KAUSHALYA RESIDENCY

by MRS KAUSHALYA RAMESH CHAVAN · Godoli, Satara

Possession date of KAUSHALYA RESIDENCY: 31 March 2024, moved from 30 March 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52700015518. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about KAUSHALYA RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KAUSHALYA RESIDENCY has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52700012043)

    Reason the builder gave MahaRERA: “all area near by project is now covered under Satara Muncipal , as it was first in Grampanchayat so only completion certificate for project is process .”

Source: KAUSHALYA RESIDENCY’s extension records on MahaRERA (P52700015518), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KAUSHALYA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700015518
Status
Lapsed (registration period ended)
Builder
MRS KAUSHALYA RAMESH CHAVAN
Location
Godoli, Satara · 415002
Project type
Residential / Group Housing
Registered on
7 Mar 2018
Completion date at registration
March 2022
Latest completion date
March 2024
Delay so far
24 months
Homes
11
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KAUSHALYA RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAUSHALYA RESIDENCY100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KAUSHALYA RESIDENCY every month.

KAUSHALYA RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: KAUSHALYA RESIDENCY (5 floors)
  • Land: 372 sq m (about 0.1 acres) · sanctioned built-up 447 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KAUSHALYA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KAUSHALYA RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KAUSHALYA RESIDENCY

What is the possession date of KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KAUSHALYA RESIDENCY in Godoli, Satara is 31 March 2024 — 24 months later than 30 March 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KAUSHALYA RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KAUSHALYA RESIDENCY's builder has filed on MahaRERA, the official one, is 31 March 2024, already 24 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KAUSHALYA RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "all area near by project is now covered under Satara Muncipal , as it was first in Grampanchayat so only completion certificate for project is process .".

What is the RERA number of KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KAUSHALYA RESIDENCY in Godoli, Satara is P52700015518.

Is KAUSHALYA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY is registered as P52700015518 and its status is "Lapsed (registration period ended)".

What is the construction status of KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KAUSHALYA RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does KAUSHALYA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KAUSHALYA RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY is registered on MahaRERA as P52700015518, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KAUSHALYA RESIDENCY's possession date changes?

The latest dates are on KAUSHALYA RESIDENCY's MahaRERA page (P52700015518). GharKundli's Kundli Watch sends a free WhatsApp update on KAUSHALYA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KAUSHALYA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY has one building filed: KAUSHALYA RESIDENCY with 5 floors.

How big is the land of KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY stands on 372 sq m of land (about 0.1 acres), with 447 sq m of sanctioned built-up area.

Where can I read reviews of KAUSHALYA RESIDENCY?

Google Maps has reviews of KAUSHALYA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KAUSHALYA RESIDENCY?

KAUSHALYA RESIDENCY by MRS KAUSHALYA RAMESH CHAVAN is in Godoli, Satara (pincode 415002), Maharashtra, and is registered on MahaRERA as P52700015518, per GharKundli's check of MahaRERA records.

How many homes are in KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY has 11 homes in 1 tower registered on MahaRERA.

When was KAUSHALYA RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHALYA RESIDENCY was registered on MahaRERA on 7 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on KAUSHALYA RESIDENCY?

No court cases are listed for KAUSHALYA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KAUSHALYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MRS KAUSHALYA RAMESH CHAVAN.