Geras Misty Waters
by Gera Developments Private Limited · Mundwa, PuneAlso near Kharadi, Keshavnagar
Possession date of Geras Misty Waters: 14 June 2023, moved from 14 June 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100001176. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2023) has passed.
What do you want to know about Geras Misty Waters?
How the possession date of Geras Misty Waters has moved
14 June 2022
Completion date given when the project was registered
14 June 2023
Extended at the builder's request (MahaRERA application EXT52100011827)
Reason the builder gave MahaRERA:
“We would like you to please grant us extension for one year as the delay in grant of final occupancy certificate is beyond our control. The Project is completed in all respect and comprises of 118 number of units. Out of 118 units, occupanc…” Read the full reason
“We would like you to please grant us extension for one year as the delay in grant of final occupancy certificate is beyond our control. The Project is completed in all respect and comprises of 118 number of units. Out of 118 units, occupancy certificate for 116 units have already been received. The balance two units are not sold, and the issuance of occupancy certificate has been kept in abeyance by PMC for the want of amenity space handover. The initial requirement of handing over the amenity space is the bifurcation of society, which was applied on 22nd July 2021 and the final order of so…”
Source: Geras Misty Waters’s extension records on MahaRERA (P52100001176), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Geras Misty Waters
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001176
- Status
- Lapsed (registration period ended)
- Builder
- Gera Developments Private Limited
- Location
- Mundwa, Pune · 411036
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- June 2022
- Latest completion date
- June 2023
- Delay so far
- 12 months
- Homes
- 118
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 24
Construction progress of Geras Misty Waters, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Geras Misty Waters | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Geras Misty Waters every month.
Geras Misty Waters: buildings, flats and land, as filed on MahaRERA
- Buildings: Geras Misty Waters (12 floors)
- Land: 5,994 sq m (about 1.5 acres) · sanctioned built-up 7,552 sq m · recreational space 705 sq m
- Boundaries filed include: Mulla- Mutha River
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Gera Developments (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 4 finished, all within the promised date; 12 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 109 complaints on MahaRERA across 14 projects.
Read Google reviews of Geras Misty Waters →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Geras Misty Waters: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Geras Misty Waters
What is the possession date of Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Geras Misty Waters in Mundwa, Pune is 14 June 2023 — 12 months later than 14 June 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Geras Misty Waters?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Geras Misty Waters's builder has filed on MahaRERA, the official one, is 14 June 2023, already 12 months later than the 14 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Geras Misty Waters extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters's builder applied to MahaRERA to extend the completion date once: to 14 June 2023, giving the reason "We would like you to please grant us extension for one year as the delay in grant of final occupancy certificate is beyond our control. The Project is completed in all respect and comprises of 118 number of units. Out of 118 units, occupancy certificate for 116 units have already been received. The balance two units are not sold, and the issuance of occupancy certificate has been kept in abeyance by PMC for the want of amenity space handover. The initial requirement of handing over the amenity space is the bifurcation of society, which was applied on 22nd July 2021 and the final order of so…".
What is the RERA number of Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Geras Misty Waters in Mundwa, Pune is P52100001176.
Is Geras Misty Waters registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters is registered as P52100001176 and its status is "Lapsed (registration period ended)".
What is the construction status of Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Geras Misty Waters is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Geras Misty Waters have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Geras Misty Waters safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters is registered on MahaRERA as P52100001176, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Geras Misty Waters's possession date changes?
The latest dates are on Geras Misty Waters's MahaRERA page (P52100001176). GharKundli's Kundli Watch sends a free WhatsApp update on Geras Misty Waters every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Geras Misty Waters have?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters has one building filed: Geras Misty Waters with 12 floors.
How big is the land of Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters stands on 5,994 sq m of land (about 1.5 acres), with 7,552 sq m of sanctioned built-up area and 705 sq m of recreational open space.
What is the track record of Geras Misty Waters's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Gera Developments (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 4 finished, all within the promised date; 12 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 109 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Geras Misty Waters?
Google Maps has reviews of Geras Misty Waters written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Geras Misty Waters?
Geras Misty Waters by Gera Developments Private Limited is in Mundwa, Pune (pincode 411036), near Kharadi, Keshavnagar, Maharashtra, and is registered on MahaRERA as P52100001176, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mulla- Mutha River.
How many homes are in Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters has 118 homes in 1 tower registered on MahaRERA.
When was Geras Misty Waters registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Geras Misty Waters was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Geras Misty Waters?
No court cases are listed for Geras Misty Waters on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Geras Misty Waters?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Gera Developments Private Limited, which has 24 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Geras Misty Waters
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411036
Other projects by Gera Developments Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.