BALAJI RESIDENCY

by AV REALITIES · Sangamnagar Satara, Satara

Possession: BALAJI RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700014317. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BALAJI RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BALAJI RESIDENCY has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT52700011496)

    Reason the builder gave MahaRERA:
    “Due to Covid Pandemic and revised sanction plan we are unable to complete the site within given time limit. Few of the completed unit are sold and the consent of the said units allottees is also attached. And due to major impact of Covid we…” Read the full reason“Due to Covid Pandemic and revised sanction plan we are unable to complete the site within given time limit. Few of the completed unit are sold and the consent of the said units allottees is also attached. And due to major impact of Covid we are unable to sold all the units. As till some of the units are still unsold we need the extension to sold the remaining units and complete the project.”

Source: BALAJI RESIDENCY’s extension records on MahaRERA (P52700014317), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BALAJI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700014317
Status
Completed
Builder
AV REALITIES
Location
Sangamnagar Satara, Satara · 415003
Project type
Residential / Group Housing
Registered on
20 Nov 2017
Completion date at registration
December 2021
Latest completion date
September 2022
Delay so far
9 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of BALAJI RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BALAJI RESIDENCY100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BALAJI RESIDENCY every month.

BALAJI RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: BALAJI RESIDENCY (2 floors)
  • Land: 301 sq m (about 0.1 acres) · sanctioned built-up 300 sq m
  • Boundaries filed include: 6MT COLONY ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BALAJI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BALAJI RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BALAJI RESIDENCY

What is the possession date of BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BALAJI RESIDENCY in Sangamnagar Satara, Satara is 30 September 2022 — 9 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for BALAJI RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BALAJI RESIDENCY's builder has filed on MahaRERA, the official one, is 30 September 2022, already 9 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BALAJI RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 September 2022, giving the reason "Due to Covid Pandemic and revised sanction plan we are unable to complete the site within given time limit. Few of the completed unit are sold and the consent of the said units allottees is also attached. And due to major impact of Covid we are unable to sold all the units. As till some of the units are still unsold we need the extension to sold the remaining units and complete the project.".

What is the RERA number of BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BALAJI RESIDENCY in Sangamnagar Satara, Satara is P52700014317.

Is BALAJI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY is registered as P52700014317 and its status is "Completed".

What is the construction status of BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on BALAJI RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does BALAJI RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BALAJI RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY is registered on MahaRERA as P52700014317, its MahaRERA status is "Completed", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BALAJI RESIDENCY's possession date changes?

The latest dates are on BALAJI RESIDENCY's MahaRERA page (P52700014317). GharKundli's Kundli Watch sends a free WhatsApp update on BALAJI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BALAJI RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY has one building filed: BALAJI RESIDENCY with 2 floors.

How big is the land of BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY stands on 301 sq m of land (about 0.1 acres), with 300 sq m of sanctioned built-up area.

Where can I read reviews of BALAJI RESIDENCY?

Google Maps has reviews of BALAJI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BALAJI RESIDENCY?

BALAJI RESIDENCY by AV REALITIES is in Sangamnagar Satara, Satara (pincode 415003), Maharashtra, and is registered on MahaRERA as P52700014317, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6MT COLONY ROAD.

How many homes are in BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY has 12 homes in 1 tower registered on MahaRERA.

When was BALAJI RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BALAJI RESIDENCY was registered on MahaRERA on 20 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on BALAJI RESIDENCY?

No court cases are listed for BALAJI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BALAJI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AV REALITIES.

Other projects in pincode 415003

All 39 projects in Sangamnagar Satara (415003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.