Shriraj Shriganesh Residency
by SHRIRAJ DEVELOPERS AND BUILDERS · Vittainagar, Satara 415004Registered on MahaRERA as “SHRIGANESH RESIDENCY”
What’s in the report? →Possession date of Shriraj Shriganesh Residency (MahaRERA P52700012949): 30 July 2019, moved from 31 July 2018 (12 months later), and it has already passed. It has 10 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52700012949. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52700012949, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2019) has passed.
What do you want to know about Shriraj Shriganesh Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shriraj Shriganesh Residency has moved
31 July 2018
Completion date given when the project was registered
30 July 2019
Extended at the builder's request (MahaRERA application EXT52700000528)
Reason the builder gave MahaRERA:
“Due to booking was rare & less also other reason are responsible for it GST Charges etc. so I have few finanatial problem. So that my project was going slow. i will complete all project within few months but maybe The completion documents p…” Read the full reason
“Due to booking was rare & less also other reason are responsible for it GST Charges etc. so I have few finanatial problem. So that my project was going slow. i will complete all project within few months but maybe The completion documents procedure will take more time thatswhy I want 12 months extentions because your more extra charges.for small project also please give me one time extention. Thanking you Your faithfully”
Source: Shriraj Shriganesh Residency’s extension records on MahaRERA (P52700012949), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shriraj Shriganesh Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52700012949
- Status
- Lapsed (registration period ended)
- Builder
- SHRIRAJ DEVELOPERS AND BUILDERS
- Location
- Vittainagar, Satara · 415004
- Project type
- Residential / Group Housing
- Registered on
- 7 Sep 2017
- Completion date at registration
- July 2018
- Latest completion date
- July 2019
- Delay so far
- 12 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shriraj Shriganesh Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHRIGANESH RESIDENCY | 100% | 100% | 80% | 70% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shriraj Shriganesh Residency every 1–2 months.
Shriraj Shriganesh Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SHRIGANESH RESIDENCY (6 floors)
- Land: 279 sq m (about 0.1 acres) · sanctioned built-up 306 sq m
- Land, as filed: SURVEY NO 319/2 B PLOT NO2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shriraj Shriganesh Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shriraj Shriganesh Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shriraj Shriganesh Residency
What is the possession date of Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shriraj Shriganesh Residency in Vittainagar, Satara is 30 July 2019 — 12 months later than 31 July 2018, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shriraj Shriganesh Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shriraj Shriganesh Residency's builder has filed on MahaRERA, the official one, is 30 July 2019, already 12 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shriraj Shriganesh Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency's builder applied to MahaRERA to extend the completion date once: to 30 July 2019, giving the reason "Due to booking was rare & less also other reason are responsible for it GST Charges etc. so I have few finanatial problem. So that my project was going slow. i will complete all project within few months but maybe The completion documents procedure will take more time thatswhy I want 12 months extentions because your more extra charges.for small project also please give me one time extention. Thanking you Your faithfully".
What is the RERA number of Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shriraj Shriganesh Residency in Vittainagar, Satara is P52700012949.
Is Shriraj Shriganesh Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency is registered as P52700012949 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shriraj Shriganesh Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHRIGANESH RESIDENCY is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does Shriraj Shriganesh Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shriraj Shriganesh Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency is registered on MahaRERA as P52700012949, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shriraj Shriganesh Residency?
Shriraj Shriganesh Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shriraj Shriganesh Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shriraj Shriganesh Residency: gharkundli.com/tools/property-cost-calculator
Has Shriraj Shriganesh Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 July 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 July 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Shriraj Shriganesh Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shriraj Shriganesh Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shriraj Shriganesh Residency's possession date changes?
The latest dates are on Shriraj Shriganesh Residency's MahaRERA page (P52700012949). GharKundli's Kundli Watch sends a free WhatsApp update on Shriraj Shriganesh Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shriraj Shriganesh Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency has one building filed: SHRIGANESH RESIDENCY with 6 floors.
How big is the land of Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency stands on 279 sq m of land (about 0.1 acres), with 306 sq m of sanctioned built-up area.
What are the reviews of Shriraj Shriganesh Residency?
Google Maps has reviews of Shriraj Shriganesh Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shriraj Shriganesh Residency?
Shriraj Shriganesh Residency by SHRIRAJ DEVELOPERS AND BUILDERS is in Vittainagar, Satara, pincode 415004, Maharashtra, and is registered on MahaRERA as P52700012949, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 319/2 B PLOT NO2. GharKundli lists all 50 MahaRERA projects in Kodoli (415004).
How many flats are in Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency has 10 homes in 1 tower registered on MahaRERA.
When was Shriraj Shriganesh Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shriraj Shriganesh Residency was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Does Shriraj Shriganesh Residency have any legal issues or court cases?
No court cases are listed for Shriraj Shriganesh Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shriraj Shriganesh Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRIRAJ DEVELOPERS AND BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of Shriraj Shriganesh Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Satara
- Navnirrmitii Square
- The Royal Abode
- Emerald Heights
- Sai Empire
- Sargam Heights
- Mangalmurti Complex
- Dwarka Wing C
- Shreeji Elite
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.