QN GREENS PHASE 1
by QUALITAS NAMAN HOME MAKERS LLP · Taloja A.V., RaigarhAlso near Panvel, Koyana Velhe, Koynavele
Possession: QN GREENS PHASE 1 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000007707. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about QN GREENS PHASE 1?
How the possession date of QN GREENS PHASE 1 has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52000003766)
Reason the builder gave MahaRERA:
“WORK COMPLETED UPTO 85%. DUE TO HEAVY RAINS FOR PROLONGED PERIOD COULD NOT COMMENCE THE EXCAVATION WORK FOR UNDERGROUND STP, PAINTING & FINISHING WORK INCLUDING PAVER BLOCK. EVEN NBFC'S DELAY IN RELEASING FUNDS OF THEIR CUSTOMERS HAS ALSO C…” Read the full reason
“WORK COMPLETED UPTO 85%. DUE TO HEAVY RAINS FOR PROLONGED PERIOD COULD NOT COMMENCE THE EXCAVATION WORK FOR UNDERGROUND STP, PAINTING & FINISHING WORK INCLUDING PAVER BLOCK. EVEN NBFC'S DELAY IN RELEASING FUNDS OF THEIR CUSTOMERS HAS ALSO CONTRIBUTED FOR THE DELAY IN COMPLETION. THE PROJECT IS OF AFFORDABLE SEGMENT AND MOST OF THE CUSTOMERS HAVE AVAILED THE HOUSING FINANCE FROM NBFC'S WHO STOPPED RELEASE OF FUNDS TO THEIR CUSTOMERS ON ACCOUNT OF THE CRISES IN THE NBFC'S SINCE WE HAVE COMPLETED UPTO 85% & ARE FULLY CONFIDENT THAT THE PROJECT WILL BE COMPLETED BY 30 JUNE 2020 AND THEREFORE SE…”30 December 2021
Revised completion date on MahaRERA
Source: QN GREENS PHASE 1’s extension records on MahaRERA (P52000007707), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on QN GREENS PHASE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- QN GREENS PHASE 2P52000015726 · possession 30 Jun 2022
- QN GREENS PHASE 3P52000018224 · possession 30 Dec 2022
- MahaRERA registration
- P52000007707
- Status
- Completed
- Builder
- QUALITAS NAMAN HOME MAKERS LLP
- Location
- Taloja A.V., Raigarh · 410208
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 154
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of QN GREENS PHASE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 1 - Wing H, I, J | 100% | 100% | 100% | 100% |
| Building 2 - Wing C, D, E, F, G | 100% | 100% | 85% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on QN GREENS PHASE 1 every month.
QN GREENS PHASE 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 1 - Wing H, I, J (5 floors) · Building 2 - Wing C, D, E, F, G (6 floors)
- Land: 5,378 sq m (about 1.3 acres) · sanctioned built-up 5,509 sq m · recreational space 401 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Qualitas Naman Home Makers has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of QN GREENS PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
QN GREENS PHASE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about QN GREENS PHASE 1
What is the possession date of QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for QN GREENS PHASE 1 in Taloja A.V., Raigarh is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for QN GREENS PHASE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date QN GREENS PHASE 1's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of QN GREENS PHASE 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "WORK COMPLETED UPTO 85%. DUE TO HEAVY RAINS FOR PROLONGED PERIOD COULD NOT COMMENCE THE EXCAVATION WORK FOR UNDERGROUND STP, PAINTING & FINISHING WORK INCLUDING PAVER BLOCK. EVEN NBFC'S DELAY IN RELEASING FUNDS OF THEIR CUSTOMERS HAS ALSO CONTRIBUTED FOR THE DELAY IN COMPLETION. THE PROJECT IS OF AFFORDABLE SEGMENT AND MOST OF THE CUSTOMERS HAVE AVAILED THE HOUSING FINANCE FROM NBFC'S WHO STOPPED RELEASE OF FUNDS TO THEIR CUSTOMERS ON ACCOUNT OF THE CRISES IN THE NBFC'S SINCE WE HAVE COMPLETED UPTO 85% & ARE FULLY CONFIDENT THAT THE PROJECT WILL BE COMPLETED BY 30 JUNE 2020 AND THEREFORE SE…".
What is the RERA number of QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of QN GREENS PHASE 1 in Taloja A.V., Raigarh is P52000007707.
Is QN GREENS PHASE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 is registered as P52000007707 and its status is "Completed".
What is the construction status of QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does QN GREENS PHASE 1 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is QN GREENS PHASE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 is registered on MahaRERA as P52000007707, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does QN GREENS PHASE 1 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: QN GREENS PHASE 2 (P52000015726, possession 30 Jun 2022); QN GREENS PHASE 3 (P52000018224, possession 30 Dec 2022). Check that your agreement names the registration of your own wing.
How can I get updates if QN GREENS PHASE 1's possession date changes?
The latest dates are on QN GREENS PHASE 1's MahaRERA page (P52000007707). GharKundli's Kundli Watch sends a free WhatsApp update on QN GREENS PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does QN GREENS PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 has 2 buildings filed: Building 1 - Wing H, I, J with 5 floors; Building 2 - Wing C, D, E, F, G with 6 floors.
How big is the land of QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 stands on 5,378 sq m of land (about 1.3 acres), with 5,509 sq m of sanctioned built-up area and 401 sq m of recreational open space.
What is the track record of QN GREENS PHASE 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Qualitas Naman Home Makers has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of QN GREENS PHASE 1?
Google Maps has reviews of QN GREENS PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is QN GREENS PHASE 1?
QN GREENS PHASE 1 by QUALITAS NAMAN HOME MAKERS LLP is in Taloja A.V., Raigarh (pincode 410208), near Panvel, Koyana Velhe, Koynavele, Maharashtra, and is registered on MahaRERA as P52000007707, per GharKundli's check of MahaRERA records.
How many homes are in QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 has 154 homes in 2 towers registered on MahaRERA.
When was QN GREENS PHASE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), QN GREENS PHASE 1 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on QN GREENS PHASE 1?
No court cases are listed for QN GREENS PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of QN GREENS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is QUALITAS NAMAN HOME MAKERS LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of QN GREENS PHASE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410208
- Konnark Meadows
- Vrundavan
- K K RESIDENCY
- Rudra Rajendra
- ARKAN CASTLE
- NANASETH RESIDENCY
- Saksham Heights
- GREEN LEAF
Other projects by QUALITAS NAMAN HOME MAKERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.