Skip to content
GharKundli

Royale Rahadki Greens New Phase

by VINOD PREMCHAND CHANDWANI · Pimple Saudagar, Pune 411017Also near Pimpri Colony

What’s in the report? →

Possession: Royale Rahadki Greens New Phase (MahaRERA P52100000194) is marked completed on MahaRERA. It has 83 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100000194. Status: Completed.

Source: MahaRERA website — records for P52100000194, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Royale Rahadki Greens New Phase?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Royale Rahadki Greens New Phase

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the November 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100000194
Status
Completed
Builder
VINOD PREMCHAND CHANDWANI
Location
Pimple Saudagar, Pune · 411017
Project type
Residential / Group Housing
Registered on
10 Jul 2017
Completion date at registration
November 2020
Latest completion date
November 2020
Homes
83
Towers
6
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
18

Construction progress of Royale Rahadki Greens New Phase, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
G100%100%100%100%
H100%100%100%100%
J100%100%100%100%
K100%100%100%100%
L100%100%100%100%
COMMERCIAL100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Royale Rahadki Greens New Phase every 1–2 months.

Royale Rahadki Greens New Phase: buildings, flats and land, as filed on MahaRERA

  • Buildings: G (6 floors) · H (6 floors) · J (6 floors) · K (6 floors) · L (6 floors) · COMMERCIAL (2 floors)
  • Land: 2,421 sq m (about 0.6 acres) · sanctioned built-up 3,465 sq m · recreational space 243 sq m
  • Land, as filed: 30/1,2,3 32/2D/3
  • Map: Get directions

The builder’s record and reviews

Vinod Premchand Chandwani has 19 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 15 finished, 14 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 40 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Royale Rahadki Greens New Phase →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Royale Rahadki Greens New Phase: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Royale Rahadki Greens New Phase

What is the possession date of Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Royale Rahadki Greens New Phase in Pimple Saudagar, Pune is 30 November 2020.

Is the builder's possession date different from the MahaRERA date for Royale Rahadki Greens New Phase?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Royale Rahadki Greens New Phase's builder has filed on MahaRERA, the official one, is 30 November 2020, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Royale Rahadki Greens New Phase in Pimple Saudagar, Pune is P52100000194.

Is Royale Rahadki Greens New Phase registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase is registered as P52100000194 and its status is "Completed".

What is the current construction status of Royale Rahadki Greens New Phase? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does Royale Rahadki Greens New Phase have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Royale Rahadki Greens New Phase safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase is registered on MahaRERA as P52100000194, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Royale Rahadki Greens New Phase?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Royale Rahadki Greens New Phase: gharkundli.com/tools/property-cost-calculator

Has Royale Rahadki Greens New Phase received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Royale Rahadki Greens New Phase completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase is marked completed on MahaRERA, and the completion date filed there is 30 November 2020. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Royale Rahadki Greens New Phase uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Royale Rahadki Greens New Phase was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Royale Rahadki Greens New Phase's possession date changes?

The latest dates are on Royale Rahadki Greens New Phase's MahaRERA page (P52100000194). GharKundli's Kundli Watch sends a free WhatsApp update on Royale Rahadki Greens New Phase every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Royale Rahadki Greens New Phase have?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase has 6 buildings filed: G with 6 floors; H with 6 floors; J with 6 floors; K with 6 floors; L with 6 floors; COMMERCIAL with 2 floors.

How big is the land of Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase stands on 2,421 sq m of land (about 0.6 acres), with 3,465 sq m of sanctioned built-up area and 243 sq m of recreational open space.

What is the track record of Royale Rahadki Greens New Phase's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vinod Premchand Chandwani has 19 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 15 finished, 14 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 40 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Royale Rahadki Greens New Phase?

Google Maps has reviews of Royale Rahadki Greens New Phase written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Royale Rahadki Greens New Phase?

Royale Rahadki Greens New Phase by VINOD PREMCHAND CHANDWANI is in Pimple Saudagar, Pune, pincode 411017 (near Pimpri Colony), Maharashtra, and is registered on MahaRERA as P52100000194, per GharKundli's check of MahaRERA records. Its land is filed as 30/1,2,3 32/2D/3. GharKundli lists all 161 MahaRERA projects in Rahatani (411017).

How many flats are in Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase has 83 homes in 6 towers registered on MahaRERA.

When was Royale Rahadki Greens New Phase registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Royale Rahadki Greens New Phase was registered on MahaRERA on 10 July 2017. GharKundli did not find a title report on the land on file there.

Does Royale Rahadki Greens New Phase have any legal issues or court cases?

1 court case is listed for Royale Rahadki Greens New Phase on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Royale Rahadki Greens New Phase?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VINOD PREMCHAND CHANDWANI, which has 18 other projects registered on MahaRERA.

Other projects in Rahatani (411017)

All 161 projects in Rahatani (411017) →

Other projects by VINOD PREMCHAND CHANDWANI

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.