by M/S - SWARAJYA GROUP · Bhuvasaheb Nagar, SataraAlso near Pakhale Mala, Phaltan

Possession date of Swarajya Prime: 29 February 2028, moved from 30 December 2021 (70 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700020795, and currently active. Its completion date has moved from December 2021 to February 2028: 70 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Swarajya Prime?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Swarajya Prime has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT52700011163)

    Reason the builder gave MahaRERA: “Due to covid situtation work is delayed and also not sell of any appartment / unit till date, This situtation delayed the whole project progress. Till date almost 60% work is completed on site.”
  3. 31 October 2027

    Extended at the builder's request (MahaRERA application EXT52700017367)

    Reason the builder gave MahaRERA: “THERE ARE MAJOR PROBLEM IS COVID 19, HENCE LABOUR & MATERIAL, SO BOOKING ARE NOT CONFIRMED TILL DATE HENCE FINANCIAL SUPPORT ARE TO WEAK.”
  4. 29 February 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Swarajya Prime’s extension records on MahaRERA (P52700020795), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Swarajya Prime

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700020795
Status
Registered and active
Builder
M/S - SWARAJYA GROUP
Location
Bhuvasaheb Nagar, Satara · 415523
Project type
Others
Registered on
10 May 2019
Completion date at registration
December 2021
Latest completion date
February 2028
Delay so far
70 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
19
Sold or booked
26%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Swarajya Prime, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SWARAJYA PRIME100%100%100%85%

Commencement certificate (CC), as filed on MahaRERA

  • SWARAJYA PRIME: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swarajya Prime every month.

Swarajya Prime: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Swarajya Prime →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Swarajya Prime: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Swarajya Prime

What is the possession date of Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Swarajya Prime in Bhuvasaheb Nagar, Satara is 29 February 2028 — 70 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Swarajya Prime?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Swarajya Prime's builder has filed on MahaRERA, the official one, is 29 February 2028, already 70 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Swarajya Prime extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2023, giving the reason "Due to covid situtation work is delayed and also not sell of any appartment / unit till date, This situtation delayed the whole project progress. Till date almost 60% work is completed on site."; to 31 October 2027, giving the reason "THERE ARE MAJOR PROBLEM IS COVID 19, HENCE LABOUR & MATERIAL, SO BOOKING ARE NOT CONFIRMED TILL DATE HENCE FINANCIAL SUPPORT ARE TO WEAK.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Swarajya Prime in Bhuvasaheb Nagar, Satara is P52700020795.

Is Swarajya Prime registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime is registered as P52700020795 and its status is "Registered and active".

What is the construction status of Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SWARAJYA PRIME is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Swarajya Prime have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Swarajya Prime safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime is registered on MahaRERA as P52700020795, its completion date has moved 70 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Swarajya Prime's possession date changes?

The latest dates are on Swarajya Prime's MahaRERA page (P52700020795). GharKundli's Kundli Watch sends a free WhatsApp update on Swarajya Prime every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Swarajya Prime have?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime has one building filed: SWARAJYA PRIME with 5 floors and 31 units.

How big is the land of Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime stands on 1,100 sq m of land (about 0.3 acres), with 1,183 sq m of sanctioned built-up area.

Where can I read reviews of Swarajya Prime?

Google Maps has reviews of Swarajya Prime written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Swarajya Prime?

Swarajya Prime by M/S - SWARAJYA GROUP is in Bhuvasaheb Nagar, Satara (pincode 415523), near Pakhale Mala, Phaltan, Maharashtra, and is registered on MahaRERA as P52700020795, per GharKundli's check of MahaRERA records.

How many homes are in Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime has 19 homes in 1 tower registered on MahaRERA, and 26% of them are sold or booked.

When was Swarajya Prime registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Swarajya Prime was registered on MahaRERA on 10 May 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Swarajya Prime?

No court cases are listed for Swarajya Prime on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Swarajya Prime?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S - SWARAJYA GROUP.

All projects with possession due in 2028 in Satara →

Other projects in Phaltan

All 57 projects in Phaltan (415523) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.