CITRUS PARK

by FILTRUM INFRASTRUCTURE PVT LTD · Aundh, SataraAlso near Shirwal

Possession date of CITRUS PARK: 31 December 2023, moved from 31 October 2019 (50 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52700013639. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about CITRUS PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CITRUS PARK has moved

  1. 31 October 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52700005641)

    Reason the builder gave MahaRERA: “Due to poor market condition and dispute with the contractors, construction work was halted”
  3. 30 December 2022

    Extended at the builder's request (MahaRERA application EXT52700012125)

    Reason the builder gave MahaRERA: “We require the extension as we are awaiting completion certificate from the local authorities and also to handover the project.”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52700017720)

    Reason the builder gave MahaRERA:
    “We Filtrum Infrastructure Private Limited are developing a residential project Citrus Park and we were due to complete the project on 30/12/2022 as per RERA. We would like to inform you that we have already completed the project and submitt…” Read the full reason“We Filtrum Infrastructure Private Limited are developing a residential project Citrus Park and we were due to complete the project on 30/12/2022 as per RERA. We would like to inform you that we have already completed the project and submitted the documents for completion certificate with the Government Authority however till date we have not received the Completion certificate from the Government Authority and due the same we are unable to do sale deed of the new buyers. We request you to kindly grant an extension for one year till 30/12/2023 and oblige us.”

Source: CITRUS PARK’s extension records on MahaRERA (P52700013639), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CITRUS PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700013639
Status
Lapsed (registration period ended)
Builder
FILTRUM INFRASTRUCTURE PVT LTD
Location
Aundh, Satara · 412801
Project type
Residential / Group Housing
Registered on
16 Oct 2017
Completion date at registration
October 2019
Latest completion date
December 2023
Delay so far
50 months
Homes
48
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CITRUS PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C100%100%80%40%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CITRUS PARK every month.

CITRUS PARK: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Filtrum Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of CITRUS PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CITRUS PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CITRUS PARK

What is the possession date of CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CITRUS PARK in Aundh, Satara is 31 December 2023 — 50 months later than 31 October 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for CITRUS PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CITRUS PARK's builder has filed on MahaRERA, the official one, is 31 December 2023, already 50 months later than the 31 October 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CITRUS PARK extended?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Due to poor market condition and dispute with the contractors, construction work was halted"; to 30 December 2022, giving the reason "We require the extension as we are awaiting completion certificate from the local authorities and also to handover the project."; to 31 December 2023, giving the reason "We Filtrum Infrastructure Private Limited are developing a residential project Citrus Park and we were due to complete the project on 30/12/2022 as per RERA. We would like to inform you that we have already completed the project and submitted the documents for completion certificate with the Government Authority however till date we have not received the Completion certificate from the Government Authority and due the same we are unable to do sale deed of the new buyers. We request you to kindly grant an extension for one year till 30/12/2023 and oblige us.".

What is the RERA number of CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CITRUS PARK in Aundh, Satara is P52700013639.

Is CITRUS PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK is registered as P52700013639 and its status is "Lapsed (registration period ended)".

What is the construction status of CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on C is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does CITRUS PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is CITRUS PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK is registered on MahaRERA as P52700013639, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CITRUS PARK's possession date changes?

The latest dates are on CITRUS PARK's MahaRERA page (P52700013639). GharKundli's Kundli Watch sends a free WhatsApp update on CITRUS PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CITRUS PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK has one building filed: C with 6 floors.

How big is the land of CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK stands on 6,621 sq m of land (about 1.6 acres), with 2,757 sq m of sanctioned built-up area and 400 sq m of recreational open space.

What is the track record of CITRUS PARK's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Filtrum Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of CITRUS PARK?

Google Maps has reviews of CITRUS PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CITRUS PARK?

CITRUS PARK by FILTRUM INFRASTRUCTURE PVT LTD is in Aundh, Satara (pincode 412801), near Shirwal, Maharashtra, and is registered on MahaRERA as P52700013639, per GharKundli's check of MahaRERA records.

How many homes are in CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK has 48 homes in 1 tower registered on MahaRERA.

When was CITRUS PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CITRUS PARK was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on CITRUS PARK?

No court cases are listed for CITRUS PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CITRUS PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is FILTRUM INFRASTRUCTURE PVT LTD.