Vardhaman Enclave
by Vardhaman Builders · Bhayander West, Thane
Possession date of Vardhaman Enclave: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700076855, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vardhaman Enclave?
How the possession date of Vardhaman Enclave has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA21012619525)
Reason the builder gave MahaRERA:
“Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2026 to complete the project. No Sold U…” Read the full reason
“Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2026 to complete the project. No Sold Units in This Project.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vardhaman Enclave’s extension records on MahaRERA (P51700076855), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vardhaman Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700076855
- Status
- Registered and active
- Builder
- Vardhaman Builders
- Location
- Bhayander West, Thane · 401101
- Project type
- Residential / Group Housing
- Registered on
- 3 Jul 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Vardhaman Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1A | 100% | 100% | 40% | 20% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1A: covers G+7 FLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vardhaman Enclave every month.
Vardhaman Enclave: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1A (8 floors, 14 units)
- Car parking: 4 covered
- Land: 2,100 sq m (about 0.5 acres) · sanctioned built-up 789 sq m
The builder’s record and reviews
Vardhaman Builders has 3 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Vardhaman Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vardhaman Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vardhaman Enclave
What is the possession date of Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vardhaman Enclave in Bhayander West, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vardhaman Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vardhaman Enclave's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vardhaman Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2026 to complete the project. No Sold Units in This Project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vardhaman Enclave in Bhayander West, Thane is P51700076855.
Is Vardhaman Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave is registered as P51700076855 and its status is "Registered and active".
What is the construction status of Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No 1A is 100% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does Vardhaman Enclave have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vardhaman Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave is registered on MahaRERA as P51700076855, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vardhaman Enclave's possession date changes?
The latest dates are on Vardhaman Enclave's MahaRERA page (P51700076855). GharKundli's Kundli Watch sends a free WhatsApp update on Vardhaman Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vardhaman Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave has one building filed: Building No 1A with 8 floors and 14 units.
How much parking does Vardhaman Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered car parking spaces for Vardhaman Enclave.
How big is the land of Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave stands on 2,100 sq m of land (about 0.5 acres), with 789 sq m of sanctioned built-up area.
What is the track record of Vardhaman Enclave's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Builders has 3 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vardhaman Enclave?
Google Maps has reviews of Vardhaman Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vardhaman Enclave?
Vardhaman Enclave by Vardhaman Builders is in Bhayander West, Thane (pincode 401101), Maharashtra, and is registered on MahaRERA as P51700076855, per GharKundli's check of MahaRERA records.
How many homes are in Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave has 14 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Vardhaman Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Enclave was registered on MahaRERA on 3 July 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Vardhaman Enclave?
No court cases are listed for Vardhaman Enclave on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Vardhaman Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vardhaman Builders, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vardhaman Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 401101
- MUKUNDAM
- IMPERIAL RESIDENCY
- Sudama Vallabh wing A,B,C
- Anantsavitri Ratna Heights
- North Westend Tower 1
- MAN MANDIR
- North Westend Tower 2
- SALASAR GRANDEUR II
Other projects by Vardhaman Builders
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.