Skip to content
GharKundli

Dreams Sankalp L M wings

by Dreams Construction Pvt. Ltd. · Swargate, Pune 412207Registered on MahaRERA as “Dreams Sankalp L M wings”

What’s in the report? →

Possession date of Dreams Sankalp L M wings (MahaRERA P52100001529): 30 December 2021, moved from 28 February 2019 (34 months later), and it has already passed. It has 86 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100001529. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100001529, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Dreams Sankalp L M wings?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Dreams Sankalp L M wings has moved

  1. 28 February 2019

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52100001495)

    Reason the builder gave MahaRERA: “Due to demonetisation and the GST the cash flow was badly hampered.”
  3. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52100005901)

    Reason the builder gave MahaRERA: “Environment NOC in process, obtaining required NOC for completion certificate, Civil work almost finished.”
  4. 30 June 2021

    Extended at the builder's request (MahaRERA application EXT52100008820)

    Reason the builder gave MahaRERA:
    “Due to Covid 19 and lockdown labours was not available and its impact on sales. right now site is partly completed we need to complete unsold inventory balance work as funds available . we also applied for part completion to PMRDA but due t…” Read the full reason“Due to Covid 19 and lockdown labours was not available and its impact on sales. right now site is partly completed we need to complete unsold inventory balance work as funds available . we also applied for part completion to PMRDA but due to air force NOC its getting delay. we need extension for do registration of flats agreement, otherwise we cann't sale the flat and we will suffer to our fund flow. Request to give one more chance to come out from this situation. Regards”
  5. 30 December 2021

    Revised completion date on MahaRERA

Source: Dreams Sankalp L M wings’s extension records on MahaRERA (P52100001529), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dreams Sankalp L M wings

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100001529
Status
Lapsed (registration period ended)
Builder
Dreams Construction Pvt. Ltd.
Location
Swargate, Pune · 412207
Project type
Residential / Group Housing
Registered on
28 Jul 2017
Completion date at registration
February 2019
Latest completion date
December 2021
Delay so far
34 months
Homes
86
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Dreams Sankalp L M wings, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
L wing100%100%100%100%
M wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dreams Sankalp L M wings every 1–2 months.

Dreams Sankalp L M wings: buildings, flats and land, as filed on MahaRERA

  • Buildings: L wing (13 floors) · M wing (13 floors)
  • Land: 1,604 sq m (about 0.4 acres) · sanctioned built-up 5,814 sq m · recreational space 2,150 sq m
  • Land, as filed: New 862 P
  • Map: Get directions

The builder’s record and reviews

Dreams Construction has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Dreams Sankalp L M wings →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dreams Sankalp L M wings: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dreams Sankalp L M wings

What is the possession date of Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dreams Sankalp L M wings in Swargate, Pune is 30 December 2021 — 34 months later than 28 February 2019, the date given at registration. That date has already passed.

The date has already moved 34 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Dreams Sankalp L M wings?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dreams Sankalp L M wings's builder has filed on MahaRERA, the official one, is 30 December 2021, already 34 months later than the 28 February 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Dreams Sankalp L M wings extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2020, giving the reason "Due to demonetisation and the GST the cash flow was badly hampered."; to 31 December 2020, giving the reason "Environment NOC in process, obtaining required NOC for completion certificate, Civil work almost finished."; to 30 June 2021, giving the reason "Due to Covid 19 and lockdown labours was not available and its impact on sales. right now site is partly completed we need to complete unsold inventory balance work as funds available . we also applied for part completion to PMRDA but due to air force NOC its getting delay. we need extension for do registration of flats agreement, otherwise we cann't sale the flat and we will suffer to our fund flow. Request to give one more chance to come out from this situation. Regards".

What is the RERA number of Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dreams Sankalp L M wings in Swargate, Pune is P52100001529.

Is Dreams Sankalp L M wings registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings is registered as P52100001529 and its status is "Lapsed (registration period ended)".

What is the current construction status of Dreams Sankalp L M wings? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Dreams Sankalp L M wings have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Dreams Sankalp L M wings safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings is registered on MahaRERA as P52100001529, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 34 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dreams Sankalp L M wings?

Dreams Sankalp L M wings isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Dreams Sankalp L M wings?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Dreams Sankalp L M wings: gharkundli.com/tools/property-cost-calculator

Has Dreams Sankalp L M wings received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Dreams Sankalp L M wings uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Dreams Sankalp L M wings was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Dreams Sankalp L M wings's possession date changes?

The latest dates are on Dreams Sankalp L M wings's MahaRERA page (P52100001529). GharKundli's Kundli Watch sends a free WhatsApp update on Dreams Sankalp L M wings every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dreams Sankalp L M wings have?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings has 2 buildings filed: L wing with 13 floors; M wing with 13 floors.

How big is the land of Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings stands on 1,604 sq m of land (about 0.4 acres), with 5,814 sq m of sanctioned built-up area and 2,150 sq m of recreational open space.

What is the track record of Dreams Sankalp L M wings's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Construction has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Dreams Sankalp L M wings?

Google Maps has reviews of Dreams Sankalp L M wings written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dreams Sankalp L M wings?

Dreams Sankalp L M wings by Dreams Construction Pvt. Ltd. is in Swargate, Pune, pincode 412207, Maharashtra, and is registered on MahaRERA as P52100001529, per GharKundli's check of MahaRERA records. Its land is filed as New 862 P. GharKundli lists all 379 MahaRERA projects in Wagholi (412207).

How many flats are in Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings has 86 homes in 2 towers registered on MahaRERA.

When was Dreams Sankalp L M wings registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreams Sankalp L M wings was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.

Does Dreams Sankalp L M wings have any legal issues or court cases?

No court cases are listed for Dreams Sankalp L M wings on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Dreams Sankalp L M wings?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dreams Construction Pvt. Ltd., which has 2 other projects registered on MahaRERA.

Other projects in Wagholi (412207)

All 379 projects in Wagholi (412207) →

Other projects by Dreams Construction Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.