Skip to content
GharKundli

Heramb Prime

by Mangesh Vitthal Wadekar · Satara City, Satara 415002

What’s in the report? →

Possession: Heramb Prime (MahaRERA P52700009659) is marked completed on MahaRERA. It has 10 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700009659. Status: Completed.

Source: MahaRERA website — records for P52700009659, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Heramb Prime?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Heramb Prime

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700009659
Status
Completed
Builder
Mangesh Vitthal Wadekar
Location
Satara City, Satara · 415002
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
April 2022
Latest completion date
April 2022
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Heramb Prime, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Heramb Prime100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Heramb Prime every 1–2 months.

Heramb Prime: buildings, flats and land, as filed on MahaRERA

  • Buildings: Heramb Prime (6 floors)
  • Land: 683 sq m (about 0.2 acres) · sanctioned built-up 953 sq m
  • Land, as filed: CTS NO 12
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Heramb Prime →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Heramb Prime: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Heramb Prime

What is the possession date of Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Heramb Prime in Satara City, Satara is 30 April 2022.

Is the builder's possession date different from the MahaRERA date for Heramb Prime?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Heramb Prime's builder has filed on MahaRERA, the official one, is 30 April 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Heramb Prime in Satara City, Satara is P52700009659.

Is Heramb Prime registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime is registered as P52700009659 and its status is "Completed".

What is the current construction status of Heramb Prime? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime's status on MahaRERA is "Completed". As filed by the builder, slab work on Heramb Prime is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Heramb Prime have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Heramb Prime safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime is registered on MahaRERA as P52700009659, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Heramb Prime?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Heramb Prime: gharkundli.com/tools/property-cost-calculator

Has Heramb Prime received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Heramb Prime completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime is marked completed on MahaRERA, and the completion date filed there is 30 April 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Heramb Prime uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Heramb Prime was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Heramb Prime's possession date changes?

The latest dates are on Heramb Prime's MahaRERA page (P52700009659). GharKundli's Kundli Watch sends a free WhatsApp update on Heramb Prime every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Heramb Prime have?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime has one building filed: Heramb Prime with 6 floors.

How big is the land of Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime stands on 683 sq m of land (about 0.2 acres), with 953 sq m of sanctioned built-up area.

What are the reviews of Heramb Prime?

Google Maps has reviews of Heramb Prime written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Heramb Prime?

Heramb Prime by Mangesh Vitthal Wadekar is in Satara City, Satara, pincode 415002, Maharashtra, and is registered on MahaRERA as P52700009659, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 12. GharKundli lists all 218 MahaRERA projects in Satara City (415002).

How many flats are in Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime has 10 homes in 1 tower registered on MahaRERA.

When was Heramb Prime registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Heramb Prime was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Does Heramb Prime have any legal issues or court cases?

1 court case is listed for Heramb Prime on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Heramb Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mangesh Vitthal Wadekar.

Other projects in Satara City (415002)

All 218 projects in Satara City (415002) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.