Lodha Crown Dombivli 4
by Lodha Developers Limited · Mangaon, Thane 421203Registered on MahaRERA as “Crown Dombivli 4”
What’s in the report? →Possession date of Lodha Crown Dombivli 4 (MahaRERA P51700056338): 30 October 2028. It has 276 homes, 68% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700056338, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700056338, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Lodha Crown Dombivli 4?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Lodha Crown Dombivli 4 has moved
30 June 2028
Completion date given when the project was registered
30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lodha Crown Dombivli 4’s extension records on MahaRERA (P51700056338), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lodha Crown Dombivli 4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Crown Dombivli 1P51700048779 · possession 31 Dec 2028
- Crown Dombivli 2P51700049154 · possession 31 Dec 2028
- Crown Dombivli 3P51700053191 · possession 31 Dec 2027
- MahaRERA registration
- P51700056338
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Mangaon, Thane · 421203
- Project type
- Residential / Group Housing
- Registered on
- 29 May 2024
- Completion date at registration
- June 2028
- Latest completion date
- October 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 276
- Sold or booked
- 68%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Lodha Crown Dombivli 4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ruby F | 0% | 100% | 36% | 0% |
| Ruby G | 0% | 100% | 36% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Ruby F: covers 15 floors
- Ruby G: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Crown Dombivli 4 every 1–2 months.
Lodha Crown Dombivli 4: buildings, flats and land, as filed on MahaRERA
- Buildings: Ruby F (15 floors, 150 units) · Ruby G (15 floors, 126 units)
- Land: 1,965 sq m (about 0.5 acres) · sanctioned built-up 11,536 sq m · recreational space 1,111 sq m
- Land, as filed: 60/7 Part
- Map: Get directions
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 602 complaints on MahaRERA across 163 projects.
Read Google reviews of Lodha Crown Dombivli 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lodha Crown Dombivli 4: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Lodha Crown Dombivli 4
What is the possession date of Lodha Crown Dombivli 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Crown Dombivli 4 in Mangaon, Thane is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Lodha Crown Dombivli 4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Crown Dombivli 4's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Lodha Crown Dombivli 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Crown Dombivli 4 in Mangaon, Thane is P51700056338.
Is Lodha Crown Dombivli 4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 is registered as P51700056338 and its status is "Registered and active".
What is the current construction status of Lodha Crown Dombivli 4? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Lodha Crown Dombivli 4 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Lodha Crown Dombivli 4 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 is registered on MahaRERA as P51700056338, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Lodha Crown Dombivli 4?
Lodha Crown Dombivli 4 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Lodha Crown Dombivli 4?
For a flat in Lodha Crown Dombivli 4 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Lodha Crown Dombivli 4 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Lodha Crown Dombivli 4 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha Crown Dombivli 4 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Lodha Crown Dombivli 4 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Crown Dombivli 1 (P51700048779, possession 31 Dec 2028); Crown Dombivli 2 (P51700049154, possession 31 Dec 2028); Crown Dombivli 3 (P51700053191, possession 31 Dec 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Lodha Crown Dombivli 4's possession date changes?
The latest dates are on Lodha Crown Dombivli 4's MahaRERA page (P51700056338). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Crown Dombivli 4 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lodha Crown Dombivli 4 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 has 2 buildings filed: Ruby F with 15 floors and 150 units; Ruby G with 15 floors and 126 units.
How big is the land of Lodha Crown Dombivli 4?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 stands on 1,965 sq m of land (about 0.5 acres), with 11,536 sq m of sanctioned built-up area and 1,111 sq m of recreational open space.
What is the track record of Lodha Crown Dombivli 4's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Lodha Crown Dombivli 4?
Google Maps has reviews of Lodha Crown Dombivli 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Lodha Crown Dombivli 4?
Lodha Crown Dombivli 4 by Lodha Developers Limited is in Mangaon, Thane, pincode 421203, Maharashtra, and is registered on MahaRERA as P51700056338, per GharKundli's check of MahaRERA records. Its land is filed as 60/7 Part. GharKundli lists all 98 MahaRERA projects in Dombivali (421203).
How many flats are in Lodha Crown Dombivli 4, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 has 276 homes in 2 towers registered on MahaRERA, and 68% of them are sold or booked.
When was Lodha Crown Dombivli 4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Crown Dombivli 4 was registered on MahaRERA on 29 May 2024. GharKundli did not find a title report on the land on file there.
Does Lodha Crown Dombivli 4 have any legal issues or court cases?
No court cases are listed for Lodha Crown Dombivli 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Lodha Crown Dombivli 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lodha Crown Dombivli 4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Dombivali (421203)
- Crown Dombivli 1
- Crown Dombivli 3
- Crown Dombivli 2
- Liana D
- Jasper C and D
- Patel Heritage
- The Landmark
- Mahalaxmi Nivara
Other projects by Lodha Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.