by SAI SIDDHI BUILDERS AND DEVLOPERS · Kodoli, Satara

Possession date of SAI NAGARI: 30 October 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700027475, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAI NAGARI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI NAGARI has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAI NAGARI’s extension records on MahaRERA (P52700027475), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI NAGARI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700027475
Status
Registered and active
Builder
SAI SIDDHI BUILDERS AND DEVLOPERS
Location
Kodoli, Satara · 415004
Project type
Others
Registered on
11 Dec 2020
Completion date at registration
June 2027
Latest completion date
October 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
155
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAI NAGARI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING0%0%0%0%
B WING0%0%0%0%
C WING100%100%100%100%
D WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI NAGARI every month.

SAI NAGARI: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (5 floors) · B WING (5 floors) · C WING (5 floors) · D WING (5 floors)
  • Land: 3,279 sq m (about 0.8 acres) · sanctioned built-up 8,013 sq m · recreational space 407 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI NAGARI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI NAGARI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI NAGARI

What is the possession date of SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI NAGARI in Kodoli, Satara is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAI NAGARI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI NAGARI's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI NAGARI in Kodoli, Satara is P52700027475.

Is SAI NAGARI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI is registered as P52700027475 and its status is "Registered and active".

What is the construction status of SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does SAI NAGARI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI NAGARI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI is registered on MahaRERA as P52700027475, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI NAGARI's possession date changes?

The latest dates are on SAI NAGARI's MahaRERA page (P52700027475). GharKundli's Kundli Watch sends a free WhatsApp update on SAI NAGARI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI NAGARI have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI has 4 buildings filed: A WING with 5 floors; B WING with 5 floors; C WING with 5 floors; D WING with 5 floors.

How big is the land of SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI stands on 3,279 sq m of land (about 0.8 acres), with 8,013 sq m of sanctioned built-up area and 407 sq m of recreational open space.

Where can I read reviews of SAI NAGARI?

Google Maps has reviews of SAI NAGARI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI NAGARI?

SAI NAGARI by SAI SIDDHI BUILDERS AND DEVLOPERS is in Kodoli, Satara (pincode 415004), Maharashtra, and is registered on MahaRERA as P52700027475, per GharKundli's check of MahaRERA records.

How many homes are in SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI has 155 homes in 4 towers registered on MahaRERA.

When was SAI NAGARI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI NAGARI was registered on MahaRERA on 11 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI NAGARI?

No court cases are listed for SAI NAGARI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI NAGARI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI SIDDHI BUILDERS AND DEVLOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Satara →

Other projects in pincode 415004

All 19 projects in Kodoli (415004) →

Other projects by SAI SIDDHI BUILDERS AND DEVLOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.