Eshaanya Phase 1

by Ashwyn Suresh Patkar · Dhamni, Raigarh

Registered on MahaRERA under P52000000305. Status: Completed. Its completion date has moved from July 2023 to December 2025, 29 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Eshaanya Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000000305
Status
Completed
Builder
Ashwyn Suresh Patkar
Location
Dhamni, Raigarh · 410201
Project type
Plotted
Registered on
15 Jul 2017
Completion date at registration
July 2023
Latest completion date
December 2025
Delay so far
29 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Eshaanya Phase 1: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Eshaanya Phase 1

Is Eshaanya Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eshaanya Phase 1 is registered as P52000000305 and its status is "Completed".

Where is Eshaanya Phase 1?

Eshaanya Phase 1 by Ashwyn Suresh Patkar is in Dhamni, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000000305, per GharKundli's check of MahaRERA records.

When is possession of Eshaanya Phase 1 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Eshaanya Phase 1 in Dhamni, Raigarh is 31 December 2025 — 29 months later than 1 July 2023, the date given at registration.

Does Eshaanya Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Eshaanya Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashwyn Suresh Patkar.

Other projects in pincode 410201

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.