GREEN SPRINGS
by VISION ASSOCIATES · Sidhhanathwadi, Satara
Possession: GREEN SPRINGS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52700001770. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about GREEN SPRINGS?
How the possession date of GREEN SPRINGS has moved
30 June 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT52700005861)
Reason the builder gave MahaRERA: “Application for completion certificate is made to the concern authority but the authority is requiring more time for the same.”
31 December 2023
Extended at the builder's request (MahaRERA application EXT52700010800)
Reason the builder gave MahaRERA: “NON AVAILABILITY OF LABOUR AND CONSTRUCTION MATERIAL BECAUSE OF COVID 19 PANDEMIC”
Source: GREEN SPRINGS’s extension records on MahaRERA (P52700001770), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GREEN SPRINGS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52700001770
- Status
- Completed
- Builder
- VISION ASSOCIATES
- Location
- Sidhhanathwadi, Satara · 412803
- Project type
- Residential / Group Housing
- Registered on
- 29 Jul 2017
- Completion date at registration
- June 2019
- Latest completion date
- December 2023
- Delay so far
- 54 months
- Homes
- 73
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of GREEN SPRINGS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GREEN SPRINGS | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GREEN SPRINGS every month.
GREEN SPRINGS: buildings, flats and land, as filed on MahaRERA
- Buildings: GREEN SPRINGS (6 floors)
- Land: 2,815 sq m (about 0.7 acres) · sanctioned built-up 3,378 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GREEN SPRINGS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GREEN SPRINGS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GREEN SPRINGS
What is the possession date of GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GREEN SPRINGS in Sidhhanathwadi, Satara is 31 December 2023 — 54 months later than 30 June 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for GREEN SPRINGS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GREEN SPRINGS's builder has filed on MahaRERA, the official one, is 31 December 2023, already 54 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GREEN SPRINGS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "Application for completion certificate is made to the concern authority but the authority is requiring more time for the same."; to 31 December 2023, giving the reason "NON AVAILABILITY OF LABOUR AND CONSTRUCTION MATERIAL BECAUSE OF COVID 19 PANDEMIC".
What is the RERA number of GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GREEN SPRINGS in Sidhhanathwadi, Satara is P52700001770.
Is GREEN SPRINGS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS is registered as P52700001770 and its status is "Completed".
What is the construction status of GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS's status on MahaRERA is "Completed". As filed by the builder, slab work on GREEN SPRINGS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does GREEN SPRINGS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is GREEN SPRINGS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS is registered on MahaRERA as P52700001770, its MahaRERA status is "Completed", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GREEN SPRINGS's possession date changes?
The latest dates are on GREEN SPRINGS's MahaRERA page (P52700001770). GharKundli's Kundli Watch sends a free WhatsApp update on GREEN SPRINGS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GREEN SPRINGS have?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS has one building filed: GREEN SPRINGS with 6 floors.
How big is the land of GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS stands on 2,815 sq m of land (about 0.7 acres), with 3,378 sq m of sanctioned built-up area.
Where can I read reviews of GREEN SPRINGS?
Google Maps has reviews of GREEN SPRINGS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GREEN SPRINGS?
GREEN SPRINGS by VISION ASSOCIATES is in Sidhhanathwadi, Satara (pincode 412803), Maharashtra, and is registered on MahaRERA as P52700001770, per GharKundli's check of MahaRERA records.
How many homes are in GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS has 73 homes in 1 tower registered on MahaRERA.
When was GREEN SPRINGS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GREEN SPRINGS was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GREEN SPRINGS?
No court cases are listed for GREEN SPRINGS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GREEN SPRINGS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISION ASSOCIATES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GREEN SPRINGS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wai
- DIGVIJAY ANANDRAO GAIKWAD
- SAKSHI NISARG
- VASTULAXMI RESIDENCY
- SAI Vrundavan Wing A
- VANTARA
- SWARNGIRI HEIGHTS
- NAKSHATRA RESIDENCY
- Versatile Viva
Other projects by VISION ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.