews

Aadarsh Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2023, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Parvati Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Parvati Niwas: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Parvati Niwas

What is the possession date of Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Parvati Niwas in Naupada, Thane is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Parvati Niwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Parvati Niwas's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Parvati Niwas extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The current facts of the case are being explained hereunder. The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/12/2025. Though almost all units available for sale are sold, pace of sale is very slow due to many reasons. In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contributed the delay.…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Parvati Niwas in Naupada, Thane is P51700052981.

Is Parvati Niwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas is registered as P51700052981 and its status is "Registered and active".

What is the construction status of Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Parvati Niwas is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Parvati Niwas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Parvati Niwas safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas is registered on MahaRERA as P51700052981, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Parvati Niwas's possession date changes?

The latest dates are on Parvati Niwas's MahaRERA page (P51700052981). GharKundli's Kundli Watch sends a free WhatsApp update on Parvati Niwas every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Parvati Niwas have?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas has one building filed: Parvati Niwas with 8 floors and 54 units.

What are the flat sizes (carpet area) in Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Parvati Niwas: 1 BHK: 315 to 377 sq ft carpet (27 homes); 2 BHK: 526 to 544 sq ft carpet (14 homes); Shops: 66 to 231 sq ft carpet (12 homes); 1 Room Kitchen: 218 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas stands on 811 sq m of land (about 0.2 acres), with 2,730 sq m of sanctioned built-up area.

What is the track record of Parvati Niwas's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aadarsh Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2023, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Parvati Niwas?

Google Maps has reviews of Parvati Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Parvati Niwas?

Parvati Niwas by AADARSH DEVELOPERS is in Naupada, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700052981, per GharKundli's check of MahaRERA records. Its boundaries filed there include Veer Bajiprabhu Deshpande Marg.

How many homes are in Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas has 54 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Parvati Niwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parvati Niwas was registered on MahaRERA on 10 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Parvati Niwas?

No court cases are listed for Parvati Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Parvati Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AADARSH DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in pincode 400602

All 258 projects in Naupada (400602) →

Other projects by AADARSH DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.