GAJANAN HEIGHTS

by AMIT DHANAJI PAWAR · Banawadi, SataraAlso near Vidyanagar Karad, Yashvantnagar

Possession: GAJANAN HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52700032219. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GAJANAN HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAJANAN HEIGHTS has moved

  1. 2 October 2022

    Completion date given when the project was registered

  2. 2 October 2023

    Extended at the builder's request (MahaRERA application EXT52700013615)

    Reason the builder gave MahaRERA: “COVID AND OTHER ECONOMICAL AND CUSTOMER PROBLEM”

Source: GAJANAN HEIGHTS’s extension records on MahaRERA (P52700032219), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAJANAN HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700032219
Status
Completed
Builder
AMIT DHANAJI PAWAR
Location
Banawadi, Satara · 415124
Project type
Residential / Group Housing
Registered on
15 Dec 2021
Completion date at registration
October 2022
Latest completion date
October 2023
Delay so far
12 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GAJANAN HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GAJANAN HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAJANAN HEIGHTS every month.

GAJANAN HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: GAJANAN HEIGHTS (6 floors)
  • Land: 359 sq m (about 0.1 acres) · sanctioned built-up 630 sq m
  • Boundaries filed include: LAY OUT 9 METER ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GAJANAN HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAJANAN HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAJANAN HEIGHTS

What is the possession date of GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GAJANAN HEIGHTS in Banawadi, Satara is 2 October 2023 — 12 months later than 2 October 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GAJANAN HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAJANAN HEIGHTS's builder has filed on MahaRERA, the official one, is 2 October 2023, already 12 months later than the 2 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GAJANAN HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 2 October 2023, giving the reason "COVID AND OTHER ECONOMICAL AND CUSTOMER PROBLEM".

What is the RERA number of GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GAJANAN HEIGHTS in Banawadi, Satara is P52700032219.

Is GAJANAN HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS is registered as P52700032219 and its status is "Completed".

What is the construction status of GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on GAJANAN HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GAJANAN HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GAJANAN HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS is registered on MahaRERA as P52700032219, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAJANAN HEIGHTS's possession date changes?

The latest dates are on GAJANAN HEIGHTS's MahaRERA page (P52700032219). GharKundli's Kundli Watch sends a free WhatsApp update on GAJANAN HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAJANAN HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS has one building filed: GAJANAN HEIGHTS with 6 floors.

How big is the land of GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS stands on 359 sq m of land (about 0.1 acres), with 630 sq m of sanctioned built-up area.

Where can I read reviews of GAJANAN HEIGHTS?

Google Maps has reviews of GAJANAN HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAJANAN HEIGHTS?

GAJANAN HEIGHTS by AMIT DHANAJI PAWAR is in Banawadi, Satara (pincode 415124), near Vidyanagar Karad, Yashvantnagar, Maharashtra, and is registered on MahaRERA as P52700032219, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAY OUT 9 METER ROAD.

How many homes are in GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS has 16 homes in 1 tower registered on MahaRERA.

When was GAJANAN HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GAJANAN HEIGHTS was registered on MahaRERA on 15 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on GAJANAN HEIGHTS?

No court cases are listed for GAJANAN HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GAJANAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AMIT DHANAJI PAWAR.