The Cosmopolis
by VISHAL SANJAY GALANDE · Vadgaon Sheri, Pune 411028Also near Mundhwa, Hadapsar, Amanora Park Town
What’s in the report? →Possession date of The Cosmopolis (MahaRERA P52100001149): 30 October 2020, moved from 15 September 2019 (13 months later), and it has already passed. It has 41 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100001149. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100001149, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2020) has passed.
What do you want to know about The Cosmopolis?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of The Cosmopolis has moved
15 September 2019
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100005373)
Reason the builder gave MahaRERA:
“I HAVE TAKEN PART COMPLETITION OF THE SAID BUILDING AND SAME HAS BEEN UPLOADED IN PROJECT DETAILS UNDER COMPLETITION CERTIFICATE TAB. I HAVE TAKEN ALL NOC'S EXCEPT CAR LIFT , FIRE NOC'S AND GARDEN NOC. WHICH I WILL RECEIVE BY NOVEMBER END.…” Read the full reason
“I HAVE TAKEN PART COMPLETITION OF THE SAID BUILDING AND SAME HAS BEEN UPLOADED IN PROJECT DETAILS UNDER COMPLETITION CERTIFICATE TAB. I HAVE TAKEN ALL NOC'S EXCEPT CAR LIFT , FIRE NOC'S AND GARDEN NOC. WHICH I WILL RECEIVE BY NOVEMBER END. AFTER WHICH I WILL APPLY FOR FULL COMPLETION OF BUILDING. CONSTRUCTION WORK IS ALSO COMPLETED 95%. I HAVE ALSO STARTED SOCIETY REGISTRATION WORK. REQUEST YOU TO KINDLY GRANT ME EXTENSION TILL 30/12/2019. THANKYOU.”30 October 2020
Revised completion date on MahaRERA
Source: The Cosmopolis’s extension records on MahaRERA (P52100001149), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Cosmopolis
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001149
- Status
- Lapsed (registration period ended)
- Builder
- VISHAL SANJAY GALANDE
- Location
- Vadgaon Sheri, Pune · 411028
- Project type
- Others
- Registered on
- 26 Jul 2017
- Completion date at registration
- September 2019
- Latest completion date
- October 2020
- Delay so far
- 13 months
- Homes
- 41
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of The Cosmopolis, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THE COSMOPOLIS | 100% | 100% | 100% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Cosmopolis every 1–2 months.
The Cosmopolis: buildings, flats and land, as filed on MahaRERA
- Buildings: THE COSMOPOLIS (12 floors)
- Land: 1,400 sq m (about 0.3 acres) · sanctioned built-up 2,224 sq m
- Boundaries filed include: MAGARPATTA MUNDHWA ROAD
- Land, as filed: 138/9,138/11
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Cosmopolis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Cosmopolis: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about The Cosmopolis
What is the possession date of The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Cosmopolis in Vadgaon Sheri, Pune is 30 October 2020 — 13 months later than 15 September 2019, the date given at registration. That date has already passed.
The date has already moved 13 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for The Cosmopolis?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Cosmopolis's builder has filed on MahaRERA, the official one, is 30 October 2020, already 13 months later than the 15 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Cosmopolis extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis's builder applied to MahaRERA to extend the completion date once: to 30 April 2020, giving the reason "I HAVE TAKEN PART COMPLETITION OF THE SAID BUILDING AND SAME HAS BEEN UPLOADED IN PROJECT DETAILS UNDER COMPLETITION CERTIFICATE TAB. I HAVE TAKEN ALL NOC'S EXCEPT CAR LIFT , FIRE NOC'S AND GARDEN NOC. WHICH I WILL RECEIVE BY NOVEMBER END. AFTER WHICH I WILL APPLY FOR FULL COMPLETION OF BUILDING. CONSTRUCTION WORK IS ALSO COMPLETED 95%. I HAVE ALSO STARTED SOCIETY REGISTRATION WORK. REQUEST YOU TO KINDLY GRANT ME EXTENSION TILL 30/12/2019. THANKYOU.".
What is the RERA number of The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Cosmopolis in Vadgaon Sheri, Pune is P52100001149.
Is The Cosmopolis registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis is registered as P52100001149 and its status is "Lapsed (registration period ended)".
What is the current construction status of The Cosmopolis? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on THE COSMOPOLIS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does The Cosmopolis have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is The Cosmopolis safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis is registered on MahaRERA as P52100001149, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in The Cosmopolis?
The Cosmopolis isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in The Cosmopolis?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The Cosmopolis: gharkundli.com/tools/property-cost-calculator
Has The Cosmopolis received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has The Cosmopolis uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for The Cosmopolis was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if The Cosmopolis's possession date changes?
The latest dates are on The Cosmopolis's MahaRERA page (P52100001149). GharKundli's Kundli Watch sends a free WhatsApp update on The Cosmopolis every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Cosmopolis have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis has one building filed: THE COSMOPOLIS with 12 floors.
How big is the land of The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis stands on 1,400 sq m of land (about 0.3 acres), with 2,224 sq m of sanctioned built-up area.
What are the reviews of The Cosmopolis?
Google Maps has reviews of The Cosmopolis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of The Cosmopolis?
The Cosmopolis by VISHAL SANJAY GALANDE is in Vadgaon Sheri, Pune, pincode 411028 (near Mundhwa, Hadapsar, Amanora Park Town), Maharashtra, and is registered on MahaRERA as P52100001149, per GharKundli's check of MahaRERA records. Its boundaries filed there include MAGARPATTA MUNDHWA ROAD. Its land is filed as 138/9,138/11. GharKundli lists all 301 MahaRERA projects in Hadapsar (411028).
How many flats are in The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis has 41 homes in 1 tower registered on MahaRERA.
When was The Cosmopolis registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Cosmopolis was registered on MahaRERA on 26 July 2017. GharKundli did not find a title report on the land on file there.
Does The Cosmopolis have any legal issues or court cases?
No court cases are listed for The Cosmopolis on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of The Cosmopolis?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISHAL SANJAY GALANDE.
Check it yourself on MahaRERA
- How to check the possession date of The Cosmopolis
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- Urban Nest Phase1
- Shriram Pride Building
- Que 101 Phase I
- Balwant Empire
- Madhughat
- Ats - the Condominiums
- Dynamic Solitaire – Phase II
- Siddhi Aurum
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.