AKSHAR ESTONIA
by VAGAD BUILDERS AND DEVELOPERS PRIVATE LIMITED · Vashi, Raigarh
Possession: AKSHAR ESTONIA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000004543. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about AKSHAR ESTONIA?
How the possession date of AKSHAR ESTONIA has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52000005195)
Reason the builder gave MahaRERA: “OC Rejected due to CRZ Procedural Compliance”
30 December 2021
Revised completion date on MahaRERA
Source: AKSHAR ESTONIA’s extension records on MahaRERA (P52000004543), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AKSHAR ESTONIA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000004543
- Status
- Completed
- Builder
- VAGAD BUILDERS AND DEVELOPERS PRIVATE LIMITED
- Location
- Vashi, Raigarh · 400702
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 355
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AKSHAR ESTONIA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 100% | 100% | 100% | 100% |
| C | 100% | 100% | 100% | 100% |
| D | 100% | 100% | 100% | 100% |
| SHOPS | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAR ESTONIA every month.
AKSHAR ESTONIA: buildings, flats and land, as filed on MahaRERA
- Buildings: A (18 floors) · B (17 floors) · C (17 floors) · D (17 floors) · SHOPS (2 floors)
- Land: 13,292 sq m (about 3.3 acres) · sanctioned built-up 19,938 sq m · recreational space 3,589 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AKSHAR ESTONIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AKSHAR ESTONIA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AKSHAR ESTONIA
What is the possession date of AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AKSHAR ESTONIA in Vashi, Raigarh is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AKSHAR ESTONIA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAR ESTONIA's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AKSHAR ESTONIA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "OC Rejected due to CRZ Procedural Compliance".
What is the RERA number of AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AKSHAR ESTONIA in Vashi, Raigarh is P52000004543.
Is AKSHAR ESTONIA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA is registered as P52000004543 and its status is "Completed".
What is the construction status of AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does AKSHAR ESTONIA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AKSHAR ESTONIA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA is registered on MahaRERA as P52000004543, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AKSHAR ESTONIA's possession date changes?
The latest dates are on AKSHAR ESTONIA's MahaRERA page (P52000004543). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAR ESTONIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AKSHAR ESTONIA have?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA has 5 buildings filed: A with 18 floors; B with 17 floors; C with 17 floors; D with 17 floors; SHOPS with 2 floors.
How big is the land of AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA stands on 13,292 sq m of land (about 3.3 acres), with 19,938 sq m of sanctioned built-up area and 3,589 sq m of recreational open space.
Where can I read reviews of AKSHAR ESTONIA?
Google Maps has reviews of AKSHAR ESTONIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AKSHAR ESTONIA?
AKSHAR ESTONIA by VAGAD BUILDERS AND DEVELOPERS PRIVATE LIMITED is in Vashi, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000004543, per GharKundli's check of MahaRERA records.
How many homes are in AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA has 355 homes in 5 towers registered on MahaRERA.
When was AKSHAR ESTONIA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AKSHAR ESTONIA was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AKSHAR ESTONIA?
No court cases are listed for AKSHAR ESTONIA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of AKSHAR ESTONIA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VAGAD BUILDERS AND DEVELOPERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of AKSHAR ESTONIA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vashi
- ORCHID ARCADE
- DAATA GARDENIA
- MEGA 75 WEST
- BHUMIRAJ HILLS
- NEWA BUSINESS PARK BUILDING A PHASE 1
- KALPAK HILLS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.