Lodha Palava -Signet 2

by Lodha Developers Limited · Kole, Thane 421204Registered on MahaRERA as “Palava -Signet 2”

What’s in the report? →

Possession date of Lodha Palava -Signet 2 (MahaRERA P51700054751): 31 July 2027. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700054751, and currently active.

Source: MahaRERA website — records for P51700054751, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Lodha Palava -Signet 2?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Lodha Palava -Signet 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700054751
Status
Registered and active
Builder
Lodha Developers Limited
Location
Kole, Thane · 421204
Project type
Commercial
Registered on
12 Feb 2024
Completion date at registration
July 2027
Homes
0
Sold or booked
74%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Lodha Palava -Signet 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Commercial Bldg Signet P2100%45%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Commercial Bldg Signet P2: covers 10 floors

Latest CC order on MahaRERA: dated 30/12/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Palava -Signet 2 every 1–2 months.

Lodha Palava -Signet 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Commercial Bldg Signet P2 (10 floors, 517 units)
  • Land: 4,349 sq m (about 1.1 acres) · sanctioned built-up 15,604 sq m · recreational space 2,829 sq m
  • Land, as filed: 26 Part,27 Part,46 Part,53 Part,59/1 Part Gharivali ,21 Part,76 Part Kole
  • Map: Get directions

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Lodha Palava -Signet 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha Palava -Signet 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lodha Palava -Signet 2

What is the possession date of Lodha Palava -Signet 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Palava -Signet 2 in Kole, Thane is 31 July 2027.

Is the builder's possession date different from the MahaRERA date for Lodha Palava -Signet 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Palava -Signet 2's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lodha Palava -Signet 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Palava -Signet 2 in Kole, Thane is P51700054751.

Is Lodha Palava -Signet 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 is registered as P51700054751 and its status is "Registered and active".

What is the current construction status of Lodha Palava -Signet 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Commercial Bldg Signet P2 is 45% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Lodha Palava -Signet 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lodha Palava -Signet 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 is registered on MahaRERA as P51700054751, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lodha Palava -Signet 2?

Lodha Palava -Signet 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lodha Palava -Signet 2?

For a flat in Lodha Palava -Signet 2 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lodha Palava -Signet 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Lodha Palava -Signet 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha Palava -Signet 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Lodha Palava -Signet 2's possession date changes?

The latest dates are on Lodha Palava -Signet 2's MahaRERA page (P51700054751). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Palava -Signet 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha Palava -Signet 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 has one building filed: Commercial Bldg Signet P2 with 10 floors and 517 units.

How big is the land of Lodha Palava -Signet 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 stands on 4,349 sq m of land (about 1.1 acres), with 15,604 sq m of sanctioned built-up area and 2,829 sq m of recreational open space.

What is the track record of Lodha Palava -Signet 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lodha Palava -Signet 2?

Google Maps has reviews of Lodha Palava -Signet 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lodha Palava -Signet 2?

Lodha Palava -Signet 2 by Lodha Developers Limited is in Kole, Thane, pincode 421204, Maharashtra, and is registered on MahaRERA as P51700054751, per GharKundli's check of MahaRERA records. Its land is filed as 26 Part,27 Part,46 Part,53 Part,59/1 Part Gharivali ,21 Part,76 Part Kole. GharKundli lists all 252 MahaRERA projects in Manpada (421204).

How many flats are in Lodha Palava -Signet 2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 has 0 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.

When was Lodha Palava -Signet 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Palava -Signet 2 was registered on MahaRERA on 12 February 2024. GharKundli did not find a title report on the land on file there.

Does Lodha Palava -Signet 2 have any legal issues or court cases?

No court cases are listed for Lodha Palava -Signet 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Lodha Palava -Signet 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Manpada (421204)

All 252 projects in Manpada (421204) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.