by KST CONSTRUCTIONS · Agashivnagar, SataraAlso near Malkapur Karad

Possession: KST PLANET is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700003925. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about KST PLANET?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KST PLANET has moved

  1. 1 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52700016941)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have already received the OC for the Project and we hope to get the Extension so that we can close the project.”

Source: KST PLANET’s extension records on MahaRERA (P52700003925), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KST PLANET

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700003925
Status
Completed
Builder
KST CONSTRUCTIONS
Location
Agashivnagar, Satara · 415539
Project type
Residential / Group Housing
Registered on
7 Aug 2017
Completion date at registration
June 2022
Latest completion date
June 2023
Delay so far
12 months
Homes
108
Towers
10
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of KST PLANET, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%100%100%100%
BUILDING NO 2100%100%100%100%
BUILDING NO 3100%100%100%100%
BUILDING NO 4100%100%100%100%
BUNGLOW NO 1 AND 2100%100%100%100%
BUNGALOW NO 3 AND 4100%100%100%100%
BUNGALOW NO 5 AND 6100%100%100%100%
BUILDING NO 7 AND 8100%100%100%100%
BUNGALOW NO 9 AND 10100%100%100%100%
OFFICE BUILDING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KST PLANET every month.

KST PLANET: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (6 floors) · BUILDING NO 2 (6 floors) · BUILDING NO 3 (6 floors) · BUILDING NO 4 (6 floors) · BUNGLOW NO 1 AND 2 (2 floors) · BUNGALOW NO 3 AND 4 (2 floors) · BUNGALOW NO 5 AND 6 (2 floors) · BUILDING NO 7 AND 8 (2 floors) · and 2 more
  • Land: 6,700 sq m (about 1.7 acres) · sanctioned built-up 5,895 sq m · recreational space 645 sq m

The builder’s record and reviews

KST Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of KST PLANET →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KST PLANET: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KST PLANET

What is the possession date of KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KST PLANET in Agashivnagar, Satara is 30 June 2023 — 12 months later than 1 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for KST PLANET?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KST PLANET's builder has filed on MahaRERA, the official one, is 30 June 2023, already 12 months later than the 1 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KST PLANET extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have already received the OC for the Project and we hope to get the Extension so that we can close the project.".

What is the RERA number of KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KST PLANET in Agashivnagar, Satara is P52700003925.

Is KST PLANET registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET is registered as P52700003925 and its status is "Completed".

What is the construction status of KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 10 towers. GharKundli's full report compares construction progress with the deadline.

Does KST PLANET have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KST PLANET safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET is registered on MahaRERA as P52700003925, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KST PLANET's possession date changes?

The latest dates are on KST PLANET's MahaRERA page (P52700003925). GharKundli's Kundli Watch sends a free WhatsApp update on KST PLANET every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KST PLANET have?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET has 10 buildings filed: BUILDING NO 1 with 6 floors; BUILDING NO 2 with 6 floors; BUILDING NO 3 with 6 floors; BUILDING NO 4 with 6 floors; BUNGLOW NO 1 AND 2 with 2 floors; BUNGALOW NO 3 AND 4 with 2 floors; and 4 more.

How big is the land of KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET stands on 6,700 sq m of land (about 1.7 acres), with 5,895 sq m of sanctioned built-up area and 645 sq m of recreational open space.

What is the track record of KST PLANET's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), KST Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KST PLANET?

Google Maps has reviews of KST PLANET written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KST PLANET?

KST PLANET by KST CONSTRUCTIONS is in Agashivnagar, Satara (pincode 415539), near Malkapur Karad, Maharashtra, and is registered on MahaRERA as P52700003925, per GharKundli's check of MahaRERA records.

How many homes are in KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET has 108 homes in 10 towers registered on MahaRERA.

When was KST PLANET registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KST PLANET was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KST PLANET?

No court cases are listed for KST PLANET on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KST PLANET?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KST CONSTRUCTIONS, which has 1 other project registered on MahaRERA.