Aqura Paradise
by AQURA BUILDER & DEVELOPER PRIVATE LIMITED · Near National Highway Bridge, Pune 411016Also near Shivajinagar, Shivaji Nagar, Model Colony
What’s in the report? →Possession date of Aqura Paradise (MahaRERA P52100000498): 30 June 2022, moved from 31 January 2020 (29 months later), and it has already passed. It has 28 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100000498. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100000498, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about Aqura Paradise?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aqura Paradise has moved
31 January 2020
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100005631)
Reason the builder gave MahaRERA: “Due to rules imposed by Ministry of Defense to get NOC from Aviation Authority and the poor market condition we were unable to complete the project within the due date.”
30 June 2021
Extended at the builder's request (MahaRERA application EXT52100009026)
Reason the builder gave MahaRERA: “Due to unprecedented condition arises due to COVID-19 pandemic and poor market condition afterward we are unable to complete the project within the due time.”
31 December 2021
Extended at the builder's request (MahaRERA application EXT52100010461)
Reason the builder gave MahaRERA: “Due to Pandamic of Covid 19”
30 June 2022
Revised completion date on MahaRERA
Source: Aqura Paradise’s extension records on MahaRERA (P52100000498), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aqura Paradise
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100000498
- Status
- Lapsed (registration period ended)
- Builder
- AQURA BUILDER & DEVELOPER PRIVATE LIMITED
- Location
- Near National Highway Bridge, Pune · 411016
- Project type
- Residential / Group Housing
- Registered on
- 18 Jul 2017
- Completion date at registration
- January 2020
- Latest completion date
- June 2022
- Delay so far
- 29 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Aqura Paradise, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AQURA PARADISE | 100% | 100% | 95% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aqura Paradise every 1–2 months.
Aqura Paradise: buildings, flats and land, as filed on MahaRERA
- Buildings: AQURA PARADISE (10 floors)
- Land: 682 sq m (about 0.2 acres) · sanctioned built-up 682 sq m · recreational space 235 sq m
- Land, as filed: CTS NO 953, FPN 336/1
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Aqura Builder And Developer has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 1 project.
Read Google reviews of Aqura Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aqura Paradise: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aqura Paradise
What is the possession date of Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aqura Paradise in Near National Highway Bridge, Pune is 30 June 2022 — 29 months later than 31 January 2020, the date given at registration. That date has already passed.
The date has already moved 29 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aqura Paradise?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aqura Paradise's builder has filed on MahaRERA, the official one, is 30 June 2022, already 29 months later than the 31 January 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aqura Paradise extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "Due to rules imposed by Ministry of Defense to get NOC from Aviation Authority and the poor market condition we were unable to complete the project within the due date."; to 30 June 2021, giving the reason "Due to unprecedented condition arises due to COVID-19 pandemic and poor market condition afterward we are unable to complete the project within the due time."; to 31 December 2021, giving the reason "Due to Pandamic of Covid 19".
What is the RERA number of Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aqura Paradise in Near National Highway Bridge, Pune is P52100000498.
Is Aqura Paradise registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise is registered as P52100000498 and its status is "Lapsed (registration period ended)".
What is the current construction status of Aqura Paradise? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AQURA PARADISE is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Aqura Paradise have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aqura Paradise safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise is registered on MahaRERA as P52100000498, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aqura Paradise?
Aqura Paradise isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aqura Paradise?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aqura Paradise: gharkundli.com/tools/property-cost-calculator
Has Aqura Paradise received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Aqura Paradise uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aqura Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aqura Paradise's possession date changes?
The latest dates are on Aqura Paradise's MahaRERA page (P52100000498). GharKundli's Kundli Watch sends a free WhatsApp update on Aqura Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aqura Paradise have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise has one building filed: AQURA PARADISE with 10 floors.
How big is the land of Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise stands on 682 sq m of land (about 0.2 acres), with 682 sq m of sanctioned built-up area and 235 sq m of recreational open space.
What is the track record of Aqura Paradise's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Builder And Developer has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Aqura Paradise?
Google Maps has reviews of Aqura Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aqura Paradise?
Aqura Paradise by AQURA BUILDER & DEVELOPER PRIVATE LIMITED is in Near National Highway Bridge, Pune, pincode 411016 (near Shivajinagar, Shivaji Nagar, Model Colony), Maharashtra, and is registered on MahaRERA as P52100000498, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 953, FPN 336/1. GharKundli lists all 83 MahaRERA projects in Model Colony (411016).
How many flats are in Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise has 28 homes in 1 tower registered on MahaRERA.
When was Aqura Paradise registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aqura Paradise was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Does Aqura Paradise have any legal issues or court cases?
No court cases are listed for Aqura Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Aqura Paradise?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AQURA BUILDER & DEVELOPER PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Aqura Paradise
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pune City
- Swamipushpa
- Wyng
- Hrishikesh and Vasantili Apartment
- Hibiscus
- Shree Gauri
- Purva Aspire
- Triveni Co-operative Housing Society Ltd PH 2
- Godavari Apartment Condominium
Other projects by AQURA BUILDER & DEVELOPER PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.