Baycastle
by Bhairav Realty · Nagothane, Raigarh
Possession date of Baycastle: 31 December 2023, moved from 31 December 2018 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000006668. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about Baycastle?
How the possession date of Baycastle has moved
31 December 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52000000960)
Reason the builder gave MahaRERA: “The constrution had s;owd down due to non availibity of sand required for constrution. we will complete the construction in revised time shedule.”
30 April 2020
Extended at the builder's request (MahaRERA application EXT52000005335)
Reason the builder gave MahaRERA:
“1) The Promoter respectfully submits that the project of the Promoter is at Alibaug, Nehuli Village. The Promoter has completed construction of two buildings and possession is given to about 70 Flat Purchasers. The Promoter state that the t…” Read the full reason
“1) The Promoter respectfully submits that the project of the Promoter is at Alibaug, Nehuli Village. The Promoter has completed construction of two buildings and possession is given to about 70 Flat Purchasers. The Promoter state that the third building will be ready by August, 2020 and the balance one building will be completed within December, 2020. 2) The Promoter states that the delay in completion of the project is mainly because of market conditions and unavailability of sand and construction materials. 3) The Promoter states that the extension of the project U/s 73 is sought on the g…”30 June 2021
Extended at the builder's request (MahaRERA application EXT52000008890)
Reason the builder gave MahaRERA:
“The Applicant most respectfully submits that initially the Applicant had applied for extension of the project along with consent terms however because of technical difficulties the consent terms were not shown on website though tried to be…” Read the full reason
“The Applicant most respectfully submits that initially the Applicant had applied for extension of the project along with consent terms however because of technical difficulties the consent terms were not shown on website though tried to be uploaded and therefore this honorable court was pleased to extend the project by 6 months only. The Applicant is annexing herewith the consents given by the flat purchasers again for extension of project. The Applicant most respectfully submits that the delay caused in completion of the project is mainly because of Covid 19 situation so also unavailabilit…”31 December 2022
Extended at the builder's request (MahaRERA application EXT52000011597)
Reason the builder gave MahaRERA:
“Due to covid 19 project got delayed but we consistently trying our best to deliver possession of on going buildings that are Amber A wing & building C Ruby. we already given possesion of 97 units in building B-Opal,F-Topaz,D-Emerald,A- Ambe…” Read the full reason
“Due to covid 19 project got delayed but we consistently trying our best to deliver possession of on going buildings that are Amber A wing & building C Ruby. we already given possesion of 97 units in building B-Opal,F-Topaz,D-Emerald,A- Amber B wing.Total Consent calculated as Possesion done 97 + consent of ongoing building 14 = 111. Request you to consider our case & grant us extension at earliest.”31 December 2023
Extended at the builder's request (MahaRERA application EXT52000013566)
Reason the builder gave MahaRERA:
“Dear sir/mam I am submitting consent obtained from customers, total number of buildings that are mentioned below A Amber -A wing ( consent obtained C ruby wing (consent obtained) A Amber - B ( Possession done) B Opal - (possession done) D E…” Read the full reason
“Dear sir/mam I am submitting consent obtained from customers, total number of buildings that are mentioned below A Amber -A wing ( consent obtained C ruby wing (consent obtained) A Amber - B ( Possession done) B Opal - (possession done) D Emerald (possession done) F Topaz (Possession done) Total sold flat in A - A Wing & C wing are 26 14 consent for obtained out of it that is 53.84 % Rest i am attaching possession letters of my existing customers who have taken possession. I request you grant me approval at earliest”
Source: Baycastle’s extension records on MahaRERA (P52000006668), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Baycastle
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000006668
- Status
- Lapsed (registration period ended)
- Builder
- Bhairav Realty
- Location
- Nagothane, Raigarh · 402201
- Project type
- Residential / Group Housing
- Registered on
- 16 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2023
- Delay so far
- 60 months
- Homes
- 141
- Towers
- 5
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Baycastle, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A named as Amber | 100% | 100% | 50% | 0% |
| B named as Opal | 100% | 100% | 100% | 100% |
| C named as Ruby | 100% | 0% | 0% | 0% |
| D named as Emerald | 100% | 100% | 100% | 100% |
| F named as Topaz | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Baycastle every month.
Baycastle: buildings, flats and land, as filed on MahaRERA
- Buildings: A named as Amber (6 floors) · B named as Opal (6 floors) · C named as Ruby (6 floors) · D named as Emerald (6 floors) · F named as Topaz (6 floors)
- Land: 8,763 sq m (about 2.2 acres) · sanctioned built-up 6,896 sq m · recreational space 1,116 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Kishor Otermal Jain has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 6 complaints on MahaRERA across 2 projects.
Read Google reviews of Baycastle →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Baycastle: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Baycastle
What is the possession date of Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Baycastle in Nagothane, Raigarh is 31 December 2023 — 60 months later than 31 December 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Baycastle?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Baycastle's builder has filed on MahaRERA, the official one, is 31 December 2023, already 60 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Baycastle extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle's builder applied to MahaRERA to extend the completion date 5 times: to 30 April 2020, giving the reason "The constrution had s;owd down due to non availibity of sand required for constrution. we will complete the construction in revised time shedule."; to 30 April 2020, giving the reason "1) The Promoter respectfully submits that the project of the Promoter is at Alibaug, Nehuli Village. The Promoter has completed construction of two buildings and possession is given to about 70 Flat Purchasers. The Promoter state that the third building will be ready by August, 2020 and the balance one building will be completed within December, 2020. 2) The Promoter states that the delay in completion of the project is mainly because of market conditions and unavailability of sand and construction materials. 3) The Promoter states that the extension of the project U/s 73 is sought on the g…"; to 30 June 2021, giving the reason "The Applicant most respectfully submits that initially the Applicant had applied for extension of the project along with consent terms however because of technical difficulties the consent terms were not shown on website though tried to be uploaded and therefore this honorable court was pleased to extend the project by 6 months only. The Applicant is annexing herewith the consents given by the flat purchasers again for extension of project. The Applicant most respectfully submits that the delay caused in completion of the project is mainly because of Covid 19 situation so also unavailabilit…"; to 31 December 2022, giving the reason "Due to covid 19 project got delayed but we consistently trying our best to deliver possession of on going buildings that are Amber A wing & building C Ruby. we already given possesion of 97 units in building B-Opal,F-Topaz,D-Emerald,A- Amber B wing.Total Consent calculated as Possesion done 97 + consent of ongoing building 14 = 111. Request you to consider our case & grant us extension at earliest."; to 31 December 2023, giving the reason "Dear sir/mam I am submitting consent obtained from customers, total number of buildings that are mentioned below A Amber -A wing ( consent obtained C ruby wing (consent obtained) A Amber - B ( Possession done) B Opal - (possession done) D Emerald (possession done) F Topaz (Possession done) Total sold flat in A - A Wing & C wing are 26 14 consent for obtained out of it that is 53.84 % Rest i am attaching possession letters of my existing customers who have taken possession. I request you grant me approval at earliest".
What is the RERA number of Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Baycastle in Nagothane, Raigarh is P52000006668.
Is Baycastle registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle is registered as P52000006668 and its status is "Lapsed (registration period ended)".
What is the construction status of Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Baycastle have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Baycastle safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle is registered on MahaRERA as P52000006668, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Baycastle's possession date changes?
The latest dates are on Baycastle's MahaRERA page (P52000006668). GharKundli's Kundli Watch sends a free WhatsApp update on Baycastle every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Baycastle have?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle has 5 buildings filed: A named as Amber with 6 floors; B named as Opal with 6 floors; C named as Ruby with 6 floors; D named as Emerald with 6 floors; F named as Topaz with 6 floors.
How big is the land of Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle stands on 8,763 sq m of land (about 2.2 acres), with 6,896 sq m of sanctioned built-up area and 1,116 sq m of recreational open space.
What is the track record of Baycastle's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kishor Otermal Jain has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Baycastle?
Google Maps has reviews of Baycastle written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Baycastle?
Baycastle by Bhairav Realty is in Nagothane, Raigarh (pincode 402201), Maharashtra, and is registered on MahaRERA as P52000006668, per GharKundli's check of MahaRERA records.
How many homes are in Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle has 141 homes in 5 towers registered on MahaRERA.
When was Baycastle registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Baycastle was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Baycastle?
No court cases are listed for Baycastle on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Baycastle?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Bhairav Realty, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Baycastle
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagothane
All 111 projects in Alibag (402201) →Other projects by Bhairav Realty
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.