by NITIN VASANTRAO KADAM · Khindwadi, Satara 415004

What’s in the report? →

Possession date of Shree Datta Samarth (MahaRERA P52700020739): 30 March 2023, and it has already passed. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700020739. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52700020739, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2023) has passed.

What do you want to know about Shree Datta Samarth?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shree Datta Samarth

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700020739
Status
Lapsed (registration period ended)
Builder
NITIN VASANTRAO KADAM
Location
Khindwadi, Satara · 415004
Project type
Residential / Group Housing
Registered on
8 May 2019
Completion date at registration
March 2023
Latest completion date
March 2023
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shree Datta Samarth, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE DATTA SAMARTH100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Datta Samarth every 1–2 months.

Shree Datta Samarth: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE DATTA SAMARTH (5 floors)
  • Land: 480 sq m (about 0.1 acres) · sanctioned built-up 570 sq m
  • Land, as filed: S N 8/6/6 PLOT NO 1,2,3
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shree Datta Samarth →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Datta Samarth: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shree Datta Samarth

What is the possession date of Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shree Datta Samarth in Khindwadi, Satara is 30 March 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shree Datta Samarth?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Datta Samarth's builder has filed on MahaRERA, the official one, is 30 March 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shree Datta Samarth in Khindwadi, Satara is P52700020739.

Is Shree Datta Samarth registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth is registered as P52700020739 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shree Datta Samarth? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE DATTA SAMARTH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shree Datta Samarth have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shree Datta Samarth safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth is registered on MahaRERA as P52700020739, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shree Datta Samarth?

Shree Datta Samarth isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shree Datta Samarth?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shree Datta Samarth: gharkundli.com/tools/property-cost-calculator

Has Shree Datta Samarth received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shree Datta Samarth uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shree Datta Samarth was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shree Datta Samarth's possession date changes?

The latest dates are on Shree Datta Samarth's MahaRERA page (P52700020739). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Datta Samarth every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Datta Samarth have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth has one building filed: SHREE DATTA SAMARTH with 5 floors.

How big is the land of Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth stands on 480 sq m of land (about 0.1 acres), with 570 sq m of sanctioned built-up area.

What are the reviews of Shree Datta Samarth?

Google Maps has reviews of Shree Datta Samarth written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shree Datta Samarth?

Shree Datta Samarth by NITIN VASANTRAO KADAM is in Khindwadi, Satara, pincode 415004, Maharashtra, and is registered on MahaRERA as P52700020739, per GharKundli's check of MahaRERA records. Its land is filed as S N 8/6/6 PLOT NO 1,2,3. GharKundli lists all 50 MahaRERA projects in Kodoli (415004).

How many flats are in Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth has 17 homes in 1 tower registered on MahaRERA.

When was Shree Datta Samarth registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Datta Samarth was registered on MahaRERA on 8 May 2019. GharKundli did not find a title report on the land on file there.

Does Shree Datta Samarth have any legal issues or court cases?

No court cases are listed for Shree Datta Samarth on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shree Datta Samarth?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NITIN VASANTRAO KADAM.