RAJNAKSHATRA
by AADIRAJ BUILDERS AND DEVELOPERS · Goleshwar, Satara
Possession date of RAJNAKSHATRA: 30 December 2023, moved from 30 December 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52700013444. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about RAJNAKSHATRA?
How the possession date of RAJNAKSHATRA has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT52700013658)
Reason the builder gave MahaRERA: “DUE TO COVID-19 IMPACT AND FINANCIAL CRISIS TOTAL SITE WAS STOPPED DUE TO LACK OF LABOUR AND MATERIAL SUPPLY SO WE ARE UNABLE TO COMPLETE SITE WITHIN GIVEN TIME SPAN”
Source: RAJNAKSHATRA’s extension records on MahaRERA (P52700013444), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RAJNAKSHATRA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52700013444
- Status
- Lapsed (registration period ended)
- Builder
- AADIRAJ BUILDERS AND DEVELOPERS
- Location
- Goleshwar, Satara · 415124
- Project type
- Others
- Registered on
- 7 Oct 2017
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 249
- Towers
- 9
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of RAJNAKSHATRA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1B1 | 100% | 100% | 100% | 100% |
| A2B2 | 100% | 100% | 100% | 100% |
| A3B3 | 100% | 100% | 100% | 100% |
| A4 | 0% | 0% | 0% | 0% |
| CD | 0% | 0% | 0% | 0% |
| BUNGLOW 1 | 0% | 0% | 0% | 0% |
| BUNGLOW 2 | 0% | 0% | 0% | 0% |
| BUNGLOW 3 | 0% | 0% | 0% | 0% |
| bunglow 4 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAJNAKSHATRA every month.
RAJNAKSHATRA: buildings, flats and land, as filed on MahaRERA
- Buildings: A1B1 (12 floors) · A2B2 (12 floors) · A3B3 (12 floors) · A4 (5 floors) · CD (11 floors) · BUNGLOW 1 (2 floors) · BUNGLOW 2 (2 floors) · BUNGLOW 3 (2 floors) · and 1 more
- Land: 11,500 sq m (about 2.8 acres) · sanctioned built-up 14,015 sq m · recreational space 967 sq m
- Boundaries filed include: KARAD TASGAON ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RAJNAKSHATRA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAJNAKSHATRA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAJNAKSHATRA
What is the possession date of RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAJNAKSHATRA in Goleshwar, Satara is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for RAJNAKSHATRA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAJNAKSHATRA's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RAJNAKSHATRA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "DUE TO COVID-19 IMPACT AND FINANCIAL CRISIS TOTAL SITE WAS STOPPED DUE TO LACK OF LABOUR AND MATERIAL SUPPLY SO WE ARE UNABLE TO COMPLETE SITE WITHIN GIVEN TIME SPAN".
What is the RERA number of RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAJNAKSHATRA in Goleshwar, Satara is P52700013444.
Is RAJNAKSHATRA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA is registered as P52700013444 and its status is "Lapsed (registration period ended)".
What is the construction status of RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 9 towers. GharKundli's full report compares construction progress with the deadline.
Does RAJNAKSHATRA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is RAJNAKSHATRA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA is registered on MahaRERA as P52700013444, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RAJNAKSHATRA's possession date changes?
The latest dates are on RAJNAKSHATRA's MahaRERA page (P52700013444). GharKundli's Kundli Watch sends a free WhatsApp update on RAJNAKSHATRA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAJNAKSHATRA have?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA has 9 buildings filed: A1B1 with 12 floors; A2B2 with 12 floors; A3B3 with 12 floors; A4 with 5 floors; CD with 11 floors; BUNGLOW 1 with 2 floors; and 3 more.
How big is the land of RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA stands on 11,500 sq m of land (about 2.8 acres), with 14,015 sq m of sanctioned built-up area and 967 sq m of recreational open space.
Where can I read reviews of RAJNAKSHATRA?
Google Maps has reviews of RAJNAKSHATRA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAJNAKSHATRA?
RAJNAKSHATRA by AADIRAJ BUILDERS AND DEVELOPERS is in Goleshwar, Satara (pincode 415124), Maharashtra, and is registered on MahaRERA as P52700013444, per GharKundli's check of MahaRERA records. Its boundaries filed there include KARAD TASGAON ROAD.
How many homes are in RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA has 249 homes in 9 towers registered on MahaRERA.
When was RAJNAKSHATRA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJNAKSHATRA was registered on MahaRERA on 7 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RAJNAKSHATRA?
No court cases are listed for RAJNAKSHATRA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of RAJNAKSHATRA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AADIRAJ BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of RAJNAKSHATRA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karad
- AANAND VIHARR
- silver valley
- D S COMPLEX
- TANUSH PARK PHASE II
- ANANDNAGAR
- SQUARE CASTLE
- NAMO RESIDENCY
- SAAD RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.