Borgaonkar Harihar Darshan
by Borgaonkar Realty · Khadakpada, Thane 421301Registered on MahaRERA as “HARIHAR DARSHAN”
What’s in the report? →Possession date of Borgaonkar Harihar Darshan (MahaRERA P51700079018): 30 April 2027. It has 29 homes, 54% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700079018, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700079018, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Borgaonkar Harihar Darshan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Borgaonkar Harihar Darshan has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Borgaonkar Harihar Darshan’s extension records on MahaRERA (P51700079018), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Borgaonkar Harihar Darshan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700079018
- Status
- Registered and active
- Builder
- Borgaonkar Realty
- Location
- Khadakpada, Thane · 421301
- Project type
- Mixed
- Registered on
- 31 Jan 2025
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 29
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Borgaonkar Harihar Darshan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HARIHAR DARSHAN CO-OP HOUSING SOCIETY LIMITED | 100% | 100% | 90% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- HARIHAR DARSHAN CO-OP HOUSING SOCIETY LIMITED: covers 7 floors
Latest CC order on MahaRERA: dated 06/06/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Borgaonkar Harihar Darshan every 1–2 months.
Borgaonkar Harihar Darshan: buildings, flats and land, as filed on MahaRERA
- Buildings: HARIHAR DARSHAN CO-OP HOUSING SOCIETY LIMITED (7 floors, 44 units)
- Car parking: 20 covered
- Land: 610 sq m (about 0.2 acres) · sanctioned built-up 1,998 sq m
- Land, as filed: 29/11, 29/17 P Plot no 50, 51 CTS No 195, 196, 197
- Map: Get directions
The builder’s record and reviews
Borgaonkar Realty (a group of 5 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Borgaonkar Harihar Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Borgaonkar Harihar Darshan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Borgaonkar Harihar Darshan
What is the possession date of Borgaonkar Harihar Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Borgaonkar Harihar Darshan in Khadakpada, Thane is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Borgaonkar Harihar Darshan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Borgaonkar Harihar Darshan's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Borgaonkar Harihar Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Borgaonkar Harihar Darshan in Khadakpada, Thane is P51700079018.
Is Borgaonkar Harihar Darshan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan is registered as P51700079018 and its status is "Registered and active".
What is the current construction status of Borgaonkar Harihar Darshan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HARIHAR DARSHAN CO-OP HOUSING SOCIETY LIMITED is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Borgaonkar Harihar Darshan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Borgaonkar Harihar Darshan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan is registered on MahaRERA as P51700079018, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Borgaonkar Harihar Darshan?
Borgaonkar Harihar Darshan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Borgaonkar Harihar Darshan?
For a flat in Borgaonkar Harihar Darshan (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Borgaonkar Harihar Darshan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Borgaonkar Harihar Darshan a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan's planning authority on MahaRERA is Kalyan-Dombivli Municipal Corporation, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Borgaonkar Harihar Darshan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Borgaonkar Harihar Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Borgaonkar Harihar Darshan's possession date changes?
The latest dates are on Borgaonkar Harihar Darshan's MahaRERA page (P51700079018). GharKundli's Kundli Watch sends a free WhatsApp update on Borgaonkar Harihar Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Borgaonkar Harihar Darshan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan has one building filed: HARIHAR DARSHAN CO-OP HOUSING SOCIETY LIMITED with 7 floors and 44 units.
How much parking does Borgaonkar Harihar Darshan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered car parking spaces for Borgaonkar Harihar Darshan.
How big is the land of Borgaonkar Harihar Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan stands on 610 sq m of land (about 0.2 acres), with 1,998 sq m of sanctioned built-up area.
What is the track record of Borgaonkar Harihar Darshan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Realty (a group of 5 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Borgaonkar Harihar Darshan?
Google Maps has reviews of Borgaonkar Harihar Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Borgaonkar Harihar Darshan?
Borgaonkar Harihar Darshan by Borgaonkar Realty is in Khadakpada, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700079018, per GharKundli's check of MahaRERA records. Its land is filed as 29/11, 29/17 P Plot no 50, 51 CTS No 195, 196, 197. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Borgaonkar Harihar Darshan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan has 29 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was Borgaonkar Harihar Darshan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Borgaonkar Harihar Darshan was registered on MahaRERA on 31 January 2025. GharKundli did not find a title report on the land on file there.
Does Borgaonkar Harihar Darshan have any legal issues or court cases?
No court cases are listed for Borgaonkar Harihar Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Borgaonkar Harihar Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Borgaonkar Realty, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Borgaonkar Harihar Darshan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan (421301)
- Laxmi Pride
- Sarvodaya Classic
- Tycoons Valley Tower A
- GNP Landmark
- 36 Mansions A wing
- Heaven Enclave
- Mohan Altezza III
- Mohan Tribeca
Other projects by Borgaonkar Realty
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.